In short
Why big energy infrastructure projects (especially in the US) take too long and cost too much, and what changes—policy, permitting, integrated delivery, workforce/supply-chain investment—can speed them up without sacrificing safety/environment.
Guests and backgrounds
- Melissa Lott, Partner for Energy at Microsoft; focuses on energy transition/energy security, “speed of trust,” and project certainty.
- Craig Albert, President and COO of Bechtel (EPC). Engineer by training; joined Bechtel ~28 years ago; led major global projects.
Key claims
- Long permitting timelines, policy instability, and resource constraints delay revenue service, raise financing costs, and undermine investability—slowing energy security and therefore the energy transition.
- Once a decision is made, it should be executed without repeatedly reopening it; NEPA is a process to assess impacts, but timeline uncertainty persists.
- Integrated EPC (engineering, procurement, construction under one principal) reduces rework and total cost.
- Government help (e.g., financing) and permit reform (streamlining agencies, adding deadlines/consequences) are critical.
Notable examples
- Bechtel’s LNG: 32 trains delivered since early 2000s, “all on schedule and within budget.”
- Sydney airport: 2.5 years from site choice to full construction approval; completed 7 months early.
- Vogtle nuclear units: Vogel 3/4; Unit 4 ~30% faster and lower construction cost; lessons include resequencing, integrated EPC, early training, and supply-chain investment.
- Bechtel current builds: 17 LNG trains (US/Australia), gigawatt solar in Indiana, AP1000 in Poland, TerraPower Natrium in Wyoming, TVA SMR, Intel/Micron fabs, airports in Riyadh/Perth.
Written by AI. May contain mistakes. Listen to the episode to check what was said.
Chapters
Tap a time to open that second in VOThe Irony of Energy Transition
0:00 to 0:44
Exploration of the challenges in balancing energy security and transition timelines.
“And here's the irony is that you've heard the phrase, there's no energy transition without energy security.”
Challenges of Infrastructure Development
1:16 to 1:48
Discussion on the difficulties of building infrastructure on time and budget.
“It's early here on the West Coast while we're recording, and the sun is coming up to my right, and I can hear the birds chirping.”
Craig's Journey in Infrastructure
2:15 to 4:14
Craig discusses his engineering background and career at Bechtel.
“He's Craig Albert, who is the President and Chief Operating Officer at Bechtel Corporation.”
The Role of Bechtel in Big Projects
4:14 to 5:48
Overview of Bechtel's unique role and capabilities in large infrastructure projects.
“As I say, I think a lot of people will have heard of the company.”
Major Infrastructure Projects by Bechtel
5:48 to 8:01
Craig shares examples of significant infrastructure projects Bechtel is involved in.
“So it gives us a lot of really good bandwidth and opportunity to get involved in a lot of different things.”
The Challenge of Building Infrastructure
8:01 to 9:16
Exploring the obstacles to infrastructure development, especially in developed countries.
“And so certainly, as I say, if anyone knows about the challenges in getting those projects built, and the obstacles and issues that you face, that's going to be you.”
Understanding Infrastructure Development Difficulties
9:16 to 11:33
Craig discusses why it's hard to build projects and the implications for energy transition.
“we start thinking about some of the specifics and some of the potential solutions would you agree with that general statement, Craig?”
Consensus and Decision-Making in Projects
11:33 to 13:20
The importance of collective decision-making and its impact on project timelines.
“So, Melissa, I know this is an issue that you and I have talked about many times.”
The NEPA Process and Its Impact
13:20 to 14:00
Discussion on the National Environmental Policy Act and its role in project approvals.
“And so the idea of should it take this long?”
Understanding NEPA's Impact on Projects
14:00 to 16:40
Learn about the National Environmental Policy Act's role and the associated uncertainties in project timelines.
“NEPA, the footnote, we should always drop in the National Environmental Policy Act, which is the kind of governing framework legislation in the United States for all infrastructure approvals, among other things.”
Show all 31 chapters
International Infrastructure Comparisons
16:40 to 20:20
Explore how infrastructure project timelines in the U.S. compare to those in other countries, including the challenges faced.
“And, you know, what's happening in the U.S.”
The Regulatory Environment for Projects
20:20 to 23:10
Discuss the complexities of the U.S. regulatory environment and its effects on infrastructure development.
“My opinion is that the legal and regulation challenges are the primary contributor, but not the only contributor.”
Lessons from the Vogel Nuclear Project
23:10 to 26:50
Gain insights from the experiences with the Vogel nuclear project and its implications for future infrastructure.
“You kind of arrived halfway through that project, didn't you?”
Improvements in Nuclear Project Execution
26:50 to 28:00
Learn how lessons from Vogel can lead to improved execution in future nuclear projects and overall industry productivity.
“But to answer your question, that was our role.”
Lessons from Vogel and Nuclear Construction
28:00 to 29:10
Learn about the key lessons from the Vogel nuclear project and their implications for future projects.
“And keep in mind, that's construction only.”
Importance of Early Investment in Workforce and Supply Chain
29:10 to 31:20
Discover the necessity of investing in labor and supply chain early in energy projects.
“Tell us what you think the key lessons were.”
Risks of Atrophy in Energy Infrastructure
31:20 to 33:58
Understand the risks associated with workforce and supply chain atrophy in nuclear projects.
“And you just have to be – you can't underinvest in the human side of building these jobs.”
Current State of Nuclear Projects in the U.S.
33:58 to 36:14
Explore the current developments and future potential of nuclear projects in the U.S.
“In the nuclear world, you know, we have such an opportunity now to reverse the atrophy, reconstitute it.”
Lessons Learned and Speeding Up Construction Timelines
36:14 to 37:46
Learn how to leverage lessons learned to speed up construction timelines for energy projects.
“Yeah, so just to baseline some of this, one thing I just wanted to review for folks who didn't follow or live Vogel very closely, in terms of the overall timeframe, I mean, it was a 14-year process, roughly.”
The Need for Government Action in Nuclear Energy
37:46 to 40:06
Discuss the necessity of government action to support nuclear energy development.
“Yes, I think that I can't think of any of the periods from 9 to 13, 13 to 17, and 17 to 23 that didn't have significant speed-up opportunities.”
Financial Viability of Nuclear Power Today
40:06 to 42:05
Examine the financial feasibility and demand for nuclear power in the current market.
“Because as I say, if you leave it just to the market, it's not going to happen.”
Financial Feasibility and Regulatory Support for Nuclear Power
42:05 to 43:52
Discusses the financial feasibility of nuclear power projects and the supportive regulatory environment that exists.
“But what I would say about the feasibility, the financial feasibility, in the U.S.”
LNG Success and Lessons for Nuclear Projects
43:52 to 46:33
Explores the rapid growth of the LNG industry and discusses lessons that the nuclear sector can learn from this success.
“It has a huge impact on you or could have a huge impact on you.”
EPC Costs and Project Delivery Insights
46:33 to 49:57
Analyzes the importance of Engineering, Procurement, and Construction (EPC) costs in project delivery and how lessons from LNG can help nuclear projects.
“I wouldn't claim there's been no cost inflation.”
