27 Oct 2026 · 1h 15m · 28 chapters

Whether the US can build enough interregional transmission (especially long-distance HVDC) to keep pace with rising electricity demand driven by data centers/AI and other load growth, and what reforms could speed timelines and improve financing, cost allocation, and market recognition of transmission benefits.
Written by AI. May contain mistakes.
Discussion on the urgency of addressing electric demand and the need for reforms.
“What I would say is if the bill doesn't pass, the work continues at the regional and the state level and with FERC.”
Exploration of Grid United's efforts to improve transmission networks.
“Madeleine Gould-Loughlin is the Director of Regulatory Affairs at Grid United.”
Discussion on local landowner opposition and strategies for community buy-in.
“interregional transmission, but it's really come down to, you know, where the rubber hits the road is let's actually build some of these projects.”
How engaging with local communities benefits transmission projects.
“There are so many people involved in these projects.”
Challenges and strategies related to regulations and cost allocation in transmission projects.
“or to the local communities or even sometimes to entire states as a result of this new infrastructure being built.”
What capacity value means for grid operators and its implications for transmission.
“There's a lot of other issues around grid planning and around cost allocation and who pays for the line to get built.”
Discussion on HVDC transmission benefits and the challenges of resource allocation.
“Interregional transmission is one of the lowest cost ways to meet that.”
Exploring the future implications of transmission projects and HVDC development.
“all from having transmission capacity running into your grid.”
Learn how transmission value is accredited and its implications for utility partnerships.
“But when it's specifically a participant funded line, having that accredited capacity flow back to the specific funders.”
Discover the hurdles faced in building transmission projects and the importance of funding and permitting.
“but really needing to see certainty and kind of clarity on these rule changes by the middle of next year if this is going to impact the early 2030s COD projects.”
Examine how potential permitting reforms could accelerate transmission project timelines.
“And I think a large piece of that is the momentum and the large diverse group of stakeholders that are invested in the project because we're speaking to the benefits that each of those group is receiving.”
Meet Jenny Chen and learn about the Regulatory Assistance Project's mission and focus areas.
“But, you know, we're not crossing our fingers.”
Explore the critical need for investment in transmission capacity to meet rising power demand.
“So it's a very broad-based agreement that more investment in transmission is needed.”
Learn about hybrid models for transmission development that combine regulatory and market approaches.
“And some of the incentive here for developers is to propose the most valuable projects possible because they all want to meet the cap.”
Explore the complexities of cost allocation in the U.S. transmission model and how it compares to the UK.
“to make the most of their assets and in doing so they're increasing the utilization, they're providing more benefits and if you're using your assets smartly, more efficiently, you don't have to build as much.”
Discuss the urgent need for innovative solutions in the power sector to meet rising demand.
“Some folks who don't think about transmission on a day-to-day basis probably find this topic a little bit complicated.”
Discusses the supply constraint issues in the energy sector, emphasizing the need for more electricity supply amid rising demand.
“And yet it's not often getting the power that it needs for a variety of reasons.”
Explores the challenges of interconnection queues for renewable energy projects and the impact of cost uncertainty on project viability.
“bring that speed to power, meet this moment.”
Examines the importance of cost certainty in interconnection processes and discusses potential solutions to improve project planning.
“And there's sort of a criticism, I think, from the regulators, because they're like, what are you doing?”
Analyzes regional transmission planning initiatives and discusses their implications for market efficiency and cost reduction.
“Yeah, I think there are two really big pieces.”
Discusses the ongoing debate about market design in energy systems, focusing on the balance between affordability and demand.
“And I wonder if that then relates to one of the other issues that people talk about a lot in terms of difficulties with getting new supply into the grid, which is market design and market structure.”
Exploration of the complexities and issues surrounding utility interconnection processes and competition.
“And I do wonder, something I often think about when I think about the debate around market design is if you take the 30 ,000 feet view, we're in an environment of strongly growing demand and concern about affordability.”
Discussion on the importance of permitting reform to enhance supply on the grid amidst growing demand.
“I'm interested in getting your views on permitting reform.”
Insights into the conversations and efforts for interregional transmission planning and its significance.
“I try to never sink into despair, for starters.”
Speculation on the future of the grid based on potential legislative changes and ongoing regional efforts.
“and MISO, the mid-continent ISO, on what's called the Coordinated System Plan, the CSP, and that is really their version of inter-regional transmission planning.”
Discussion on the implications of pending legislation on grid development.
“So those things will change if that bill passes.”
Exploration of the risks associated with not passing the bill.
“You know, China's the one that, you know, obviously comes to mind, and we are well behind in modernizing our grid.”
Optimism about the bipartisan nature of recent negotiations on energy policy.
“Certainly a critical moment, a very, very important time we're in right now, even just in the next, as you say, couple of months or so?”

Get the gist, explore an idea or ask about something said.
On Energy Gang, what are the key points of this episode?
Automatic transcript. May contain errors.
0:00What I would say is if the bill doesn't pass, the work continues at the regional and the state level and with FERC. The problem is we don't we're not able to continue at the pace we know we need to to meet growing electric demand. Right now, we are kind of stumbling forward. We're moving forward, but we're not running. If this bill passes, it puts us at a run and we have a lot of catching up to do. You have to kind of attack it from all of those angles in order to condense the timeline. But we've seen real actionable progress on this. We received a final environmental impact statement from the Department of Energy in just 21 months, when that typically takes three to five years.
0:36We're at a point where, you know, if we really want to meet the demand that, you know, our government feels is necessary to drive the American economy, that, you know, we do have to make some reforms in order to meet that demand both efficiently, affordably, reliably, and, you know, hopefully sustainably because we're in this for the long run. Today, it matters more than ever for all the reasons we're just talking about. Like, this is the moment we all need to meet. And the supply that's needed to meet that demand is stuck. It's stuck in the queues. And it's also stuck because we are still not building the amount of regional transmission that's needed to connect those new resources.
1:19Katherine Hamilton: This episode is brought to you by ACOR, the leading nonprofit organization uniquely operating at the intersection of energy affordability, reliability, and clean energy deployment. ACOR is focused on stabilizing energy prices, strengthening the electric grid, and driving investment in cost-effective technologies to ensure that clean energy delivers for people, businesses, and the US economy.
1:46Katherine Hamilton: Hello and welcome to The Energy Gang, a discussion show from Wood Mackenzie about the fast-changing world of energy. I'm Ed Crooks, and this is the first in a series of two special episodes recorded at the ACOR Grid Forum in Washington, D.C., looking at the strategies and technologies that are shaping the future of the grid. On this show, we're going to be talking about why it's so hard to get new transmission infrastructure built, particularly in the United States, and what can be done to expedite badly needed investment in the grid. To start, I spoke to somebody who's right at the sharp end of this issue, trying to build new transmission.
2:18Katherine Hamilton: Madeleine Gould-Loughlin is the Director of Regulatory Affairs at Grid United. And I asked her first what the company is working on. So Grid United, we're an independent transmission development company. We primarily focus on long distance HVDC interregional transmission, connecting the seams, the different grids. So the Western and Eastern interconnections. We have not done a very good job in this country of building those connections. and as we focus on extreme weather events, reliability, resiliency, these exact type of connections between seams become very compelling and valuable. Right. So as you say, there is a very broad consensus that in the United States, there is an urgent need for more transmission to get built, as you say, to improve resilience and reliability for affordability reasons and above all, of course, to meet rising demand for power.
