13 Oct 2026 · 13m · 7 chapters

The episode discusses the “staggering costs” of building a single AI data center, from land and engineering power to chips and copper, and how those costs have risen due to supply/demand bottlenecks. It frames Meta, Amazon, Microsoft, and Alphabet as spending about $750B in CapEx, with research suggesting ~$1.7T next year.
chip and server components cost more; chip plants take years and can’t scale fast enough; raw-commodity bottlenecks affect everything (steel, cement, copper, natural gas turbines, transformers).
paying ~$30,000 for a couple-square-inch chip; 72 chips per server; data centers spending ~20–40% of energy on cooling; “powered land” (e.g., Tract Capital securing 30,000+ acres) because electricity generation is constrained.
Lynn Duan (Bloomberg News managing editor of technology; previously oversaw energy and commodities team) and Ian King (Bloomberg News U.S. semiconductor reporter).
Written by AI. May contain mistakes.
Explore the staggering costs associated with building AI data centers.
“Some people treat ChatGPT like some kind of smart search engine, and some use it to get work done.”
Explore the staggering costs associated with building AI data centers.
“We want to get to one of the most read stories on the Bloomberg Terminal today.”
Discuss the various components contributing to the rising costs of data centers.
“It's enough to cut$5 ,500 in a check for every household in the U.S.”
Examine the importance and costs of chips used in data centers.
“We can't build enough giant chip plants to feed these data centers with enough components.”
Analyze the cyclical nature of the semiconductor market and its impact on data centers.
“Anybody who tells you that this is going to be different is probably not really understanding how the industry works.”
Discuss the significant power demands of data centers and their implications.
“a company that we have profiled, has secured more than 30 ,000 acres of this kind of powered land just to sell it to data center providers.”
Explore the uncertainties surrounding investments in data centers and the potential AI bubble burst.
“is framed around whether all of this investment is going to be worth it.”

Get the gist, explore an idea or ask about something said.
On Bloomberg Businessweek, what are the key points of this episode?
Automatic transcript. May contain errors.
0:00Carol Massar: Some people treat ChatGPT like some kind of smart search engine, and some use it to get work done. ChatGPT Work is a new way of working in ChatGPT that can take action across your apps and files, stay with a project for hours if needed, and turn a goal into finished work. It's designed to help you move from a chaotic starting point to a reviewable first version. So all the source materials, briefs, and scattered information that you have to grind through to turn into something useful can just become something useful. Put ChatGPT to work on your most ambitious ideas and projects. Get started at ChatGPT.com by selecting Work Mode, available on Plus and Pro plans.
0:42Carol Massar: If you're a business owner, you need a card that can keep up. With the Delta SkyMiles Reserve Business American Express card, everyday purchases transform into miles you can use towards future travel. So business as usual can lead to a well-deserved getaway. And for a limited time, card members can earn 200 ,000 bonus miles, the highest miles offered this year. Whether you're traveling for business or planning your next adventure, now's a great time to make every purchase go further. Apply today at www.delta.com slash podcast. Offer ends November 4th. Minimum spending requirements and terms apply.
1:44Asana, where humans and agents workflow together. Try it at asana.com. That's A-S-A-N-A dot com. Bloomberg Audio Studios. Podcasts. Radio. News. You're listening to Bloomberg Businessweek with Carol Masser and Tim Stenevek on Bloomberg Radio. All right.
2:07Carol Massar: We want to get to one of the most read stories on the Bloomberg Terminal today. It is about the staggering costs of a single AI data center from steel, cement, to chips and copper, to land engineering power and more. There's a lot that goes into the cost of those data centers. And increasingly, all of those things cost a lot more than they used to. Okay, but given how expensive everything is, when you add it all up, it's actually not that difficult to see how Meta, Amazon, Microsoft, and Alphabet are spending a whopping$750 billion on CapEx alone. No. At least when you scroll through this story.
2:42Carol Massar: Right? Yeah. You get it. And I keep thinking about Mandeep's story and research about the spend next year, about$1.7 trillion. And I see this number and you realize how much is really because of these four companies in a big way. Well, Lynn Duan is the byline with an assist from Ian King. Lynn Duan is Bloomberg News' managing editor of technology. She used to be out here in New York. Now she's out there in California. Ian King is Bloomberg News' U.S. semiconductor reporter. They both join us from San Francisco. Lynn, I just love how you opened this story, contextualizing just how big a number$750 billion is.
3:17Can you just lay it out for us? Well, first of all, thanks for having me. I miss you all out there in New York. I'm sorry I have to dial in by Zoom these days. I felt like that$750 billion needed a lot of context. It's just such a massive number, right? As you say, we're talking about heading into the trillion dollar realm next year. And so I thought, how can I wrap people's heads around this? I know GDP of a country. Yes, GDP of all of Ireland, of all of Belgium. It's more than half of what all of the companies in the S &P 500 index spent in total last year. It's enough to cut$5 ,500 in a check for every household in the U.S.