Workforce Challenges in Energy Infrastructure Projects
49:57 to 53:49
Addresses the challenges of workforce capacity and the importance of retaining skilled workers for energy projects.
“The engineering is done to optimize construction.”
Vertical Integration in Construction for Efficiency
53:49 to 56:00
Discusses Bechtel's strategy of vertical integration to control supply chains and improve project efficiency.
“A big failure in the sense of what you mean being late.”
Bechtel's Vertical Integration Strategy
56:00 to 57:29
Learn how Bechtel manages its own welding organization and steel sourcing for efficiency.
“and and and so we decided we would just have our own welding organization that we could call upon for some of the more complicated welding and not have to go to market every time So we do it with people.”
Efficiency Gains in Solar Project Execution
57:30 to 59:24
Discover how Bechtel significantly increased solar panel installation rates through efficiency improvements.
“Yeah, it's more right than what a lot of people would think, actually.”
Challenges in U.S. Solar Construction Costs
59:25 to 1:00:36
Understand the factors contributing to high solar construction costs in the U.S. and potential solutions.
“And it doesn't get as much attention in the country today, but we're doing all of everything.”
The Need for Labor Reform in Construction
1:00:37 to 1:04:05
Explore how improving the perception and conditions of craft professions is vital for infrastructure development.
“You've talked quite a lot, Craig, about what you specifically have done at Bechtel.”
Value of Craft Professions in Infrastructure
1:04:06 to 1:05:02
Examine the significance of skilled labor in energy infrastructure and the societal value of construction jobs.
“and how we think about credentials and how we think about what a path to success looks like and how that's evolved over time.”
Transcript
Automatic transcript. May contain errors.0:00And here's the irony is that you've heard the phrase, there's no energy transition without energy security. If we slow the path down to energy security because of long timelines to get jobs started, then you're actually slowing the path to energy transition. I was just thinking as Craig was talking about the difference between the words should and could, how long should these things take? How long could these things take? What are the compromises that we're willing to make? a good construction worker makes six figures. Somehow we are still a country that prioritizes college over the trades.
0:43Hello and welcome to The Energy Gang, a discussion show from Wood Mackenzie about the fast-changing world of energy. I'm Ed Crooks, and on this show we're going to be talking about how big things get done. I think everyone who's interested in energy will know that it's very, very difficult to get new infrastructure built. It's particularly difficult to get it built on time and on budget. And that may be true most of all in the US, but really it's a problem in all developed countries and in many middle and lower income countries too. To talk about that, I am joined again by our good friend Melissa Lott.
1:13Melissa is a partner for Energy at Microsoft. Hello, Melissa. How are you? I'm great. It's early here on the West Coast while we're recording, and the sun is coming up to my right, and I can hear the birds chirping. So that's a pretty good morning start, I will say. That is lovely. It's a beautiful morning. Yeah, it is not so early here in New York. Already the sun is up and it's getting hot. I think they're talking about temperatures peaking at 101 degrees F, about 39 degrees Celsius today. an issue I think we're going to be talking about a little bit during the course of this show because it's certainly relevant to the question of getting infrastructure built.
1:47But yeah, so we're really living it right now. And of course, as always with you, Melissa, we have to tell people about your usual disclaimer. Anything you say on this show is your own personal opinion and not an official statement from Microsoft. So as I was saying, we want to talk about how big things get done. And it's a great pleasure to welcome someone to the show who is facing those critical issues to do with construction, infrastructure development every day of his life. He's Craig Albert, who is the President and Chief Operating Officer at Bechtel Corporation. Hello, Craig. Welcome to the show.
2:22Yeah, thank you very much. Good morning. Nice to see you both. Thank you very much indeed for joining us. Now, something we always like to do with people who are new to the show is talk to them a little bit about their careers, how they got started, and how they got to the roles they now hold, what career paths took them there. So perhaps, Craig, could you tell us a little bit about yourself? How did you get first started in working on these big infrastructure projects and how did you get to that job you have at Bechtel? Yeah, okay, good way to start. Thank you, Ed. So first of all, I'm an engineer and I think I realized that that was what I needed to be at a very young age.
2:59And I was always really fascinated by what a single engineer could do. And then early in my career, I started to realize that two engineers could do more than twice as much as one engineer. And the math sort of continues. And I got really fascinated by what could a thousand engineers do together? And what kind of scale and what's possible? And so I was always really fascinated by that. And about eight or ten years into my career, I met Bechtel. working together on a job. And as I got to know Bechtel, I kind of thought, yeah, that's what I want to do, what they do, building really, really big things that really matter, that serve an important need for the public, for industry, and they can do it anywhere, any size, anywhere.
3:47And I just sort of fell in love with that. And so joined Bechtel 28 years ago, have been on many, many different projects in many different positions in several countries, multiple industries, and really learned how to successfully build things, anything, anywhere. Also learned a lot about what not to do, which is often the best way to learn. And about seven years ago is when I was asked to take on this position that I'm currently in now as the president of the company. so it's been a it's been it's been a adventurous love affair uh myself and big projects right absolutely and as you say perhaps at times a uh uh tortured love affair we can get into some of the issues as you say around that and and some of the lessons about what not to do i think was going to be a really important part of our conversation today perhaps you could tell us a little bit more about Bechtel as well.
4:49As I say, I think a lot of people will have heard of the company. People know the name. I think of you as it's an EPC company, right? Engineering, procurement, and construction. What exactly do you do? What is the role that Bechtel plays when a big project is getting built? So first, I would just say for those that don't know Bechtel, the people in the general public may not have heard of Bechtel because we don't usually deal directly with consumers in the retail market. Our customers are big industrial players. We are an engineer and a builder, and we build really large things that only very few companies would even consider taking on.
5:33We are 128 years old. It's a really unique company. We can take on things that maybe publicly traded companies can't. We don't worry about quarter-to-quarter results. We really play the long game. So it gives us a lot of really good bandwidth and opportunity to get involved in a lot of different things. EPC, engineering, procurement, construction. So for anything to be built, engineering and procurement and construction have to be integrated. Has to be. What Bechtel does is we take on jobs where that integration is really needed more deeply. You know, the really big jobs, really complex or require significant speed or really big quality challenges.
6:26When the jobs get hard, the integration of those three things becomes more critical. So give us some examples then. What are the kinds of projects that Bechtel's worked on, or what other perhaps even specific projects? Are there examples of big bits of infrastructure that you have worked on that people might have heard of? Yeah, we have quite a portfolio of jobs right now in a bit of a growth cycle in the industry. We are currently building 17 LNG trains, liquid, natural, gas, liquefaction plants, 17 in the U.S. and Australia. that's 85 million tons per annum. We have five major solar projects going on in the U.S., including the first gigawatt-sized solar job in Indiana.
7:15We have an AP-1000 nuclear plant that we're underway now in Poland. We're building TerraPower's Natrium Advanced Reactor Project Wyoming. We're working on the first utility scale light water small modular reactor with the GE technology for Tennessee Valley Authority in Tennessee. We've got two really big semiconductor manufacturing plants underway now for Intel and Micron, which was just recently announced. That'll be in New York. Copper concentrators in South America and Australia. Australia, we're building an airport in Riyadh, Saudi Arabia, and an airport in Perth, Australia. A lot of big jobs, Ed.