3:13Katherine Hamilton: this new world that we're in because of data centers and AI, but also other drivers of growing electricity demand. So you at Grid United are setting out to meet that need for more transmission. What are the big issues you face as you're trying to build out new transmission projects? Yeah, so as you mentioned, you know, there's been this broad consensus on the value of interregional transmission, but it's really come down to, you know, where the rubber hits the road is let's actually build some of these projects. Let's get them over the finish line. They often have very long development cycles, have struggle kind of getting over the financing and construction hurdles.
3:54And so what we've set out to do at Grid United, in particular with our North Plains Connector project, a 420-mile, 3 ,000-megawatt line connecting SPP, MISO, and the Western Interconnection, obviously a very ambitious project. and we've looked to, okay, what are the kind of main things that are inhibiting these types of projects from moving forward? And a big one of those is opposition. And we've flipped the development cycle on its head a little bit and started with the local landowner communities, gotten their buy-in, and then allowed those local landowners and communities to serve as the glue as we kind of zoom out and bring in additional stakeholders, whether it's the grid operators, the state utility commissions.
4:43There are so many people involved in these projects. But really starting with the local landowners, getting their support has proved valuable in kind of getting the support that you need to keep things going over a long development cycle. Right.
4:58Katherine Hamilton: And that local opposition, in particular, what has just been about landowners not wanting power lines running across their land and them not really seeing any benefit to them or to the local communities or even sometimes to entire states as a result of this new infrastructure being built. Yeah. And I think, you know, viewing them as true partners, you know, our engineering team might not have appreciated the, you know, hundreds of reroutes that were made, but accommodating the local needs, really viewing them as partners in this process rather than going to a commission first in kind of introducing a line to a community.
5:33Katherine Hamilton: And what does that mean then seeing landowners as partners? What actual concrete benefits do they get? Our typical approach with kind of local funding and granting is we find an organization that disperses the funds. So, you know, we're not the experts in the local community. So they're able to, you know, fund investments in the school, in the local roads, in the fire department, really concrete and tangible benefits. And then And obviously you have those who are actually hosting the lines and receiving more of direct payments. But that really has translated into momentum for the project and has allowed us to bring on other partners, like our utility partners, who see the communities really want this investment.
6:18They're interested in it. This is something, this is a really compelling project. And so that's allowed us then to translate that into utilities who are interested in owning and operating the project.
6:29Katherine Hamilton: and there's always been a lot of uh debate around issues around eminent domain and the issues with um if there is one particular landowner who won't let the line cross their land the problems that that can create is that still an issue have you got ways to get around that um so this is you know with our npc project this is all voluntary uh landowner commitment And again, I think that landowners can feel when there's a sincere relationship and approach with the company. And so we've taken the time up front to make that investment and ultimately seeing that translate into meaningful impact for the project.
7:13Katherine Hamilton: Right. So that's really interesting then. And as you say, it does sound like a real step forward in terms of dealing with one of the obstacles to getting a new transmission built. It's far from the only obstacle, right? There's a lot of other issues around grid planning and around cost allocation and who pays for the line to get built. What are you doing about those? Yeah. So one of the main things that we're focused on now, you know, NPC, we have a consortium of utility partners, utilities from the Pacific Northwest all the way to kind of local utilities in North Dakota and Montana. and they're very interested in, you know, they have resource adequacy needs that they need to meet and they're evaluating all of the different options to meet that.
8:00And so as these utilities are faced with investment decisions, they're looking at what's the lowest cost way that I can meet the needs of my customers in a way that delivers this reliable, resilient power. Interregional transmission is one of the lowest cost ways to meet that. However, there are not current market rules that allow them to capture that direct capacity benefit. So when they're going to their regulators and asking to participate in this type of project, they need to connect the capacity value to the investment they're making. Otherwise, they're going to have to make that investment twice in order to actually meet their resource adequacy needs.
8:40Right.
8:40Katherine Hamilton: So that sounds very interesting. I just want to unpack that a little bit. So when you talk about capacity value then, so what does that represent? Yeah, so capacity accreditation, that's how grid operators decide how much a resource counts towards keeping the lights on during the toughest hours. So think of it like a reliability score. Gas plants, batteries, wind farms, they'll receive this type of accreditation. And demand is growing extremely fast. and the rules were created for kind of a grid of the past. So as we evolve, as the grid operators' needs evolve, there's a need to reexamine what types of resources receive this accredited capacity.
9:24And HVDC transmission in particular and the resources that are enabled, the power that's able to flow over these lines, delivers real tangible capacity benefits to regions, particularly over long distances as you have uncorrelated, you know load and and generation profiles right so just to be clear about that then if you are
9:47Katherine Hamilton: a grid operator then you're looking for capacity to as you say make sure you can keep the lights on and you would calculate that on the basis of generation resources that are available to you and you'd have a certain capacity value for gas and one for coal and one for solar and wind and so on. But you're saying you don't get any benefit at all, or you don't kind of record any benefit at all from having transmission capacity running into your grid. Correct. And in particular for interregional transmission, and part of that is due to, you know, grid operators are typically focused on modeling their individual system.
10:26And in order to see this, to capture this value, you're having to model systems simultaneously. So that's something that we've done, you know, know, as an interregional transmission developer, we've spent a lot of time working on this, you know, loss of load expectation modeling to really understand what are the value of these lines and how do you capture that? Right.
10:48Katherine Hamilton: So to think about that in practical terms and in terms of one of your projects then, I mean, what's, give me an example then of how that might operate in a specific grid for a specific project. Yeah. So our North Plains Connector project, it's 3000 megawatts total, but it splits off 1500 megawatts into MISO and 1500 megawatts into SPP. And because it's a bi-directional line, oftentimes the capacity values that you're seeing are, you know, higher. So it might be very close to that 3000 megawatts total or even higher because the power can flow in in both directions. And is there a particular kind of resource base that that's connecting to then?
11:27Katherine Hamilton: What's the source of that power going to be? Yeah, so this is connected to, you know, large pools of resources. This is not specifically what you might call a gen tie or a generator tie. So this isn't tying into one specific resource. And that's one of the real strengths of these types of interregional lines. You can tap into a whole range of diverse resources that peak at different times. And oftentimes one of the most compelling pieces is actually the load diversity as opposed to just the generation diversity. When you're going over a span of 400 miles, you're capturing, you know, these regions are peaking in terms of their, you know, whether it's rush hour or, you know, wake up time, going to bed.
12:12And so it's oftentimes that load profile that's even more diverse than the generation.
12:20Katherine Hamilton: Right. So how do you get grid operators to recognize the benefit of that then? What needs to change? Yeah, so we are working, you know, grid operators currently accredit capacity for resources. We are working with them to expand the rules or oftentimes just, you know, adding an additional resource class or resource type so that transmission can be considered. And, you know, this is a challenge with transmission development timelines. These are lengthy projects, and oftentimes people ask, why now? Utilities, as I mentioned earlier, are making these investment decisions now. And those investment decisions are based on the market rules of today.
13:03So the investment signals need to be sent that there will be a way to capture this capacity value. and again translating that for their regulators that this is a way that they can meet their resource adequacy needs.
13:16Katherine Hamilton: Would there not be a way, rather than recognizing the capacity value of the transmission specifically, to recognize the value of the generation resources at the other end of the line? That is oftentimes in practice how it works. You know, MISO is currently going through this process. They're looking at, you know, resources enabled by HVDC, whether that's through a pool, whether that's through a specific generation source. Right. But you're saying, well, that's not an adequate. That's currently in process. That would be an adequate substitute. Yeah, it's almost a proxy for the line itself of the power that's flowing.
