vo listened to this episode to put together the overview and transcript, so there may be the odd mistake.

In short

Episode topic: Gigawatt-scale battery storage in the UK/Europe (“Battle of Britain”), and whether “bigger is better” versus smaller, distributed batteries.

Guests

Chris Elder, CEO of Fidra Energy (ex-Intergen gas generation; later led battery site strategy using existing gas infrastructure; principal investor EIG). Hosts also mention Laurent Segeland (London) and Gerard Reed (Berlin), but the main guest is Chris Elder.

Key claims

Market inflection in 12–18 months; governments need 22–27 GW battery storage by 2030, requiring 500 MW+ sites (not repeated 50 MW modules). Fidra treats batteries like gas-style flexible assets: optimize trading/dispatch with multiple revenue streams, and finance like infrastructure (project finance, 65–70% gearing).

Notable examples

Thorpe Marsh (1.4 GW / 3.1 GWh, under construction; first battery skids arriving soon) and West Burton; Enderby planned (duration under review, possibly longer). Fidra targets ~50% contracted revenue over debt tenor via capacity market (about 10%) plus toll/flow contracts. Battery tech: SunGrow chosen after a 12-month tender; warranty life 15–20 years. Debt financing oversubscribed; 13 banks involved; Santander as financial advisor.

Transcript

0:06With Laurent Segeland from London and Gerard Reed from Berlin, this is Redefining Energy. Today on Redefining Energy, we're going to talk about gigascale batteries, Laurent. And I call that the Battle of Britain. And at the end of the day, we need to answer a simple question. Is bigger better? That's a very, very good question, Laurent. What's your gut reaction? My gut reaction is simple. Because the early development of batteries were coming from wind, solar, They put megawatt scale batteries. What was your first transaction? Like five megawatt? It was like, woo. And then we went to 50. And now we're going to talk about gigawatt scale batteries.

0:55Yeah. And I'm still a little bit torn on this. And that's why I'm really interested to have this conversation, right? So our guest is Chris Elder. And he's the CEO of Fidra Energy, a company nobody probably heard about, but I can tell you is one of the four horsemen of the gigawatt scale play alongside Statera, Copenhagen, Infrastructure Partners and Zenobi. Those four are the major players in this new landscape of gigawatt scale batteries. And they're hauled back by very deep-pocketed infrastructure investors. The reason I'm looking forward to this as well is because I think you said it earlier on, batteries up to now have been built really by renewable people.

1:42But these are not renewable people. What these are is they're coming from the gas area. They're coming from the trading area, the flexibility area. And that's a change. It's changing the way things are done, the way you think about energy, the way you think about running these assets, hedging them, et cetera, et cetera. So I'm really looking forward to this conversation. Well, let's bring Chris on the show. Chris, welcome to the show. Thanks for having me. Well, Chris, from my side as well, it's great to have you. And I'm looking forward to this conversation on large-scale batteries. Maybe just kick off and just actually, we'd love to hear your view on the role of large-scale batteries in the power system.

2:20We've definitely reached an inflection point in the market over the last 12 to 18 months where the idea of batteries as a 50 megawatt type asset module has really changed significantly. Not just Fidrub, but a number of other businesses have sort of taken that leap, if you want to call it, into the core infrastructure market of building very, very large batteries. In order to deliver the level of growth that most governments are looking for now in storage and use our existing infrastructure as efficiently as possible, we really need to build sites of a scale. We can't just keep building 50 megawatt batteries.

3:00And to use the UK as an example, the target for the UK government is to build around somewhere between 22 and 27 gigawatts of battery storage by 2030. So in order to do that, by building lots of 50 megawatt sites, it simply won't be achievable. So you need big sites. You need sites that are of 500 megawatt plus size. Chris, when we started looking into batteries, there are three characteristics. So number one, they were a phone manager. So when you're a fund manager, you like to have little assets everywhere. And the second is they're all coming from the wind and solar industry. Now you, you come from the gas industry.