8:00A lot of stuff indeed, right. Yeah, that's a very impressive list. And so certainly, as I say, if anyone knows about the challenges in getting those projects built, and the obstacles and issues that you face, that's going to be you. I think so. Yeah, fantastic. Excellent. Well, let's get into that discussion then. So, I mean, as I say, I think it's fairly sort of broadly accepted, I think, probably across the political spectrum, probably in different countries around the world, that we have a problem with infrastructure, as I say, particularly, I think, in developed countries. It seems to be conventional wisdom now that we have made it too hard to build anything, and that is leading to real problems in terms of economic growth, in terms of meeting energy demand, perhaps particularly in the context of AI-driven increases in electricity demand.
8:54and it's made it too difficult to make progress with decarbonization because if the transition to lower carbon energy is anything it's a massive project program of investment in new infrastructure if you can't build that you can't build a low carbon energy system so i mean perhaps before we start thinking about some of the specifics and some of the potential solutions would you agree with that general statement, Craig? I mean, do you think, is it broadly true that it's too hard to get stuff built? Yeah, I mean, I do agree with that. Too hard, maybe not the word too, but certainly much harder than it should be.
9:35And I think that is an issue. I do want to say, you know, maybe a point that I don't hear very often. One of the reasons it's so challenging in the US in particular and other developed countries, it's actually a positive reason before I go to constructive thoughts. The positive thoughts are, you know, doing work in the U.S., everybody has a voice. Every interest group has a voice. And when jobs were planned in the U.S., there's a lot of thought given to the ecosystem around that project, the environment, safety, community. And that's not bad. and it probably grew on us a little bit, but there are some real positive intended things by the difficulty of getting things done because you want them to be done well.
10:27The challenge, as you pointed out, is that the timeline, the permitting timeline, the policy instability, the resource constraints make it really, really difficult and there's a lot of very significant implications that actually undermine the progress that we're trying to make. And if I could expand, I mean, the implications are if it's really hard and takes a long time to permit, it raises the cost to develop the job. It defers when you get to revenue service. It increases financing costs. It reduces the percentage of the jobs actually going to go forward, and it hurts investability. And here's the irony is that you've heard the phrase, there's no energy transition without energy security.
11:17If we slow the path down to energy security because of long timelines to get jobs started, then you're actually slowing the path to energy transition. And that's sort of the irony that I think a lot of people would be good for them to understand. Right. So, Melissa, I know this is an issue that you and I have talked about many times. What's your take on this broad question of is it too hard to get infrastructure projects built? I was just thinking as Craig was talking about the difference between the words should and could. So, you know, it's how long should these things take? How long could these things take?
11:53And to your point, like what are the compromises that we're willing to make? So around everyone having a voice. I mean, we've talked many times, Ed, and how big things get done. It's a book that we've talked about before. Sure. And then also the speed of trust is something we've talked about and how nothing moves faster than the speed of trust. And so by having voices involved, you have a lot of positives that help projects move forward. The uncertainty in a construction timeline, the uncertainty and when I can muster up. I mean, Craig, I'm sure you don't have this off the top of your head, but I mean, do you have a single project that is less than 100 folks on site for if you're building an airport?
12:27I mean, that's thousands of people who are involved. And so when you have to marshal up that type of resources, there needs to be some path to understanding some certainty around the timeframes. And I will say full disclosure, I went to school with a lot of civil engineers. I was rogue. I was mechanical and chemical. But a number of them have worked for Bechtel for decades. And they talk about these huge projects they're undergoing and the small town of people who are working on it in the offices and on the ground. And when you're talking about infrastructure projects that are that big, whether it's an AP1000, a huge solar project, an airport, I heard you mention, and man, the nerd in me wants to know more about how that kind of a project works.
13:04But there has to be a path forward to saying, once we've made a decision, we being a collective statement, once we've made a decision to build this, how do we actually move forward intentionally, productively, making sure that we're adapting when we need to, but also never losing our North Star in it. And so the idea of should it take this long? How short of a time frame could it take while still respecting and incorporating and keeping all of these good pieces that you just outlined, Craig? That's where my brain is going, Ed. I think we all can give examples of projects where like, oh, this could have taken a lot less time if we had not had these missteps.
13:40And so that issue you raise, I think, is a really interesting one about kind of taking a decision and then sticking to it. Is that your point? That, as you say, if once we as a society involving everyone who is relevant and taking into account all the relevant considerations in terms of the environment, the economy, local communities, etc. Once you've said, yes, we're going to do this, then you should be able to just go ahead and do it without unpicking that decision, constantly revisiting it, challenging it, overturning it again and again and again. Is that your point? So when I'm thinking about your question, Ed, I'm thinking about, I wish I had one of my lawyer friends here to talk about NEPA, you know, this process we have at the federal level in the US that we've talked about on the show.
14:25NEPA, the footnote, we should always drop in the National Environmental Policy Act, which is the kind of governing framework legislation in the United States for all infrastructure approvals, among other things. And within that, what is the point of it? Let's take a look at projects, understand the impacts of it, understand what pathways we have to mitigate those impacts and make a choice. Now, the choice is not part of NEPA. NEPA is the process of actually identifying the impacts and identifying the different possible scenarios that you can move forward in. But I'll say it's a near universal piece of feedback I get from, you know, the folks who are coordinating the big NEPA projects and those processes where they're like, man, uncertainty about timelines.
15:04Like how fast is it going to happen? When do we do certain things? When is it done? When have we finished that process? But I also get that feedback from the communities that I work with. So different communities where they say, when do I put my voice into this process? When can I say, okay, we have closed that chapter of this discussion and I'm moving on to the next one? That uncertainty is certainly significant and it affects big projects. And we see those effects amplified across big projects. Yeah, I think it's a really good point that several points that Melissa's made. And, you know, one of the vantage points that we have is we're not just doing work in the U.S.
15:38We are doing work in other developed countries and other developing countries. and we can see how the system works in other places and have some really good examples. And then maybe some encouragement about, I think, where we're going with permit reform in the country right now that address a lot of the things we're discussing. So really, we just finished an airport in Sydney, Australia. Very well done. Great respect for the community and environment and all the things that we're trying to protect with our regulation. it took two and a half years only two and a half years from when they chose a site to when they gave us the go ahead for full construction two and a half years that would take eight or ten in the u.s um and uh and then of course once it started it was not interrupted which often uh doesn't happen in the u.s there's often interruptions um so and then we ended up getting the job done early public infrastructure job done seven months early it was unheard of Oh, unheard of, yeah.
16:39So it can happen. And, you know, what's happening in the U.S. right now is there's finally really good bipartisan support for permit reform. And the things that we're talking about get directly at this discussion. How, you know, right now you have to submit a permit application to five different agencies. And five different agencies are all evaluating the same things. So there's got to be a way to streamline, get rid of the redundancy. That's part of what the permit reform is about. There are no deadlines or consequences on an agency not issuing their conclusion. They can just drift. So there has to be deadlines.