13:56Katherine Hamilton: And when we talk about recognizing the value, what does that mean in practical terms? Do you actually get paid for that? Yeah. So, you know, what we've looked at is when you have transmission that's, you know, these large long term portfolios where the whole region is paying for it, a way that you could accredit that value is simply, you know, broadly lowering the reserve margin that's required by by all folks in the footprint. But when it's specifically a participant funded line, having that accredited capacity flow back to the specific funders. So that could be lowering their individual reserve margin.
14:35That could be allowing them, you know, the specific capacity value that if there's an auction that they can, you know, bid in day ahead markets.
14:44Katherine Hamilton: Right. So and you're saying that is something which is coming. Is that going to make a difference? And if so, how soon? Yeah, so we're working in MISO, SPP in the West right now in regards to our North Plains Connector Project, but really all on behalf of all HVDC transmission. We are looking to see rules in MISO and SPP by the end of this year, early next year. Those kind of have to work their way through the stakeholder groups and then oftentimes require a FERC filing as there's tariff implications. but really needing to see certainty and kind of clarity on these rule changes by the middle of next year if this is going to impact the early 2030s COD projects.
15:28Right.
15:29Katherine Hamilton: So taking a step back then to this question about not enough transmission infrastructure being built in the United States, how does this actually help that? I mean, I can see why if you're a transmission developer, this is good for you because it enables you to capture more of the value that you're creating. but is that actually going to mean that projects can be delivered faster? Yeah. So, you know, one of the ways that we've tried to work on these interregional projects is finding different utility partners. So with our North Plains project, you know, we're up to a consortium of nine different utility partners and piecing together, you know, a 3000 megawatt project oftentimes requires, you know, a couple hundred megawatts from multiple participating utilities.
16:14And one of the final hurdles in building these projects really is the financing piece. And so as, again, like I mentioned, their utilities are tasked with making these investment decisions. And this all flows into, you know, the permitting for the project and kind of the general momentum and progress that you can make. The utility partners having confidence in making these types of investment decisions and signaling their interest in developing more interregional projects that are more efficient for their rate payers. It's more efficient to make these kind of interregional connections rather than building generation that might be needed one or two peak days a year.
16:59So I think you've really seen an increased focus on an interregional transmission as load growth and affordability challenges kind of go hand in hand. And there's more of a focus on how can we use our existing resources that we have today? How can we tap into this uncorrelated load and generation diversity? And yeah, oftentimes that kind of requires cobbling together a few different folks to participate in a project at a scale that makes an impact.
17:30Katherine Hamilton: So as you say, there are some changes which are positive, as you would see them happening in some parts of the country. The systems are moving to some degree in the direction you'd like them to move. When might we see positive results from this? Again, going back to these questions about timing, I noticed there was a new power line just coming to service from Quebec down to New York. That one, I think, took 16 years from project launch to commercial operations date. That's not at all untypical. That's actually perhaps even on the short side for some of these projects. Some have taken longer than 20 years to get into service.
18:17Katherine Hamilton: Do you think you can significantly reduce those times? I do. And I think, again, it's a combination of all the things we've been talking about. So it's that landowner first approach, condensing that timeline, which feeds into permitting, and then also piecing together, how are you going to finance and pay for this? And where does the value flow? And you have to kind of attack it from all of those angles in order to condense the timeline. But we've seen real actionable progress on this. You know, we received a final environmental impact statement from the Department of Energy in just 21 months when that typically takes three to five years.
18:52And I think a large piece of that is the momentum and the large diverse group of stakeholders that are invested in the project because we're speaking to the benefits that each of those group is receiving.
19:05Katherine Hamilton: And what about permitting reform then? Obviously, a lot of excitement around the legislation that was launched earlier this year. Power transmission, one very specific focus of that. The legislation, if it passes into law, is supposed to make building new transmission lines significantly easier. Are you building much hope and expectation on that? I mean, do you think something along those lines will pass? And if it does, would it really make a big difference? I mean, bipartisan permitting reform is something that we've been following as a company, investing time and energy in. One of the things with our existing portfolio of projects, those are very much under the assumption of a status quo environment.
19:54These deals take time and it will take time in the implementation phase as well. So what we're working on right now is, OK, if all things remain the same, how do we condense the timeline? You know, obviously in a future scenario where there is permitting reform, that would help our cause. And that would build more, hopefully build more interregional transmission.
20:18Katherine Hamilton: So if you do get reform, then great. It will make it possible for you to do more. But you're not relying on that. You're doing what you need to do to make progress faster, even with the system we have today. Correct. And I mean, I think you see the needs of the system in the next three to five years. And we've been in this business now for, you know, a little over five years. So some of these projects are very, you know, near starting of construction and financing. And so those were all, you know, conceived of. And those projects started their development long before much of this load growth was seen.
21:01But now, yeah, we're trying to get to the finish line and permitting reform would be a welcome thing for us to see. But, you know, we're not crossing our fingers.
21:16Katherine Hamilton: Madeleine Gould-Lachlan, thank you very much. Next, I sat down with Jenny Chen, who's a principal of the Regulatory Assistance Project, also known as RAP. I talked to her about her ideas for regulatory reform to support investment into regional transmission. I asked her first about the Regulatory Assistance Project and its perspective on grid development. RAP is a non-profit. We have offices globally. And what we do is we come up with solutions options. We come from a very objective, research-based perspective. And the idea is to provide decision makers with the pros and cons of different options to the problems that they're facing.
21:56Katherine Hamilton: Right. And specifically then, as that relates to energy and to the grid, what is your work on that? So I personally focus on the bulk power system. So these are grids that encompass a lot of utility territories and how these utilities might be able to share resources, jointly plan infrastructure, so that we can get the most out of the grid as a region and benefit from the economies of scale. Some of these grids also operate power markets, regional power markets, that enable us to share electricity in real time. So ensuring that these markets and infrastructure could bring on lower costs, lower emissions resources is something that we focus on at RAP.
22:44Right.
22:44Katherine Hamilton: Got it. So I want to talk about investment in new grid infrastructure, new transmission in particular. It seems very clear that there is a need for more transmission capacity in the United States to strengthen resilience and reliability, to improve affordability, to give people access to the lowest cost resources, and in particular to meet growing demand. because we're in this condition now of strong growth in power demand to a degree that the country hasn't seen for decades. So it's a very broad-based agreement that more investment in transmission is needed. However, it still seems to be very, very hard to get new transmission built.
23:34Katherine Hamilton: From your perspective, and thinking about the regulatory regime around transmission, what could be done to expedite investment in that capacity to get more of it built? So there are definitely a lot of issues around transmission build out. And I would say that the type of transmission that we would like to see more of are the longer line transmission projects. There is a fair amount of local upgrades, shorter transmission projects that are within utility territories. And some of these projects that could be rate-based, for example, through utilities, tend to have, you know, they tend to have an easier time of being built.
24:14So the projects that we would love to see come online tend to connect regions where you might have a lot more lower cost, cleaner energy potential, you know, lower emissions, electricity that's at lower cost to generate essentially. And they might not be in the same location as like where you might have a large data center, energy intensive manufacturing, or just population centers. So the issue is that when we look at the planning process, it comes with a cost allocation process. And a lot of different decision makers in different states must agree on how they're going to allocate costs between their customers.
25:02So this might be between states. It might be between regional transmission organizations and independent system operators. Now, on the other hand, that's one model of transmission build out. And the main issue there is cost allocation and ensuring that these projects get through the planning process. There's another model where the developers are independent and they take on all of the risks themselves. So they're not getting the benefit of cost recovery from rate payers. They have to go to the markets, whether they're bilateral or organized markets, and earn revenues based off of what is needed.