4:06So it's a lot. I mean, I think that the only thing that is comparable to this is the build-out of the U.S. highway system. Otherwise, we have never seen such a build-out of this enormity dollar-wise.
4:19Carol Massar: Ian, let's bring you into this because, as we know, these data centers, they're complicated. There's a lot of moving parts. And a lot of those parts, whether it's power, whether it's semiconductors, increasingly have gone up. And I think a lot of it is just basic supply and demand. There's just so much demand that the prices of these things have gone up, and it just costs a lot to make them all happen. Yeah, that's absolutely right. I mean, you've got to think about it. The main component in these buildings is something that's like a couple of square inches. And you're paying$30 ,000 for one of those.
4:52It's using as much electricity as several large flat screen televisions, and you're putting 72 of those in a server. So imagine the expense of just putting one server there, of feeding it with power for a year. And obviously, there's more than just one server in these machines, in these giant data centers, as Lynn's story really, really shows very well. Ian, I'm wondering, though, if this stuff gets cheaper. And remember, we have the Oracle force majeure that we saw just a couple of weeks ago. But look, as we're reminded all the time, the cure for high prices is high prices. If you have a lot of people going after something, then more people come off the sidelines and try to give the market those things that are expensive because they want in on the action.
5:41Can this stuff get cheaper or is this different? Well, the other$30 billion question here is chip plants, right, cost even more than these things. So you don't just rock up and say, oh, OK, I'll build a chip factory. You can't do that either. It's, you know, two years to build a chip plant, and we need multiple chip plants to meet the amount of demand that we've got right now. So the problem isn't just a, you know, we can't build enough data centers. We can't build enough giant chip plants to feed these data centers with enough components. So it's kind of a compounding issue. And there's no real end in sight if demand stays at the current levels.
6:20We're just not going to be able to meet it.
6:21Carol Massar: So let's go to, we want to bring up a pie chart as part of this story. Just give everybody an idea. And I'll spell it out for those who are listening on radio as well. But it is a pie chart. And a big chunk of that pie, which is in yellow for those who are watching right now, Now, 17.1 billion will go to chips and servers. That's the estimate that we've come up with here at Bloomberg. Then you've got about 2.8 billion in contingency planning. 2.2 billion goes to other. 2.4 billion is construction. About 3 billion goes to power. 1.7 billion goes to cooling. Ian, it is disproportionately, as you just laid out, semiconductors, right?
7:02Carol Massar: That's what makes it all sing, these data centers, and creates the AI that people are consuming at this point. We go back to you, Tim and I, time and time again, that you remind us that there are cycles. And again, you do have demand, as Tim said, then you have build, then you have excess capacity, and then you have some fallout. Is this cycle likely to be like any other, or no? Just maybe the duration of the cycle could be different. We've never seen anything of the magnitude of this current cycle. You've got one company that's heading to$100 billion per quarter in sales at a 75 % gross margin.
7:43You've got memory chip companies that have demand for the next several years already locked up. So there's never been anything like this in terms of the magnitude, in terms of how long it'll go. If I knew that, I wouldn't be sat here talking to you.
7:57Carol Massar: But you do remind us that it's cyclical, right? There's nothing to make you think that this is going to be any different this time around. I mean, the industry has always, always overbuilt, right? We've always had this lag between supply and demand. We've never been able to match it. Anybody who tells you that this is going to be different is probably not really understanding how the industry works. It's just a case of when the pendulum swings back. Lynn, I want to bring you back in here. We're talking to Lynn Duan. She's Bloomberg News Managing Editor of Technology at Bloomberg. And also Ian King, Bloomberg News U.S.
8:33semiconductor reporter. Both join us from San Francisco. The story we're talking about is the staggering cost of a single data center from land to chips. I encourage everybody to read this on the terminal or read it at Bloomberg.com and just play with the interactive element a little bit because it just shows how these costs add up. and there are a lot of costs in there that you wouldn't necessarily associate with this type of capex. And that's where I want to send it to you, Lynn. What was the most surprising element of cost that goes into a data center from your research that you found? Well, I just want to double down on what Ian said about the cyclical nature of chips.
9:12And that way, I used to oversee the energy and commodities team at Bloomberg. And in that way, chips have very much become like any other commodity. Every commodity market and energy market is cyclical. You have these cycles of oversupply and then shortage of supply. And what really stood out to me in doing this deep dive with Cushman and Wakefield and Bloomberg Intelligence is that there is this bottleneck across all raw commodities, not just chips, but natural gas turbines and power transformers and concrete and cement and copper and steel. The inflationary nature of this boom is across the board.
9:55I think that was probably the most staggering revelation to me is it's not just about the chips. It's about the costs of all of these things soaring. And then suddenly you understand why some of these data centers are running into huge problems and potential delays.
10:09Carol Massar: This is why though, Lynn, when we talk about delays, those that purchase land are entities that is already powered, the powered land, like it's something that we've kind of started to learn about too in conversations with real estate folks, that is in demand because you've already got access. Right. And we're not even talking about power demand, it's a powered land itself soaring in costs. You know, we have firms that are building themselves as sort of the arbitrage, the supplier of powered land, like Tract Capital, a company that we have profiled, has secured more than 30 ,000 acres of this kind of powered land just to sell it to data center providers.