17:23Other countries that do this have deadlines. Industry lives with deadlines. Regulators have to live with deadlines. So there's a few really specific things like that that can just make a huge difference in this challenge that we're talking about. Yeah, that's really fascinating. And actually, I want to just dig into that point about international comparisons, because people talk about China a lot. And they say, oh, they build all this high speed rail so quickly, or they're building these new nuclear plants so quickly. Fine. The United States is never going to be China in terms of its political system.
17:55European countries are not going to do that. So China is probably not a great comparison. What I am interested in, though, is the question of whether the United States is noticeably worse in terms of these issues than other developed countries in, if you like, the West. And it does seem like if you look at, certainly in my home country, the United Kingdom, there are terrible horror stories about how long many big infrastructure projects have taken. If you look at high-speed rail there or some of the new nuclear plants that they've been building, you know, that's been true in France and other European countries as well.
18:34It does seem to be a general problem around the world in many different countries. But question then, is there something which is specifically kind of unique to the United States, something about the American system that makes these problems particularly bad here? I think we have to recognize that the intentions of the regulations in the U.S. that take long are really good intentions, and I think they do lead to better quality projects in the end. It's just that it's overly penalizing industry, and it might be causing us to suboptimize. We have to find a way to take the really well-intended regulations and streamline them.
19:17We compete with China in a lot of places around the world. and when the playing field is level, we can beat them. In the Balkans, in Eastern Europe, in the Balkans, we go head-to-head with the Chinese on building motorways and when we have to play by the same rules and use the same supply chains and resources and they're not allowed to bring people from China to execute work in Serbia and they do it the way we do it, we win. We're actually more productive, better quality and safer and deliver a better product. So we have to find a way to level the playing field with the things that are other than the actual project execution.
20:02If we can get it to where project execution is the only way we're competing, we can win. Right. Because I was going to ask then, we've been talking about a lot then about sort of political, regulatory, legal systems. are there other issues that in western countries make it hard to develop large infrastructure projects is it about the supply chain you just mentioned is it about the workforce is it about skills and capabilities capacity in the industry capacity in the epc industry for instance that makes it hard to get this stuff done or from what you're saying is it really those political and legal regulatory issues that are at the heart of it.
20:48My opinion is that the legal and regulation challenges are the primary contributor, but not the only contributor. So I got a couple of different thoughts when I'm listening to you, Craig, and I want to make sure that I'm not building a seven-layer cake in my brain, and that's not how you're outlining it. But it's like when we look at the challenges of big projects, you're saying the regulations, the permitting, the policy environment is a primary challenge. It is very significant. But then, and this is why it's a cake in my head. So spoiler, that's what it is. On top of that, we have, and I know we've talked about these aspects on the show, Ed, around supply chains and workforce challenges, which as an aside, in prepping for this show, I ran across y 'all's, what is it, Next Generation Builders Program for high school girls in Ohio.
21:35So I'll camp build it. So that's really fun, but I'll park that for a minute. But when we go to the next layers, I'm hearing that there are more things that are shifting and changing in the environment. And there's certain things you can do that add additional challenges to it. There's certain things you can do. So you can start skidding up stuff in one country, you can start putting together something over here and then ship it versus shipping parts or pieces or constructing it over here. But there really are these all of these challenges are piling up on top of each other. And they all contribute just to lesser or more degrees.
22:06Am I building that right in my mental image of what you're trying to outline? I think so. I think you are. I think that there's no layer in the cake that can't be improved, and there's actions we're taking to improve every one of them. But fundamentally, the word disadvantage is that we'll have to call it a disadvantage, that labor costs more, but you really wouldn't want it any other way because, you know, we have standards for how we treat people in the workplace. So within that, I've got one question, which is how much of that cake is very much just general big projects and how much of it is really specific?
22:48So I'm thinking about nuclear. I was following Yale's announcements around your new office in Gdansk in Poland and bringing in the new AP1000 and that whole transition away from coal that's going on in the country. and I was thinking through how much of this volume wise is very much just big infrastructure big infrastructure things and how much of it is very specific to the type of infrastructure you're building right that's a great segue actually to what I just wanted to ask about which is yeah well yeah because I think it's it's really helpful probably to look at specific projects and specific industries and as I'm very interested here about what you're doing in Poland I wanted to look back at the experience of the last two big nuclear reactors built in the United States, Vogel in Georgia, Vogel 3 and 4, where Bechtel played a key role.
23:39You kind of arrived halfway through that project, didn't you? I mean, essentially, as I understand it, sort of brought in to rescue it after the original companies working on it had some pretty severe difficulties. So, yeah, I was interested in hearing about your experience on that project, what you think you learned from it. And as Melissa was saying, then, how do you apply that then to other projects you're working on in the future, including this job in Poland? So let's talk about Vogel in the nuclear business. The first thing that I would point out is that I really believe that the companies that took that on, Southern Company and Georgia Power, are national heroes for attempting the first Greenfield nuclear project in America in 40 years.
24:34So I think there's a debt of gratitude to those two companies because that was so critical for us to make any progress in nuclear. Somebody had to go first, and they did. We were brought in. We were actually the fourth contractor brought in. And we talked earlier about integrated EPC, which I know we'll get into a little bit more. But on this job, the way it was set up, Westinghouse, the reactor supplier, was the engineer. And Southern and Georgia Power were doing the P, the buying, and then they had a contractor doing the construction, the C. So it was not integrated deeply from the very beginning.
25:19And there's also – there was a lot of atrophy. There's been a lot of atrophy in the value chain in the U.S., nuclear atrophy, I would call it. So – and one of the things that we did in Bechtel years ago, which I think is really good background in nuclear, is we designed or built two-thirds of the nuclear power plants in the U.S. over 30 or 40 years. And when – after Three Mile Island and Chernobyl, when we abandoned nuclear power as a future source of power, what we did in Bechtel was we moved our people to nuclear cleanup, nuclear propulsion, and nuclear deterrent. So we actually kept our nuclear capability.
26:05Other companies didn't do that. We did it because those were also really important missions. But we also believed nuclear power would come back someday. We just didn't know when. And so that kind of put us in a very unique position to still be able to reconstitute the nuclear capability because we still had it, just not in the power sector. So when we got to Vogel, what we did was we resequenced the job. We prioritized design so that we would reduce rework. We modified the work package approach, synced up material deliveries with construction. But really what we did was we worked with Southern and Georgia Power and Westinghouse, and we just plowed through it, you know, perseverance and fortitude and just got it done.
26:53and so many lessons learned. But to answer your question, that was our role. Our role was we came in as the fourth contractor to just brute force it across the line with people who understood from a nuclear context where we were. Yeah, so as you say then, the nuclear supply chain in the United States had really attributed over three decades and more. You had to acquire a lot of expertise and knowledge as you were working on it to get that project over the line as you say to get those two reactors completed as you say you acquired a lot of knowledge that way i know it was said there was a factoid that was flying around often quoted that even just the knowledge you'd acquired on completing vocal three then was very useful for vocal four such that the costs of vocal four were about 30 % lower than for vocal three.