25:42The model that we'd love to look at is actually an innovation from Great Britain, and it's a hybrid of the two. And it brings together some of the investment certainty or the revenue certainty that comes with the regulated model, but exposure to the markets and the demand, you know, the pull from demand that comes with the independent or merchant model. Right.
26:08Katherine Hamilton: So how do you make that happen then? When you talk about sort of combining, I guess, the best features you'd want to see of those two models, how can you do that? Yeah, so this model is called floor and cap, where you have a floor and the floor is guaranteed. It's a guaranteed amount that could be roughly about the cost of the total cost of the project, maybe plus a little tiny bit. But the idea is that the project developers are responsible for going to the markets to earn the revenues and to make enough money to support the project. Now, if they don't make enough to meet the floor, there is a guarantee that whoever it is that backs the floor.
26:55So in the case of Great Britain, for example, is the rate payers. The rate payers would be on the hook to pay the amount up to the floor. Now, there's also a cap. So in exchange for supporting a floor, underwriting the floor, the entity that's guaranteeing it has the benefit of earning the revenues that come in that are above the cap. And in Great Britain, no one's had to pay for a floor yet. They've been actually there's been some revenue come through for customers above the cap. So that's good news. And some of the incentive here for developers is to propose the most valuable projects possible because they all want to meet the cap.
27:42And the cap can be set at a level that is higher than what a regulated utility might earn. So in the U.S. it might be, you know, something like a 10 percent return. but the idea is that you want to give them the incentive to make the most of their assets and in doing so they're increasing the utilization, they're providing more benefits and if you're using your assets smartly, more efficiently, you don't have to build as much. So there are multiple benefits for consumers even though it sounds like the utilities are also making more money.
28:23Katherine Hamilton: Yeah, and I'm put like that. Intuitively, it sounds very appealing and kind of like a win-win for both sides. um i do wonder though whether this model would still run into some of the issues that you get with the cost allocation model where essentially different regulators different jurisdictions would argue with each other over who gets what benefits and who has to pay and who has to pay for the floor right isn't that crucially one of the problems with cost allocation at the moment in the United States is where you have inter-regional or inter-market transmission. It's really hard to work out exactly where the benefits are and therefore exactly who should pay the costs.
29:12Katherine Hamilton: And people will argue over that. And nobody wants to pay the costs, obviously, and everyone wants to maximize the benefits. The United Kingdom, or Great Britain to be specific, would seem to be an example of a market where it works because it is one market and one jurisdiction to have a single regulator, which is the British regulator Ofgem, you don't have that in the same way in the US. So is there really an analogy you could draw there? Is that really a model that could be imported into this country? Yeah, so this is definitely an important thing to discuss. In between Great Britain and its neighbors, Great Britain Ofgem still has to negotiate with the regulatory authorities, with France, Norway, Ireland, whoever it is that they're connecting with.
30:05And typically they split the risk of paying for the floor 50-50. So there is this risk allocation that we would have to make if we want to have ratepayers support the floor. So I say that because it doesn't have to be ratepayers who support the floor. It could be any credit worthy entity, theoretically. It could be an infrastructure fund. It could be the transmission facilitation program.
30:33Katherine Hamilton: It could be a tech company that's using data centers that have demand for power. Right. Okay. Yeah, that's interesting. Yeah. So it could be a lot of different entities. But if you have rate payers supporting the floor, it's a little bit less pressure because it's the risk of supporting the floor rather than an upfront payment for a cost allocated project that they would 100 % pay for, plus the return. And if the revenues exceed the floor, then they're not paying for it. And essentially, you're cost allocating the project through the markets. So it is the purchasers of the transmission service then who are directly paying for the project.
31:14Right.
31:15Katherine Hamilton: Yeah, that's a good point. And also then, is your participation in the cap going to be sort of proportional to your participation in the floor? In other words, you can say to people, there is this going to be this incentive here that if actually revenues turn out to be higher than the cap, and there is a dividend that comes to you, you will share in that to the proportion or to some formula, which is related to how much you have participated in the floor? Yeah, so you can do it that way. And that's how Ofgem does it. But you brought up the great example of the data centers. And you can imagine where one entity supports the floor.
31:55And because they want to encourage a community to let them site within that community or that state, they might say, okay, well, we'll support the floor. And in exchange for you letting a site here, we will provide, you know, we'll transfer the above cap revenues to you, the community. So there are ways to tweak this model. So potentially you can overcome some siting challenges.
32:24Katherine Hamilton: Right. That's really interesting because it's been a big theme of several of the discussions we've been having here at the ACOR Grid Forum is this public concern about affordability of power. and then a lot of that being turned onto data centers and the impact that data centers are having and could have in the future in terms of driving out power bills. People are very concerned about that. So if you can say to people, look, both there is a sort of a backstop here in terms of the cost being passed onto you, which the data centers are going to pick up. And also there's a potential dividend to you coming out of this.
32:59Katherine Hamilton: That's probably a much more persuasive message if you can sell that to people as to why they should approve these projects. Right. And this is one option. I would say that the flooring cap mechanism is, there are a lot of different ways that you can tweak it to enable it to work here in the United States. So the United States is a very inhomogeneous country in terms of regulatory constructs. We have some states that have state regulatory authorities that could plan, finance, do the permitting and siting in state. So entities like that, for example, could determine the need for a flooring cap project and then go through the entire process of permitting and siting and then maybe opening up a solicitation process.
33:52So New Mexico has such an authority and they could potentially talk with Colorado, for example. so yeah I think there are a lot of different ways to do it here and the nice thing about I guess this the set of options that floor and cap provides is that it's layerable with other other cost recovery options or financing options rather so we were talking about public financing so that you know there are ways where we can leverage some of that funding to you know to support the floor. But I mean, there are a lot of different ways that we can play with the model.
34:31Katherine Hamilton: ACOL's membership includes industry leaders across the full clean energy value chain. Its members were directly involved in more than 80 % of the American clean energy infrastructure projects added to the grid in 2025. ACOL members are the companies investing in and building tomorrow's electric power system, accelerating infrastructure development, strengthening grid reliability and enhancing domestic competitiveness. Visit www.acor.org to learn more about ACOR's work and upcoming events, like the ACOR Policy Forum on February 24th and 25th in Washington, DC. So as you've been describing it, it seems very compelling, like an idea at least that people ought to be looking at.
35:14Katherine Hamilton: And as I was saying earlier, it is clear to everyone there is a problem here and so uh there is a there's a premium on solutions everyone's looking for answers to this problem when you talk to people about this model um what uh interest are you finding do you think this is something that people are going to be wanting to adopt i would say that um there there are definitely people who are interested in it and then they're they're also So this model is a little bit difficult to talk about. Some folks who don't think about transmission on a day-to-day basis probably find this topic a little bit complicated.
35:58So I think as we talk with decision makers and policy makers, it would benefit us to take some time to provide some of this outreach early and often. So I think that's perhaps one challenge. But I would say another challenge would be, okay, so the de-risking mechanism helps reduce the effective amount that you have to earn in revenues for the project to break even. What it doesn't do is to improve the revenue streams. So, you know, the revenues that are available to independent developers are what they are. And for us to maximize the use of these assets, or rather for the developers to be able to optimize the use of their assets consistent with what is needed out in the world that we need for the power system or the consumers need, is that we need a set of market rules that enable HVDC or HVAC, whatever kind of transmission asset it is, to provide the service that is in demand and to be compensated for it.