3:37So you come from a totally different angle. But interestingly, you choose the main technology. So what do you think your approach is different from the legacy battery developer? In some ways, the history goes back even further. I was at Intergen for 15 years, which was the classic sort of independent power producer and gas generation business. And the legacy of the strategy, like many strategies, was a failure. We at Intergen developed a number of large CCGT combined cycle gas turbines 2010 to 15. And unfortunately, those sites were just not economic to build in the latter part of the last decade.

4:13But what we realised was that batteries were an emerging technology, that those sites that were designed and consented for gas turbines could be re-consented into large battery sites using existing infrastructure. And actually, once the CapEx curve had come down, the sort of cost curve had come down a bit, batteries would be incredibly economic relative to peaking plants, for example. So we started that work when we were at Intergen back in sort of 2017-18. And then as West Burton Energy was acquired by EIG, who are our principal investor in FIDRA, we were able to persuade them that this was really the right point in the market to go out and buy and develop our own site in the UK off a significant scale.

5:01Because ultimately, like any other renewable technology, economies of scale is important. so if you put more megawatts in the ground you will get economies of scale through lower grid connection costs lower civil works but i think we always had the mindset of we were looking at this as a flexible asset in many ways in a very similar way to a gas asset it depends upon volatility it depends upon the ability to access multiple revenue streams and i think i've probably offended a lot of people in the sort of renewables industry by saying that that battery storage is really no different to a gas plant in many ways and the way you trade it the way you think about optimizing it those are all things that we thought about when we ran gas plants so chris can i do just to talk about small versus big i understand what you say which is there's economies of scale you go large but one of the things that i see about small is the fact that small you can solve other problems as well which you can't do at large in other words you might have a bottleneck in a distribution grid you might have a data center at least backup.

6:05So how do you look at that? And how should we look at it as investors? There's a few fold advantages going large. So I think the first one, as you mentioned, economies of scale. So it's just cheaper to build on a pound per megawatt, pound per kilowatt basis, probably in our views, sort of 20 to 30 % cheaper than what we've seen in the market. It allows people to deploy large tickets. The difficulty with smaller batteries, you typically wouldn't attract the large infrastructure investors and others to put that sort of money into a project. So you had, as you talked about earlier, a lot of the fund managers, the smaller developers building these smaller assets because the equity ticket was smaller.

6:46The other advantage with these large assets is that you can go and get project financing. So again, very similar to gas plants. These are typically project finance with 65 to 70 percent gearing. that allows us to optimize the returns the scale gives us flexibility and offtake so yes we're going to need to secure some contracted revenues but ultimately when you can realize those capex savings you can still put in contracted revenues you can gear the project up and ultimately that gives a good return for investors and chris can i ask you to talk a little bit about the revenue side because one of the things that i see that's very difficult about batteries is it's the revenue side of it is to predict it because what we tend to see is that as the volatility goes down revenues go down how do you do that and then how do you persuade the project finances to put capital into that we start with a sort of magic number of trying to contract about 50 of our revenues over the debt tenor there's no magic to that it's really just a target that we think about and that could be through the capacity market so if you think about our first two projects at thortmarsh and West Burton.

7:53About 10 %-ish of revenue comes through the capacity market in the UK. So that's a 15-year index link contract. Overlaying that, we then have either tolls or flow contracts, which sort of get us to roughly the 50 % on those projects. And in that, we know where a sort of low case might outturn. So an important thing, particularly for infrastructure investors, is understanding as a minimum that they will get their money back. And it's very important to demonstrate that over a period of time. We know that the returns are going to be, we have various merchant projections, we give those to the banks in a typical way, whether it's, we use Beringa, but it could be Aurora, it could be AFRI, it could be MODO, whoever it might be, banks will take some comfort for that.

8:38But ultimately, they'll look at the low case and understand what they can sort of size accordingly. So from our perspective, it's more, have a baseline of contracted revenue, get comfort that the merchant forecasts, which make up the balance, are relatively robust. But understand there's going to be some volatility of cash flows over that period of time. When it comes to size, they put FIDRA in the category of the titans. So I would say there are two other titans, CIP and Statera, and the rest are kind of smaller. And the interesting thing with your equity backers, So you've got EIG, which is a large US infrastructure investor, but also the National Wealth Fund of the UK.