27:48Is that correct? As I say, I've seen people make that claim. Yeah, yes, that is accurate. Unit four was 30 % faster, and that would translate directly into cost than unit three. And keep in mind, that's construction only. And so you can imagine if you take all the EPC lessons, What would that mean for another unit after Unit 4 at Vogel? It's actually quite encouraging to get 30 % just in construction alone, just on construction productivity without ever having an opportunity to adjust the engineering procurement aspects of Unit 4. So it's pretty encouraging. What it did for us in the industry was a lot of people – I totally understand the blowout of Vogel and how that might discourage people from wanting to go into nuclear.
28:48It could be portrayed as a failure. That is not how we look at it in the industry. We look at it as an argument for what's possible as opposed to an argument against. If you do it right, if you really take the lessons deeply into consideration, and I'd be happy to go over some of the key lessons. Yeah, we do, actually. I'd be interested to hear them. I'm sure Melissa would be as well. Tell us what you think the key lessons were. Yeah, okay. So the first one gets back to how we started this entire podcast, and that is what's an EPC? and I mentioned that E and P and C always have to be integrated to build anything.
Read the full transcript
29:29What it means for Bechtel is EPC means you are the principal, we are the principal designer, the principal buyer and the principal builder. And with competent people, single company, integrated platform, tools that use the same data in each of those three phases, E and P and C and you optimize your execution for the total cost. You're engineering to buy the right things and to build efficiently. And it's all very, very deeply integrated. And that was the key number one lesson of Vogel is that it was not an integrated EPC from the beginning where you had one competent builder who could do all three things doing all three things.
30:17And I know we'll get into some other industries later where we have proof points and precedents of how that works. But that was the number one lesson. Set the requirements early in a really informed way for how it will impact engineering and procurement and construction and design for field productivity and minimization of rework. So that's all that big lesson number one. And just a couple more I'll mention. And you really have to invest in training early. And we partner with the trades. I mean, NABTU, North American Building Trades Union, they're like us. We're partners, a deep partnership, and they're a fantastic partner.
31:05and you have to invest really early in understanding your labor challenge. And you can't just stumble into it. You have to understand what labor can do, what assistance is needed, what kind of training needs to be done. You have to invest. You have to get out to the colleges and the high schools. And you just have to be – you can't underinvest in the human side of building these jobs. And you just can't wait and react. Same for the supply chain. You have to invest much earlier. You have to understand what your supply chain is capable of. You can have a great design, but if the supply chain can't deliver it, it's not a great design.
31:42And so much greater insight into the supply chain. And those are some of the key high-level lessons.
31:53So what I wonder is, do those lessons then get forgotten? So what I mean is, you've had this fantastic amount of learning by doing. you've developed all this capability in the workforce and in the supply chain you've driven down the cost such that vogel 4 cost a lot less than vogel 3 presumably the right thing to do at that point would have been to go on to build vogel 5 and 6 and 7 and 8 or other civil plants wherever they might have been to take advantage of all that capability you've built up if you don't immediately move on to new projects how big of a risk is there that that whole supply chain and everything just atrophies again the workforce goes off people take other jobs doing different things and so on and so all that uh all those gains you made all those benefits you acquired from doing the hard work at vogel don't um get carried through into the future yeah so this starts to get back to the point that Melissa mentioned.
33:01A lot of the lessons I just described are actually not unique to just nuclear. These lessons of integrated EPC have been learned in the LNG market, in the combined cycle power market, in airports, in metro systems. Integrated EPC is typically, poor integration is typically the cause of project blowouts, and good integration is usually the cause of a success. where nuclear is unique is it's a different language the quality requirements are unique the way you trace materials is unique and so there are additional requirements in nuclear and and you don't want it to atrophy again but i just want to make sure folks understand that that the The bigger issue here is just good old fashioned pure execution.
33:58And it's not just a nuclear issue. In the nuclear world, you know, we have such an opportunity now to reverse the atrophy, reconstitute it. And hopefully if we're successful, it doesn't happen again. Not in my lifetime. Right. And so you're working on this one other project in Poland then. and what there's the expectation hope that there'll be more AP1000s built in the US. I know we've had quite a few, we've had some statements about that from the administration or the administration's keen to press ahead with new nuclear construction. Doesn't seem to have been that much actual activity so far and not so many contracts being signed.
34:44What's your sense of how that's going? I wish it were going more quickly. But things are happening. And I think I mentioned Natrium. That's not an AP1000, but it's an advanced reactor, and we're building it. We are in construction in Wyoming. And sorry, I forget. So which one is that then? That's one of the new advanced reactors. That's the TerraPower project that Bill Gates is the principal investor in, and it's sodium-cooled reactors. And it's got their NRC license to construct, which is a huge accomplishment. It's the first advanced reactor or SMR construction license, and that's just a few months ago.
35:34So quiet progress, but definitely progress. And I'm aware of some of the larger nuclear utilities in the country that are seriously evaluating AP-1000 deployments and lining up their investors and regulators and soliciting information from industry. And so things are happening. And I do believe that it'll happen. And the same way Vogel hopefully inspires someone to go second, somebody who goes second will inspire someone to go third, fourth, and fifth a lot more quickly. Yeah, so just to baseline some of this, one thing I just wanted to review for folks who didn't follow or live Vogel very closely, in terms of the overall timeframe, I mean, it was a 14-year process, roughly.
36:27And I'm thinking through it in terms of when an EPC could, should, we won't go into those pieces of it, be involved. But it was March of 2009 when the Georgia Public Service Commission was approving that expansion project on VOGAL to add those. I think the first nuclear concrete was poured in 2013, so roughly four years later. And then it was roughly four years later when y 'all got involved, Craig. So it was 2017 when y 'all were stepping in. And then fast forward, it was in the spring of 2023 when Unit 3 came on. And I think Unit 4 followed roughly, was it nine, ten months later? Something like that?
37:05Yeah. And so I think about that. And just as a high level to this question, it's like if we can translate a lot of lessons learned that are non-nuclear specific and then layer on all the nuclear specific pieces of it and do the same for other big energy infrastructure projects, whatever they are, whatever fuel they are. It feels like there is the first few years that's getting approval from the Public Service Commission, that's getting approval from the NRC. That's a lot of stuff that just has happened, but it's really in that 2013 onwards and the run up to that 2013 pouring in the first concrete that we can do things to actually shorten up timeframes to give more certainty in terms of when this sucker is going to land and get commercially connected and actually be providing large amounts of electricity to the grid.
37:51Is that fair to say in that way? Yes, I think that I can't think of any of the periods from 9 to 13, 13 to 17, and 17 to 23 that didn't have significant speed-up opportunities. Every aspect. Even the decision to pour concrete in 2013, the minimum requirements to do that were met. But in hindsight, was there enough engineering maturity and supply chain maturity to financially justify that? Hindsight would say we should have waited. At the time, I might have done the exact same thing if I were there when that was happening. But there's no one part of the system in that whole 15-year period, 14-year period that didn't have a lot of opportunity to speed up.
38:54and within that ed i'm thinking about to your question this is where this popped into my head was okay if we want to not lose lessons learned if we want to keep kind of the train running down the tracks and not have it slow down for a bit then there's certainly that that initial before the first pouring of concrete where it's like lining up projects i mean even before 2009 like there was a lot of work that went into actually getting approvals having the concept for where these things were going to land but that bigger plan but without that kind of front work we probably can't realize a lot of these opportunities, but lining up projects so that we can realize those opportunities, say, okay, we learned this here, let's bring it over here.