37:14So I think in conjunction to the flooring cap mechanism or any transmission de-risking mechanism is that we've got to look at the market opportunities to ensuring that we can encourage these assets to provide the services that are in demand and be compensated for it. But this applies to any model for de-risking or financing transmission, I would say.
37:48Katherine Hamilton: Right, because we were talking earlier to Madeline Gould-Lachlan from Grid United, And one of the big points that she was making was she was arguing in favor of the capacity provided by transmission being recognized by the markets where it's making contribution to grid stability and therefore creating the potential for that transmission line to get rewarded for that contribution. So that sounds like something you're also advocating, right? I mean, that's essentially the point you've just been making. So these are kind of complementary models. This would be another thing you could do again to kind of strengthen that incentive for grid investment.
38:33Yes. And if you look at the revenue streams that are available between Great Britain and its neighbors, it doesn't only include congestion rents, which might be one of the primary revenue streams available here, but includes like the ability to participate in capacity markets where they exist or ancillary services markets. So, you know, markets where you're procuring services to stabilize the grid. There could be insurance receipts. You know, there are a lot of different revenue streams. But the primary ones that exist in Great Britain also exist here. It's just that It's our markets, like it's not liberalized everywhere in the US.
39:18So some markets are a little bit more open than others.
39:22Katherine Hamilton: And so are we now at a moment when the time is ripe for these ideas because of demand growth, because of everyone really being confronted with the extreme strains that are emerging on the grid and over affordability? Is there something now where do you think something's got to happen really? We're at a point where, you know, if we really want to meet the demand that, you know, our government feels is necessary to drive the American economy, that, you know, we do have to make some reforms in order to meet that demand both efficiently, affordably, reliably, and, you know, hopefully sustainably. because we're in this for the long run.
40:11There are a lot of pressures to building. I mean, there's definitely, it sounds like we have to build a lot. And that is obviously in tension with building affordably. So models like a flooring cap where you can incentivize the most efficient projects and distribute the risk and the benefits in a way that optimizes good behavior, efficient behavior from all sides, I think could be very helpful in this respect.
40:46Katherine Hamilton: JD Chen, thank you very much. I also talked to Adam Stern, who's the Director of Market Policy at Clearway, the leading independent power producer. We have over 14 gigawatts of projects that are currently operating across 27 states. So we are in most every market and we have that's a mixture of wind solar storage as well as some flexible generation and natural gas in addition we have one of the largest pipelines of Development as well across again across markets across the country and so that includes that sort of mixture of different fuel types right so this seems like a great time to be in the business you're in and If you look at for instance the share prices of some of the listed independent power producers They've absolutely gone through the roof.
41:28Katherine Hamilton: Tremendous excitement in terms of M &A activity in this sector because we're in an environment where power demand is growing more strongly now than it has done for decades. It's obvious reasons. We've talked about it a lot on the show because of AI, new data centers coming on the grid, other issues as well. Electrification of transport, re-industrialization in some cases. But anyway, put that all together, it's an environment where the country desperately needs more power. And yet it's not often getting the power that it needs for a variety of reasons. and it seems like we're kind of essentially in a supply constraint world where the demand for more electricity supply is much greater than what is going to be achievable by increased supply because of various issues and barriers that are stopping that new supply coming on.
42:32Katherine Hamilton: So when you look at that, Iveram, what are the big issues for you there? when you think about constraints on supply growth, what are the biggest problems you see? I mean, first of all, you're absolutely right. We're in an unprecedented moment. We all know that. We talk about it all the time. But at the same time, I feel like our industry in particular, you know, the renewable energy industry, the independent power producer industry, this is the moment we've been building towards. You know, we have been, you know, so active over the past decade, getting projects developed, getting into the interconnection queues, which at this point are full up of mostly wind, solar, and storage resources, to help facilitate what we all see is the transition that this grid is going through.
43:15And so the supply is there. The market is there. We're all ready. And so the fact that demand is at an all-time high, this is great news. This is what we're here to do. And not just supply power that's needed, but supply power that brings the lowest cost to ratepayers, and that's what wind, solar and storage can do. But at the same time, we have some barriers in place that we all need to be thinking about and working on in order to, I think, achieve what everybody's looking to do, bring that speed to power, meet this moment.
43:48Katherine Hamilton: You mentioned then interconnection cues. So this has been an issue that people have been concerned about for quite a few years now. Those cues to get new generation connected to the grid have been going up and up and up in recent years. Probably even started before the excitement over AI and this upturn in power demand growth when there was a lot of pressure on the grid to transition to low carbon energy. You had a lot of renewable energy and then increasingly battery storage as well coming into the interconnection queue. Are those problems in terms of length of queues still as bad as they ever were?
44:31The problems still persist. And this is why it's really worth talking about and continue to talk about. I think from a regulator's perspective, you've heard us talk about this over the past decade, and maybe you're sick of it. At the same time, today it matters more than ever for all the reasons we're just talking about. This is the moment we all need to meet. and the supply that's needed to meet that demand is stuck. It's stuck in the queues, and it's also stuck because we are still not building the amount of regional transmission that's needed to connect those new resources. And so just to get into it a little bit from my perspective, and I think a lot of us, some of the core issues plaguing interconnection queues that have caused the problems that we're seeing still remain.
45:10And one of the big ones is for most queues around the country, you don't know what the cost that you're going to be faced until you're in the queue itself. And so you have to use the queue process as somewhat of a cost discovery tool. And there's a lot of reasons why that's the case, but it's really less ideal.
45:30Katherine Hamilton: Yeah, sorry. And when you say the cost you're going to face, the cost to connect. Exactly. Exactly. Because when you're in the interconnection queue, the whole point is you're getting studied by either the transmission owner or the RTO, depending on where you are. And the result is they tell you the cost to connect, which could be the cost of connecting literally to your point of interconnection or what they call network upgrades, which is like the adjustments to the full transmission system that are needed to accommodate your power. And those costs could be a huge fraction of your overall project cost to the point where a surprise 20, 30 million that you see in your results could tell you that this project is no longer viable.
46:07And so to that magnitude, it's a really big problem that you don't know those costs until you get into the queue. Like you can do a lot of pre-work, but it's still a huge question mark. And I think that's where the dominoes start falling.
46:20Katherine Hamilton: Right. So people in your position then, IPPs, developers, have an incentive to essentially file for as many projects as possible, including many, many projects that will never come to fruition, in fact, as you say, to go through this process of cost discovery. Exactly. And there's sort of a criticism, I think, from the regulators, because they're like, what are you doing? Why are you submitting so many projects? Like you're, you know, you're just throwing all these projects spaghetti against the wall and seeing what stick. And but it's like, well, we sort of have to, you know, and we'd ideally like to build all these projects, but we don't know the cost yet.
46:54And we might build five and submit 10 or we might build 10. It kind of depends on how things work out. So if we had more cost certainty ahead of time, we can make a more sound economic decision about which projects to submit. So we don't really need to do the whole spaghetti on the wall thing.
47:10Katherine Hamilton: Right. So what are the consequences of that then? does that then choke the amount of new supply that can actually get connected yes yeah so like i said i think that cost uncertainty issue and the need to kind of submit more projects than you're going to develop is where a lot of problems start because those clusters because now everything is studied together in a cluster when previously it was studied serially one project at a time but now you have these mega mega clusters because of all these projects you know using the process is a cost discovery tool. And the bigger the cluster gets, not only the larger the upgrades are, but the harder it is for those models to solve and the more uncertain those costs are.