10:54There is one basic reason why powered land is taking off in this way, and that is because there is not enough electricity generation in this world to power all of the AI data centers that are being proposed and built right now. And powered land means that they are already either connected to the grid or already have a power source contracted out.
11:15Carol Massar: Hey, one of the things I wanted to ask you, because Ian, Lynn brought up power. Obviously, that's a big part of all of this, and that I feel like over the last couple of years, we've increasingly, when we talk AI, we talk about the power demand and needed. Data centers, in this story, data centers spend a good 20 % to 40 % of their energy simply cooling the equipment housed within and those built to power the development and training of AI systems require more cooling than most. Chips, though, Ian, are getting better, right? Smarter, faster, but I assume they're getting more productive. Hopefully, that power demand will be reduced, but that's part of what we're trying to see in terms of the development of more advanced chips?
11:54Carol Massar: That's part of it? What we're seeing is a computing problem that is, in effect, inflationary. It's inflationary in cost for all the reasons that we talked about, but it's also inflationary in terms of the power produced. Yes, they are more efficient. Yes, they do more work. But guess what? The more work they do, the more useful they become. And AI is a problem that fundamentally, the more data you throw at it, the better the software becomes. So there's an incentive to use more chips, more powerful chips, chips that can move around more data. So you've got like your laptop, right? 20 watts, right?
12:28That's quite a bit of power for something quite small. But we're talking individual chips here that are using more than 1 ,000 watts of electricity. Why are we doing that? That sounds crazy. We're doing it because it makes sense if you want to create these effective AI systems. So for the time being, unless there's a massive breakthrough in the fundamental mathematics, we're going to continue to throw more power, more powerful chips that require more energy at this issue. Ian, you have covered, I ask you this all the time, but I mean, each time we interview you, it feels like things are even more intense or more extreme than they were the last time.
13:06So given your decades long history of covering this, where you think we are in this cycle, does it match anything that you've ever seen in this industry? Absolutely not. No. I mean, people have tried to compare it to the dot-com era, people who tried to compare it to when PCs took over from mainframes. And, you know, to this, we've never seen anything to this extent. And you just need to look at the actual numbers that the companies are putting up there. Even valuations can't keep up with them. Even some of, I mean, Hocktan this weekend, the CEO of Broadcom, called like casino type investing going on.
13:44But even with that, some of these companies are relatively cheap still on a price to earnings ratio.
13:50Carol Massar: Lynn just got about 25 seconds here. Anybody that, as you were putting this together, saying, wait, boom, bust, bubble, any of that come up? I mean, there's a reason why the very end of the story is framed around whether all of this investment is going to be worth it. I think that is a huge question mark. And much like Ian, if I knew the answer to that, I wouldn't be on television with you. I will say I had a Bloomberg reader just ask a question, which is, if we are consuming all these resources with data centers, why don't we just allow human beings to consume these resources instead? That speaks to the boom and bust.
14:23We'll see what happens. Yeah, Michael Burry has done a lot about this too, about the eventual burst of the AI bubble.
14:30Carol Massar: Folks, thank you so much. Our thanks to Linda Wan, Bloomberg News Managing Editor of Tech, Ian King, Bloomberg News, U.S. Semiconductor Reporter.
14:41This is Robert Smith from Business History. If you're listening to this, there's a good chance you're a small business owner. And like every small business owner, you started with a dream to do what you love and watch it grow. What you probably didn't dream about? Keeping up with cyber threats. That's where MasterCard can help with access to tools that help identify cyber threats to better protect your business. Building your dream business? Priceless. For cybersecurity in a changing world, there's MasterCard.
15:08Carol Massar: Learn more at MasterCard.com slash small business. Artificial intelligence is transforming how businesses operate. But what will it take to build a truly autonomous AI enterprise? On October 28th in Boston, join the Bloomberg Tech Briefing, building the agentic enterprise to hear business and technology leaders explore the strategies needed to build cyber resiliency and secure trusted AI systems for the agentic AI era. Proudly sponsored by HPE. Learn more and register at bloomberglive.com slash bloombergtechbriefing.
The people, companies and trends shaping the global economy. Watch Carol and Tim LIVE every day on YouTube: http://bit.ly/3vTiACF
Roughly $750 billion. That’s how much Meta Platforms Inc., Amazon.com Inc., Microsoft Corp. and Google owner Alphabet Inc. are expected to devote to capital expenditures this year alone.
That’s more than the entire gross domestic product of Ireland or Belgium. More than half of what all of the companies in the S&P 500 Index spent in total last year. Enough to cut a $5,500 check for every household in the US.
Ian King, Bloomberg News US Semiconductor Reporter & Lynn Doan, Bloomberg News Managing Editor for Technology, join Businessweek Daily to break down the true cost of a single data center.
See omnystudio.com/listener for privacy information.