39:30That's a pipeline of projects challenge. And that does, does it not depend in large part on the economics of those projects, which at the moment for new nuclear in the United States are pretty marginal. If the market alone is going to drive what people are building, people will be building new gas fire generation and new renewables and new storage and those are the things which will give you the lowest cost power supply and get it to market the quickest which is as we've discussed many times on the show a particularly important issue at the moment for everyone interested in data center development and ai so does that mean i mean melissa i know what you think about this but does it need a lot more government action then to put the economic frameworks in place before you get to any of these issues about how the projects are actually delivered, you know, the country needs to decide collectively, we actually want new nuclear.
40:25Because as I say, if you leave it just to the market, it's not going to happen. I think there's opportunities across the board. I don't think that you need to have absolute certainty in terms of what the total pipeline looks like to move forward productively with the projects that are in the pipeline and to be, you know, having this integrated approach that can speed stuff up and make things, you know, land closer to on time, closer to on budget, in some cases that we talked about ahead of time. And maybe there's some examples we could talk about ahead of budget or lower spending than expected is a more accurate way of saying that.
40:58It certainly helps though, Ed. And that is kind of the point I was driving at, which is how do you balance the decision-making under uncertainty principles here? So we do have some uncertainty. We can't get rid of all of it, of where the next project's going to land, but then not lose these learnings in the meantime. And I think, Craig, y 'all have a different perspective than most anybody because you do this internationally. So, okay, we don't have a pipeline here, but we have these things going over here. My number I came up with, I'll say is that y 'all have been involved in more than 150 nuclear power plant.
41:30I mean, that sounds right. Now, most of those, you know, most of those were in the 60s, 70s and 80s. But since Since the 80s, there have been in the U.S., there have been a few completions, jobs that were paused after Three Mile Island got continued and completed. And we're the ones that did all of those. They were in the 90s and the early 2000s and even the teens, Watts Bar, Browns Ferry. We did finish those nuclear jobs. So there was never a decade where we weren't building one, even though people thought the industry wasn't. But what I would say about the feasibility, the financial feasibility, in the U.S.
42:13today, first of all, the regulatory system, the NRC, they're ready. And that is not the bottleneck. And so we're in a really good position, I believe, with the NRC's readiness and willingness. There's really good policy and public support right now. It's growing, and I don't think that's going to be the issue. The need for the power, really high quality. There's a big difference in the power quality when it's nuclear power. It's online all the time. It's very steady. It's high, high quality power, which is what the data centers need. So there's a really significant demand for this type of large-scale high-quality power.
42:55And I believe the return on investment parameters do work. however there is a commercial hurdle right now in the next couple of units and what i mean by that is it's still early in the cost curves maturation as you go from serial number one to serial number two to serial number three there's a a phrase you know how quickly can we get to nth of a kind cost and schedule yep and vogel is like serial number one And so there's still cost overrun risk that has to be dealt with. That's the hurdle that we have to get past. What we've been out touting is every party has to take a little more risk to make this happen.
43:42We do. Westinghouse does. The utilities do. Everybody's got to take a little more. And then we are going to need a little help from the government. If we can get past that hurdle, I think it all works. and we'll get into that pipeline of work that you're mentioning. Right. Yeah, that's really interesting. And, of course, I mean, one of the things about this is because each individual project is so big because they end up being tens of billions of dollars, as you say, then the risk of that going wrong for a specific company can be enormous. It has a huge impact on you or could have a huge impact on you.
44:22To that point, then, as you say, government backing being very important. I know the administration has talked quite a lot about the role of the energy dominance financing group, the old loan programs office, as it was. That clearly could play a very useful role in backing nuclear projects. I think they've got resources already allocated by Congress to do that. Is that something you think is going to turn out to be important? Yes, it is. First of all, every little bit helps. And those types of incentives improve the ROI. And if the ROI is improved, then the parties that are taking on the project have more capacity to absorb overrun risk.
45:08but there's still the issue of the last tranche of overrun risk. But those things that the government's doing absolutely helps and the government's been really very supportive and encouraging of industry. The government wants industry to go faster. So those are really helpful. Just to think about some other examples from the energy industry and perhaps some very clear success stories, uh in particular interested in building lng plants um so so general view it is too expensive and takes too long to build large infrastructure projects in the us lng plants it seems like have been a pretty outstanding exception to that in that the industry has grown very very rapidly um i think the first fid for a new lng export plant in the us was in 2012 maybe 2011 um since when capacity has absolutely rocketed us is now by some distance the world's largest exporter of lng and it is growing very fast there's a huge wave of construction now underway And I think a great majority of those projects, built by yourselves and by others, have come in on time or thereabouts and on budget thereabouts.
46:33I wouldn't claim there's been no cost inflation. Certainly there has been some. But in general, that industry really seems to work. Are there particular lessons, do you think, that other energy sectors could learn from the LNG industry and what it's got right? One of the things I mentioned earlier about – when I mentioned earlier that a lot of the challenges that the nuclear industry – just one more point on the nuclear industry that face is the more generic challenge of just large-scale EPC and not necessarily nuclear-specific, two different things and two different issues. To be clear, the cost of the EPC is always the most dominant cost of delivering a project.
47:18The equipment from the technology provider, whether it's the compressors for an LNG plant or the reactors for a nuclear power plant or the turbine generators and steam turbine for a combined cycle plant, those are the things that get everybody's attention and tickles everybody's fancy because they're technical and it's really exciting. But the fact is those things are generally less than one-third the cost of these jobs. And the cost is in the EPC. And that's where all the people are, and that's where the costs are. And what we learned in LNG, it's not only their lessons, it's the model. And it's the model that we're touting because it's a fantastic example.
48:05We've delivered 32 trains that are operating today that we delivered this century since the early 2000s, mid-2000 knots. 32 trains, 120 million tons per annum. It's one-third of the world's capacity, over half of the U.S.'s export capacity. And it was all on schedule and all within budget, 100%, every one of them. We didn't have any that didn't achieve the contract schedule. But you got to trace the roots of that back earlier to before the turn of the century when somebody was doing them first. And there was overrun risk. And there were things to be learned. And so the LNG industry went through what the nuclear industry needs to go through.
49:00And the LNG industry is what sort of puts the North Star of what's possible. Like this can be done. And we're now doing – we just turned over six Corpus trains, Corpus Christi trains for Chenier, six trains in the past year. And every one of them was breaking new records of time to market. And so we're still breaking records at 32, 17 – we have 49 trains between done and doing. So there's a lot of encouragement there. And these are capital-intensive jobs, compressed timelines. They require deep integration of ENPNC. We're doing heavy digital delivery. The way we carry lessons and teams forward from unit to unit is very systematic and deliberate.
49:53And it is absolutely the north star for nuclear. And that's how we're approaching it. that's really interesting and so then basically volume is crucial then is it's being able to do essentially the same project or very similar projects over and over and over again as you say to get to that point where you're at kind of nth of a kind where the one you're going to do you know the the n the n plus one of the n plus two are very much like the n uh which was like the n minus one of the n minus two that these are you know just things that are um completely repeatable unsantarized. Yeah, no, that's exactly right.