47:50Because if eventually, you know, 70 % of those projects drop out, the costs that were associated or assigned to those projects now get transferred to the projects that remain. And then that transfer becomes, again, a big surprising cost that causes like, well, I'm at phase three of the process. I should know what my costs are at this point. But now here's a surprise$30 million. You know, that's a really tough decision on whether to move forward or not. Sure. So what can be done about this?
48:16Katherine Hamilton: And as you're saying earlier, it's not a new problem. This is not something that has suddenly blown up. People have known about this for years. People have been thinking about it. People have had time to come up with solutions. What is the right way forward? Yeah, I think there are two really big pieces. One, you know, to try to address that cost uncertainty problem kind of head on. You know, there's a few things people are looking at. One in particular is an SPP, the Southwest Power Pool RTO. I think a lot of people are familiar. They recently implemented a new interconnection procedure called the consolidated planning process.
48:52And it could be a really big paradigm shift. And that is they are proactively studying the needs of the grid for both regional transmission as well as generator interconnection needs. And the result of that model is an interconnection fee that is known ahead of time before you enter the queue, and those costs are binding. They won't change. And that right there should help really address the problem where I know what my costs are, so I no longer need to sort of guess and submit more projects than I want to develop. I'm going to submit these three projects. I already know what the costs are going to be.
49:26And the queue process becomes more of like a, I don't know, a smaller part in the process as opposed to a three - to five-year big question mark.
49:34Katherine Hamilton: Right, that's really interesting. So is that an idea in SPP or is that something they've actually implemented? So that's already been approved by FERC and they actually just released their first version of that interconnection fee. And I will say it's important to say people are following this know this. It's really expensive. It's the costs are really high. And for a couple of reasons. One, you know, it includes a lot of regional transmission that probably should have been built over the years, but is now, you know, sort of being identified by these models. And that's needed. At the same time, you know, we should expect to see some higher costs as a tradeoff for getting that certainty.
50:10You know, as an industry, like we're calling for that. Like, of course, you know, it can't be so high that we can't build projects. But at the same time, you know, I think it should be OK that in exchange for getting that certainty up front, we're willing to pay a little bit more to get it. And so this is happening right now.
50:26Katherine Hamilton: Yeah, that is very interesting because I was going to ask exactly the question about Clearway, given that you are operating in many different markets across the United States. Are there particular markets that you think are doing better than others? So SPP then is one you would identify as one that is actually making some progress. Is that a model then you think other markets could usefully adopt or is it one of those things where particular conditions in SPP make it viable there, but it wouldn't really work in PJM or Kaiso or wherever? Yeah, that's a great question. You know, each RTO has different nuances and differences.
51:03And I think individually, they would say they're more maybe extreme than they actually are in reality. And however, that said, in every other region beside SPP, that problem of cost certainty is still there. And so to the extent that those other regions can adopt something like that or find some other mechanism to bring real cost certainty before you enter the queue, like everybody is in need of that. And so I think a version of CPP definitely could work in most other places, and it should because, you know, part of that proactive modeling, what that's doing is finding more cost-efficient solutions to build the transmission that's needed, as opposed to building it in more piecemeal fashion that happens through the queue right now.
51:48So we're talking about cost to rate payers, building one or two backbone lines as opposed to 30 or 40 network upgrades. The costs are just going to be a lot less. And so that's just a benefit that I think every region would like to see as well.
52:03Katherine Hamilton: Right. And I wonder if that then relates to one of the other issues that people talk about a lot in terms of difficulties with getting new supply into the grid, which is market design and market structure. in particular, I guess, at a time when demand is growing and there's huge political focus on affordability and everyone's trying to hold down costs for rate payers and anything that looks like it might add cost, you'll get pushback on. Yeah. Is that one of the issues as well, that there's a kind of, I mean, two things. think about this SPP issue then is there a danger then that that might look like it's pushing up costs for rate payers and is that something that people are going to find concerning um yeah that's a great question and like affordability has to be our number one focus too because those are our customers in the end you know that we're trying to deliver to and you know we have to be delivering the lowest cost possible and you know I think with wind solar and storage like we're already way far out ahead than doing that um at the same time yeah I mean if costs go up for whatever reasons sometimes those costs can get translated but i think the the trade-off that we're going to be seeing here is that with um you know proactively planning the transmission system we're going to find more cost efficient solutions for things that are like absolutely needed like it's not like we you know can't we absolutely need transmission not just to get the new supply online but also to get the new demand online and so that's going to be needed anyway let's find the cheapest way to do it and so i think that's like the winning argument there um at the same time you know we we can do a better job developing our projects in a much more cost efficient way without having to go through this whole question mark queue process of like what my what are my costs are going to be you know we can more efficiently um you know find other cost savings along the development process when we know what our costs are going to be from the interconnection side of things so i think overall i think we have a more yeah efficient um project and product to deliver Yeah, no, that's a great point.
54:04Katherine Hamilton: What about the broader issues around affordability and market design? So talk a lot about interconnection cues. People also point to issues around competitive markets versus regulated markets. Something we've covered quite a lot on this show recently is the very fierce debate in PJM about that market design, that market structure. Is it fit for purpose? Is it enabling the industry to balance affordability against rising demand and the need to strengthen the reliability, resilience of the grid? Is it getting that balance right? What's your view on that whole debate? Do you think we should have significant market reform in markets across the United States?
54:53Katherine Hamilton: Again, is there someone who's kind of got the right market model, you think, but other jurisdictions, regions should be looking to? Yeah, I mean, you know, it's a great question. And, you know, we live in a country where, you know, state government, federal government, they have their unique jurisdictions. And each entity really wants to hold on to that for completely valid reasons. And so therefore you have, you know, these different markets like PJM and MISO that look very different when MISO is full of vertically integrated utilities that not only own the transmission system, but also develop and own a lot of the generation.
55:29In PJM, that's not the case. You know, there's transmission owners, but most of the states, like it's independent developers who are providing that generation sources. And, you know, we're not saying like that that needs to change, but there are, you know, differences that come up and from the inherent from the inherent differences of those regions. So, for example, in MISO right now, they are proposing they already have proposed like an expedited interconnection process called ERAS, E-R-A-S. And, you know, that's already in play. and then they are now proposing they already have with FERC a new one called LARS which is like large load addition resource study and you know a lot of us are taking issue with that proposal in the sense that the entity that gets to apply to that process which which I guess I said gets you to the front of the line of the interconnection process are the utilities and so you essentially be bypassing the queue to be able to build your projects first and so you know I mean we are sympathetic to the need that we need to find new supply.
56:33At the same time, if everything's built by these transmission owners and these utilities, and you're not using the queue in a way that actually allows competition to reign, you're not going to see that cost efficiency and how the queue is able to bring cost down, which in the end is better for rate payers. I'll just say, I've had a lot of great conversations with some public utility commissioners throughout MISO, and they are big fans of vertically integrated utilities like they very much support them these are the utilities that serve their customers in their states at the same time they are pushing my so to not have a permanent expedited process and instead focus on the queues because they see the queues as the way like i said to let competition play out and let costs kind of naturally come down where they should be as opposed to just letting utilities build things where like i'm not saying they build that projects or anything but just that sometimes those costs can be higher um for reasons that they have their needs that need to be met as well.