50:31The engineering is done to optimize construction. The data is integrated between E and P and C, the tools talk to each other. We just take the risk of rework out of the system. Another thing that we do in LNG, which is a really good lesson for nuclear is we've done it so well now that when we see an LNG job, We see like a organism and our job is to de-bottleneck it. It's like an assembly line almost and our job is to de-bottleneck it. So every single time we find a bottleneck in the process, we take control of that bottleneck. So for example, we fabricate our own pipe now. Pipe is the critical path of these jobs.
51:17We kept running into problems with pipe suppliers, so we decided to make our own pipe. we're constantly de-bottlenecking and that's a great lesson in nuclear as we mature. When you talk about a train with LNG, so that's what is it? It's an independent liquefaction unit and purification unit, right? So taking that natural gas and making it into LNG, right? So when we talk about trains, that is not small. That's a big one. So I just wanted to These are$10 and$15 billion contracts. For one train, that would be. For a three-train plant, you're in the$15 billion range. But then the second thing is I've got two things that I know this came up when we were talking before the show a little bit and when you and I were talking.
52:06But I also want to come back to the workforce piece of this. So when you're able to go from LNG to LNG to LNG to LNG with the same or very similar workforce, you've got a lot of folks who carry through them. You carry the lessons through really similarly. So I've got two pieces that I'm thinking through, which is how much of this can be transferred to other projects, other energy projects, back to what we were discussing earlier. But the second thing is, I mean, the workforce is not infinite. And so, you know, when do you start hitting on those really uncomfortable places where you say, I mean, I've got a good lesson learned.
52:38I don't have the person to help me translate it to this next project if I want to speak into that. Yeah, it's definitely – that is definitely a factor, Melissa. We have a phrase in our company that we're paced by the capacity of our talent. And we can't take on something we don't have the capacity to perform and we are turning work away to this day. We are turning work away because of this. But we won't take something on if we don't have – when we do our planning, We actually think through from the designers to the craft professionals to the startup engineers. We're thinking, who are these people?
53:17Where are they coming from by name to a large degree? And at what pace can we onboard new people? At one time, we were doing one LNG plant only, and then we went to two at a time and then three at a time. And now we're doing six different plants at a time by growing capacity. So we are doing that. But you have to be really mindful of your ability because the worst thing you can do for an industry is have a big failure on a job. That sends a wave of no confidence into the industry. It's really tough to recover from. A big failure in the sense of what you mean being late. Cost and schedule blowout.
53:59Cost and schedule blowout. Yeah, got it. Yeah, yeah, yeah. Well, my brain, I've got another question, but my mind goes to if you don't do that, you lose trust, you lose confidence, and everything becomes a problem. So it's a very intentional investment there. But around this, you also mentioned pipes, I have to ask. So I live in Transformers world a lot of my life and other pieces. And so when you think about the things that are getting in your way of delivering on time on budget, okay, so you got pipes and you said, you know what, we're going to do it. We're going to pull that in closer. Um, what are the other things top of mind for you as you look at the, I'm focused on the energy portfolio, obviously, but like what pieces of that puzzle, is it pipes across the board or is it other things that you're like, we may have to pull this one in closer to, to get the job done?
54:45Yeah, we do it all the time. It's actually one of the most fun parts of my job because Bechtel has the – we have the strength to do it when we see it needs to be done. It started – it's actually started a long time ago. We basically fabricate our own pipe, big spools. And it not only did it de-risk the supply chain for us, but it allowed us to speed up the process of fabricating pipe. It's a very, you know, engineering feeds the requirements and then the fabricator gives information to construction and there were a lot of handoffs. So by taking control of the supply chain, we also sped up the EPC process and we basically moved pipe off the critical path.
55:31Like it's no longer the critical path of our work. It's amazing. We did it with steel just three years ago. We replicated our pipe strategy with structural steel. so now we fabricate our own steel we get the steel from the you know from the mills but then we fabricate the part that takes long we do that ourselves now we um we do it with labor in the sense that we have our own welding organization and because welders are really hard to come by and and and so we decided we would just have our own welding organization that we could call upon for some of the more complicated welding and not have to go to market every time So we do it with people.
56:13We build our own LNG tanks, and we used to rely on other contractors to do it, but it got to the critical path, and it replaced pipe on the critical path, so we started doing the tanks ourselves. So that's sort of a Bechtel way of doing things. We call it vertical integration. Vertically integrate to get control. Sure. And pick the pieces on that. And am I right? I think, Ed, you flagged this, that Bechtel, this primary source of steel, is it from the UAE? Did I remember that right? Yeah, that's right. I'm thinking about your world, Ed, dynamics around that and just how that plays in. But I'll leave that one for the moment.
56:54Yep. Go ahead, Craig. Sorry. Oh, no, I was just going to say, yeah, UAE is where we made an investment. We source a lot of steel in the U.S. And we do a lot of work with the steel fabricators in the U.S. to better integrate with our engineering. But we don't have an asset in the U.S. that we own and control in that way. Yeah, understood. Yeah, and so when you talk about repeatable projects in energy, I guess the same is true with solar and wind, right? that those projects are being built over and over and over again in very similar ways. And that's been a crucial factor in contributing to being able to drive down costs for solar and wind power around the world.
57:37Is that right? Yeah, it's more right than what a lot of people would think, actually. You know, solar... In the sense that people think it's simpler, and maybe these things don't apply. But that is not the case at all. I always like to tell people if the work is technically simpler, then you have a higher expectation for how well it can be done. And then everybody's trying to do it as best as they possibly can and competition kicks in and the definition of world class is just different, but it's still, phenomena is still there. Solar has all the same matters. The permitting is the biggest cost driver, and getting connected to the grid is a big cost driver.
58:28But then once you get those things done, then it all comes back down to EPC again and how efficiently you can build. With the five jobs that we have in the U.S., we took an industry that was doing like maybe 2 ,000 or 3 ,000 panels a day erected, and we are up at 15 ,000 panels per day in Indiana. 15 ,000 panels per day. I had a conversation with one of the CEOs of the panel suppliers, and they couldn't believe – they didn't even imagine that their own product could be installed that quickly. And it's because we're using drones and machine-controlled feedback and automated piling and – but digital execution, integrated EPC.
59:13It's happening in solar. and we're bringing the cost curve down and the scale of gigawatt scale now. You know, it was the vision of solar was to get to this scale. And we're kind of there. And it doesn't get as much attention in the country today, but we're doing all of everything. Yeah, no, that's fascinating. And because, as I understand it, as the cost of the panels has come down and down and down, all those other things, everything to do with construction, balance of plant grid connections um i guess the the racks that the panels are mounted on all of that all that stuff becomes relatively more significant relatively more important to the overall economics of the project and therefore something that it really makes sense to focus on and actually if you look at kind of all in system costs of construction of solar in the united states compared to other parts of the world, it's still relatively high, right?