57:32Katherine Hamilton: Yeah, that's really interesting. And I do wonder, something I often think about when I think about the debate around market design is if you take the 30 ,000 feet view, we're in an environment of strongly growing demand and concern about affordability. And whatever market design you have, the laws of physics are the same, the laws of economics are the same somehow you need investment and that investment has to be paid for and there is not a kind of a magic perfect market design that will clear away all those problems and ensure that everything falls out in some kind of beautifully elegant way that means you get the new supply that you want without anyone having to pay for it I mean is that fair do you think or am I am I kind of underestimating the importance of market design are there actually things you can do that really would make a difference yeah i mean there's always things that you can do and we're always looking we should always be asking those questions um you know and so i would never say like let's stop looking into it but it's more um we have to respect and appreciate i think we do you know each region's inherent differences and i think sometimes that comes down to state policy or state preference um and you know or who's working in which market or where the demand and supply is you know and so I think what we just need to keep focusing on is like how to minimize cost to rate payers you know and that's what we're trying to do and you know I know that's what utilities are trying to do as well and that's why like I said like the queue is just the way to kind of allow that to happen and I just want to make one clarification is that you know the transmission owners who are developing their own generation in my so they're also in the queue with us and I think that's the ideal situation and so what I was saying before is that like if they're getting to the front of the line only costs come higher I'm just saying more so that like the Q is the place to bring down costs for everybody, whether it's the TO generator project or the independent generator project.
59:29Katherine Hamilton: And then a final thought. I'm interested in getting your views on permitting reform. Again, a bit of a tangent away from the debate we've just been having, but it's also clearly something talked about a lot in the context of how do we get more supply onto the grid? Is that something you're following closely? Is that something you think is going to be very important? Or could you imagine a world in which we have permitting reform that gets passed along the lines of the bill that's been published this year? And everyone says, this is fantastic. It's wonderful. Everyone can go out and build now. but actually not that much really happens on the ground in terms of new generation getting built because of the problems with the interconnection queue that you've been talking about.
1:00:16Yeah, I mean, it's a great question. Absolutely following it very closely. And we're very excited about it because, you know, this is a bipartisan effort. You know, in this day and age, we don't see that a lot for something so large and potentially impactful. There's a lot of potential here in this bill. I think it addresses, I think, one of the other core needs that's not just plaguing the interconnection process, but that's just preventing our country from really meeting this moment. And that's, as you alluded to, just the lack of transmission that's being built. And the fact of the matter is, you know, our grid is old and it needs to be evolved and updated to meet this moment.
1:00:51And this bill could do a lot to unlock that. And that would actually help with these interconnection issues you've been talking about. Absolutely. Yeah. So, I mean, the reason why the upgrades that we see are getting larger and larger are one in part to that there's more projects in the queue. But even bigger problem is that if regional transmission isn't being built, then you see the upgrades that we're assigned to in the interconnection queue getting larger because we're building the transmission system that probably should be built in the regional process. And so as more transmission can be built regionally, that's just more grid that we can connect to and the less need for some of these larger upgrades.
1:01:31So the faster the whole process can play out and the less cost, like we said, that we pass on to any customers.
1:01:37Katherine Hamilton: Adam Stone, thank you. Finally, I spoke with Colin Meehan, who is the vice president for grid campaigns on our hosts, Acor. He runs Acor's Macro Grid Initiative, which campaigns for measures to expedite investment in the grid. And I asked him how they set about doing that. The grid is complicated. It's the biggest machine in the world. And the process of campaigning to improve the grid is complicated, too. We focus at the federal, the regional, that's the RTO, and then the state level. And we engage with FERC. We engage with federal policymakers. We also work with regional organizations that are on the ground within the different regions to advocate at state public utility commissions and at RTOs for better transmission planning, better inter-regional transmission planning, and more accurate and modern evaluation of things like advanced transmission technologies and other things that can expedite building out the grid that we need.
1:02:31Katherine Hamilton: Right. So we've spent the day here at the Grid Forum talking to people about some of the challenges and difficulties they face in getting new grid projects built. and as you say it's a very complicated picture and at all of those different levels you've been talking about there are obstacles to be surmounted. In terms of kind of which are the most important and what you're specifically addressing are the particular things you could point to to say this is a real priority for us or this is somewhere where perhaps we think we can really as ACOR make a valuable contribution and really kind of change things.
1:03:12Katherine Hamilton: Because, I mean, sometimes when I look at the issue as an outsider, as you say, you sense the complexity. I also sometimes feel a bit of a sense of looming despair because it's kind of, or it's like one of those things, it's like trying to plug a leak in a boat that has been holed in multiple places that if you think you've fixed a couple of issues, there are still some others that are really significant and they're the ones that are going to sink you. So say, how do you go about what you're doing? I try to never sink into despair, for starters. It is tough. There are a lot of different issues and it can be a challenge.
1:03:55Each region looks a little bit different and the issues are a little bit different. But I would say broadly from our perspective, looking at the macro grid, The key there is macro. And for us, that really means an interregional transmission grid, which means getting the different regions talking to each other more, planning and building high voltage transmission to move the low cost energy resources to the places that need those low cost energy resources. That creates a more reliable grid that is bigger than the weather, as we like to say, so that if there's a storm moving through the East Coast and there's wind or solar in the Midwest, we can transmit that power and keep costs low but also keep reliability high, frankly.
1:04:40Katherine Hamilton: Right. So actually, there you go. And so that's a good reason to avoid despair is to think about some of those issues in the sense that there's now intense focus on issues around resilience and reliability of the grid. There's really intense focus on affordability and public concern about rising energy bills. and of course we're in this environment of growing demand, demand growing at a pace we haven't seen for decades, all of which mean that there is a new urgency behind the search for solutions. And as you say, new transmission infrastructure can absolutely be a contributor to that, can be one of the solutions that can really make a difference.
1:05:25Katherine Hamilton: Does that mean that some of these discussions that you're having are a bit different now? Are you finding a more receptive audience because people see the potential there for transmission infrastructure to help with the problems they're facing? Absolutely. I mean, it's a rare experience, or it feels still a little bit like a new experience, I should say, to go into conversations with people and they're already thinking about how important the grid is. This is something I think about a lot, you know, a bit of a nerd. Most of us are in this space. but now it is something that is present for most people.
1:06:03They're very aware of how this is impacting their utility bills, how they're seeing reliability impacts during the winter storms that we saw earlier in the year. So it's nice to be able to have that conversation and that the urgency has made that more broadly understood. understood. It's unfortunate that it takes this urgency to get it up to that level. But we're also in a place, which I'm really grateful for, we're in a place where this is a broadly recognized issue. It is nonpartisan. It is infrastructure. And the nice thing, you know, you talk about the different crises or urgencies that we're experiencing.
1:06:45I see transmission as really the linchpin solution to all of them as it relates to the electric grid, because it will bring the lower cost resources in. It will support reliability by diversifying the regional resources.
1:07:00Katherine Hamilton: And again, focusing on the positives, are there examples of real progress being made around the country? If you have to think about particular transmission operators or regulators or anyone that's doing something that really you think is helping make it easier to get that transmission built? Where would you point to? One area that I like to highlight when I'm thinking about where things are going well is there's been a really robust conversation between SPP and MISO, the mid-continent ISO, on what's called the Coordinated System Plan, the CSP, and that is really their version of inter-regional transmission planning.
1:07:39It is great to see them having those conversations. I think there's some progress. They're actually right now in the middle of deciding which transmission lines they're going to build across their respective regions. I do think even with that progress, there's more that we know can be done. They're not really fully evaluating all the potential benefits of those inter-regional transmission lines. So I think that their outlook is a little more modest. but they're having the conversations and they are moving the ball forward. We need to see more of that.
1:08:10Katherine Hamilton: So if you were to look ahead five years and to think where the grid could be by that time, if your campaign has been successful and you've made some of the changes you'd want to make, where would we be? Well, before I can really answer that question, I do have to say, ask me November 10th. The Senate is going to take up the Baja bill, and that's going to have a significant impact on all of this. Yeah. So just a point for anyone in the audience who is not deep in the weeds on this stuff as you are. So that's the B-A-A-J-A, the Bipartisan American Affordability and Jobs Act. I always forget the American.
1:08:52Katherine Hamilton: Yeah, thank you. And so you say it like Baja do. I've been wondering what is the kind of short form to use for it. You've been in here. So earlier today, I moderated a panel with leading staff from the four corners, the four Senate offices. And that was my first question. It was supposed to be a contentious question and see if we could get people fighting. But everybody agreed it's Baja. It's Baja. So I think that's settled. But, you know, it's a critical bill. And whether or not that passes, the regional work is going to need to continue. So to get back to your question, you know, five years from now, I think if we do see successful permitting reform at the federal level, the world looks very, very different.
1:09:33You have all states and regional transmission organizations committed to and invested in interregional transmission planning because they'll be required to. You have all states evaluating advanced transmission technologies to see if they will be a benefit to their customers. And if they are a benefit, if they find that, they are required to deploy it. It's sort of like, if you're going to save your customers money, build it. That seems like a really simple thing to say. It's more complicated than that. So those things will change if that bill passes. If it doesn't, I think five years from now, I don't know.
1:10:11I guess I don't like to think about that these days. Yeah. I'm very focused on the bill.
1:10:15Katherine Hamilton: So that's really interesting because earlier we were talking to Madeleine Gould-Loughlin from Grid United, which is developing transmission projects. And the way she put it was to say, if the bill passes, that's great and will definitely help us and will definitely make things easier and will enable more transmission to get built. But we can't rely on that. Right. And we have been around this one a few times in the past, right? bipartisan permitting reform bills have emerged and then failed to make any progress. So you wouldn't necessarily want to put all of your eggs in that particular basket, presumably.
1:10:53Absolutely not. And it's a good point. What I would say is if the bill doesn't pass, the work continues at the regional and the state level and with FERC. The problem is we're not able to continue at the pace we know we need to, to meet growing electric demand. Right now, we are kind of stumbling forward. We're moving forward, but we're not running. Maybe we're at a walk or something to kind of belabor the analogy. If this bill passes, it puts us at a run, and we have a lot of catching up to do. Other countries have been building massive grids. You know, China's the one that, you know, obviously comes to mind, and we are well behind in modernizing our grid.
1:11:36So if the bill, whether or not the bill passes, I guess is what I would say, we need to continue engaging at the state level and the regional level because that action is going to happen regardless of what happens with the bill. And in particular, if we don't see successful federal permitting reform in the next five years, I think we really risk not being able to meet the demand growth that we know we need to meet. That's going to lead to higher prices and lower reliability. That being said, we still need to be doing the work to meet those needs as best we can. And that means engaging at the state and regional level.
1:12:15So that work is going to continue either way.
1:12:17Katherine Hamilton: Anyway, but bottom line from you, though, the clear message from here is it would really help if that bill passed. That bill is really important. Absolutely. That is the bottom line. It is what we're very focused on. the bill is going to do so much to help keep electric rates low for everybody. In the end, I think that's what most people are focused on right now. From my perspective, I see situations like Winter Storm Fern, where if you had an additional gigawatt of interregional transmission, you would have saved rate payers and PJM millions of dollars over just, tens of millions of dollars over just a few days.
1:12:59those kinds of solutions would become commonplace if this bill passes. At the same time, those increased prices that we're seeing, those are a warning sign. Those, you know, first you get increased prices, then you start getting real reliability issues. And so we know we're already in warning sign territory. So yeah, bottom line is this bill will solve a number of problems related to the grid.
1:13:23Katherine Hamilton: Certainly a critical moment, a very, very important time we're in right now, even just in the next, as you say, couple of months or so? Very important. And I am honestly very encouraged. Our panel today where we had the staff from the four different Senate offices, it was remarkable the focus on the bipartisan nature of their relationships and their negotiations. I feel like when you read the bill, you see it there in the text, not to be too dorky about it, but you see the compromise. And compromise is hard. but this is an area that desperately needs it. And it's a little bit exciting to be honest, to have a bill that is this ambitious and this bipartisan.
1:14:06So yeah, that's where my brain is these days.
1:14:10Katherine Hamilton: Keeping our fingers crossed. Yeah. So that's all for us from our first show, the Acor Grid Forum. Many thanks to Colin Meehan, many thanks to Adam Stern, to Jenny Chen and Madeleine Gould-Lachlan. Many thanks to our production team, Molly Mervin and Harry Weston Cottrell. and above all, as ever, many thanks to all of you for listening. We really value your feedback. Please do keep that coming. And we'll be back in just a couple of days with more from the Acor Grid Forum. Until then, goodbye.
Americas needs more electricity, and fast. Data centres for AI, and new factories for computer chips and batteries, are driving up demand for electricity, putting mounting pressure on a power grid that has already been struggling. Across different industrial sectors, and different parts of the political spectrum, there is a broad agreement that new transmission infrastructure is urgently needed. But despite that support, getting new power lines built remains a major challenge. In the first of two special episodes of The Energy Gang recorded at the ACORE Grid Forum in Washington, DC, host Ed Crooks asks what is holding back investment in the grid, and what can be done to speed it up.
The Grid Forum brings together industry leaders, politicians and policy experts to discuss the future of the American electricity system. This year the hot topics were lengthy permitting processes, uncertain project costs, and market rules that are no longer fit for purpose at a time when there is a demand for new generation to be connected to the grid as rapidly as possible.
Ed is joined first by Madeline Gould Laughlin, director of regulatory affairs at Grid United, which is developing long-distance transmission projects to connect different regions of the US. Madeline explains why she thinks grid operators need to do more to recognize the reliability benefits of inter-regional transmission, giving utilities stronger incentives to invest in new connections.
Next Jenny Chen, a principal at the Regulatory Assistance Project, explores how changes to financing and regulation could encourage investment. She discusses the cap-and-floor model for funding transmission that is used in Great Britain: it combines revenue certainty for developers with incentives to make transmission projects commercially successful. Could a similar approach work in the US, where different states, regulators and grid operators often struggle to agree on who should pay for new infrastructure?
The conversation also turns to the growing backlog of energy projects waiting to connect to the grid. Adam Stern, director of market policy at independent power producer Clearway Energy, explains how uncertain connection costs and lengthy interconnection queues are preventing new electricity supply from coming online. He highlights reforms being introduced by Southwest Power Pool that could provide developers with greater cost certainty, and could provide a model for other grid operators to follow.
Finally, Ed speaks to Colin Meehan, vice president for grid campaigns at ACORE, about the policy changes needed to accelerate grid expansion. Colin argues that stronger connections between regional electricity systems could improve reliability, unlock access to lower-cost power and help keep consumer bills down. The discussion examines the potential impact of bipartisan permitting reform in Washington, and why work at the state and regional levels will remain essential regardless of what happens at the federal level.
Across the conversations, a common challenge emerges: the investment opportunities to expand grid capacity are real, but regulatory barriers, financing challenges and slow development processes continue to hold projects back. For the energy industry, the question is how to turn the general agreement on the need for a stronger grid into the action required to build one.
This is the first of two special episodes of The Energy Gang recorded at the ACORE Grid Forum (2026) in Washington, DC, exploring the strategies, policies and technologies shaping the future of America's electricity grid.
See Privacy Policy at https://art19.com/privacy and California Privacy Notice at https://art19.com/privacy#do-not-sell-my-info.