1:00:10The United States is one of the absolutely highest cost locations for solar construction. And so everything you can do to bring that down, not through working on the panels, but through working on everything else, is going to be really important. Yeah, that's right. We're going to have to embrace automation. Right. So I see we're getting a bit short of time. So I must get to the issue then, which I'm particularly interested in, about what could be done better kind of at a social and political level to expedite these projects. You've talked quite a lot, Craig, about what you specifically have done at Bechtel.
1:00:49You've talked about the conditions that can exist in an industry to make infrastructure development more efficient. You've talked about the way developers need to think about projects. we touched a little bit on this earlier on but just in terms of the um regulatory framework the legal framework the things that could happen with permitting reform what specifically would help you if i'm sure you do talk to members of congress talk to people in the administration and you could say to them this is what we really need what are the things you'd ask for So what we do, we're right in the middle of it, advising on policy and sharing our views.
1:01:36And the good news is the government wants our views, which is always helpful. We have found that to be true across different administrations. So that's pretty encouraging. We discussed permit reform, and I think that's number one. And it's because it's just an unlocker. The next one is labor. And we have been working really hard and well with the government on this. And, you know, construction, labor, everything we're talking about, and I, you know, the way I describe it, everything we're talking about, all these assets that the world needs for AI and more power and more transportation systems, every one of these things sits on concrete, steel, electrical instruments, wires, you know, and that's what we're talking about.
1:02:28That's installed by craft professionals, and there are not enough of them in the United States. And we have to change the way we speak about the craft profession in our country. It's an honorable, highly respected, almost heroic living. It's very different today than it was years ago. A good construction worker makes six figures. But somehow we are still a country that prioritizes college over the trades. And we go about – and our generation and my parents' generation sort of we did this. And it was wrong and it was a mistake. And we have to restore the dignity to being a construction professional.
1:03:19It's a fantastic living. you can, you know, you could be 19 years old and making$100 ,000 and not have any debt and have a car and a place to live. You know, it's just a complete, so, and so we've been working with the government like on how do you, how do you take the Pell Grant system and make it, and make a vocational education qualified for a Pell Grant that's now passed. So, but that's the second area There were government help is needed in changing the mindset of the country on what success means in America. It doesn't necessarily mean going to college and wearing a tie. Those days are gone and we have to fix that.
1:04:00You're giving me a you're making me remember a book that I read a while ago by Michael Sandel called The Tyranny of Merit. and it talks about how we measure success and failure and how we think about credentials and how we think about what a path to success looks like and how that's evolved over time. And it's like, oh, you went to this college or this thing. So you've succeeded. And it's like, oh, and how we think about that as a society. A discussion for another day in depth. It's a really good one. I think, and I might've mentioned on the show a year or so ago when I was reading it, a year or two.
1:04:29You did, yeah. I remember you talking about it. Yeah, yeah. It's a really, but this is a very important point to highlight just the value of those jobs and then the importance of those jobs and the importance of people who do that work. That, look, the electricity doesn't arrive in my home or anywhere else by accident. It arrives here through infrastructure that has to be constructed and maintained. And that takes people who understand that work. And yeah, I'm going to stop myself now because we do not have time in today's discussion, but it's such an important point. Yeah. You're right. This is a fascinating topic.
1:05:09There's so much more that we could say about this. Unfortunately, we can't, though, because I know we have to end it here. And Melissa, you have to go, don't you? So let's wrap up the discussion now. But it's been fantastic talking to you both. Thanks very much indeed. Thank you very much, Craig, for joining us. Yep. My pleasure. Thank you guys very much. Great to see you again, Melissa. We'll be talking again very soon. yeah it was great to see y 'all um craig ed i really enjoyed this discussion i've got so many notes written down of follow-ups i have and things that rabbit holes i want to go down so yeah i do agree i feel like we've only scratched the surface but yeah plenty more discussions to be had on this topic and certainly it's been fantastic hearing your perspective craig i've learned so much from this discussion just that we've had right now um many thanks to our producer Molly Merwin and above all as ever many thanks to all of you for listening and watching we really value your feedback please do keep it coming send us a message leave a comment and we'll be back very soon with all the latest news and views on the future of energy until then goodbye
From the publisher
Whoever you ask, you are likely find broad agreement that the world needs more energy infrastructure. Whether you are worried about ensuring secure supplies, powering new data centres, or cutting greenhouse gas emissions, the answer is most often going to be investing in new assets: power plants, transmission lines, factories, pipelines, ports… the list goes on. But all too often, getting big projects built is painfully slow, expensive and unpredictable. It is particularly difficult in high-income countries, and perhaps in the US most of all.
For this episode, host Ed Crooks and regular guest Dr. Melissa Lott are joined by Craig Albert, the President and COO of Bechtel, one of the world’s biggest engineering and construction companies. Together, they discuss the critical problems that get in the way of infrastructure projects, and what businesses and governments can do to get past them.
First off, Craig acknowledges that the problems in the system all reflect good intentions. Communities, safety, the environment and local impacts all deserve scrutiny. The problem, especially in the US, is that the process used to take all those factors into account when approving large projects is slow, fragmented and uncertain. The result is that it pushes up costs, delays revenue, creates financing risk, and ultimately slows progress towards energy security and a lower-carbon energy system.
The conversation digs into the role of trust and certainty in decision-making. Once a project has been assessed and approved, how do you stop it from being endlessly revisited? Craig argues that some aspects of the US system create particular difficulties. Other developed countries have shown that infrastructure projects can be brought in on time and on budget. Craig cites the Western Sydney International Airport project, which moved from site selection to full construction approval in just two and a half years. In the US, he says, the same process could easily take eight to ten.
The discussion then turns to nuclear power, and the lessons from the two new AP1000 reactors built at the Vogtle plant in Georgia. Craig calls Southern Company and Georgia Power “national heroes” for taking on the first greenfield US nuclear project in decades, but he is candid about what went wrong. His biggest takeaway is the importance of deeply integrated EPC: engineering, procurement and construction working as one system from the start. He also stresses the need for earlier investment in workforce training, stronger supply-chain visibility and better sequencing to reduce costly reworks.
From there, Ed and Melissa widen the lens to look at other energy sectors. Craig explains why the US LNG industry offers a more hopeful model of projects delivered without huge cost overruns and multi-year delays. In that industry the construction companies are building repeated, standardised projects, with integrated delivery, and a relentless focus on finding and fixing bottlenecks. Bechtel has delivered dozens of LNG trains, he says, all on schedule and within budget, while still improving speed from one project to the next. Similar lessons apply in solar, where scale, automation and better execution are helping push installation rates sharply higher.
But policy and project design are only part of the story. Craig argues that workforce is the other great constraint. If every new power plant, grid upgrade, semiconductor fab and airport ultimately depends on skilled craft labour, then the US has to start treating those jobs with the respect they deserve. Restoring the status of skilled trades is not just a cultural issue. It is essential to the country’s ability to build, Craig says.
The closing message is both practical and cautionary: if the US wants more energy security, more electricity for AI and data centres, and faster progress on decarbonisation, it has to get much better at building. That means fixing permitting, reducing project uncertainty, investing earlier in supply chains, and treating skilled labour as a strategic asset, rather than an afterthought.