9:23And that's really a wonderful endorsement of the security of supply you bring. So can you explain why they chose you? It's an interesting story. So when we started trying to finance Thorpe Marsh in 2024, the first thing we were concerned about was actually the liquidity of the debt market. That was our number one concern because to finance a project of the size, we were going to need to raise 500 million plus of debt financing. And we had some initial conversations with the National Wealth Fund as a lender. What became clear quite quickly was actually that the liquidity in the debt market for a well-structured, highly contracted battery project was very much there.

10:04I mean, we were two times oversubscribed on Thorpe Marsh for our debt credit approved approaches from banks. What was a little bit harder was actually finding an equity partner to come in alongside EIG. But the National Wealth Fund at the time, one of their clear strategic priorities was to invest in battery storage. And so when they heard about our project, they heard about their investment really being into a business with an experienced management team alongside a very well regarded sponsor in EIG. and I think importantly with projects that they were investing into FID, you know, they weren't investing necessarily into a development pipeline.

10:46They were coming in at FID for the project. That really made it quite a compelling case. And so we were delighted that they invested at the platform level rather than at the project level because that gives us flexibility to go and build future projects as well. You see they've also invested in the likes of Eel Power, which is another UK battery storage platform. they're very focused on ways in which they can catalyze private capital. I would also say anecdotally, it helped the fact that the site was on the constituency of the Secretary of State at the time for energy. It was an old coal station.

11:21It was a good job creation story behind it as well. So I think all those things made it a really compelling investment for them. They've been a great partner to work with so far. You talk about ThoughtMart. that's a ginormous project 1.4 gigawatt 3.1 gigawatt hour and it's under construction so it's going to be operational next year yep what did you learn so far we come from a gas background so construction of a battery project in some ways is quite different to a gas project gas project is more complex because you have multiple different things coming into a gas project the battery project is really a logistics exercise it's in essence the way of getting things to site at the right time and when we need them to be there.

12:04So certainly the logistics are the key element to it. And we're only, I would say, in the sort of mid-phase of that. We've got our first battery skids arriving in the next couple of weeks at site. We've done all the civil works. We've done all the foundation work. So the challenge of construction, I think, is still going to come in the sense of just the logistics. But in essence, you've not got the same challenges of putting a turbine in, connecting it, running. Those things are not there. you're really just putting existing pre-built systems onto the site. Something of the scale of Thorpe Marsh, one of the key differences in that is just the scale of the civil works.

12:38So just to give you an overview of the site, it's about a 50-acre site, about 500 ,000 tonnes of pulverised fuel ash, which was on the site. It was an old coal site, basically, and that's where the ash was stored. So we had to flatten that whole site, which took us about four or five months to do that. really an incredible exercise to do it also helps to elevate the site as somebody once joked to me i can't believe anyone's building a battery on a place called thorpe marsh it seems quite odd to build a battery in the middle of a marsh but the good news is it's it is elevated from sea level but that was a huge construction challenge for us at the outset but now that we're into the more delivery of the batteries it's just a logistics exercise really and chris what do you see us are you a flexibility player are you an independent power producer are you a battery player what do you see as that and what do you see as that going forward as our model is build on operate maintain so that's ultimately what the business wants to be i don't see us as particularly different to you know what an intergem was or a drax was in the 2000s 2010s we are an ipp or an ifp whatever you might want to call it we won't do our own trading today because frankly we don't have the scale to do it.

13:55And again, I think there's such a competitive optimizer market out there that it just doesn't justify building today our own trading capability. But we'll look again at that in a few years time. But today, I think really what we'll focus on in being is we'll keep doing some development. We think our real sort of secret sauce is the ability to take projects from ready to build through to COD. We can do greenfield development, but frankly, the bit that we think we can do very well as the structuring in terms of commercial or financing construction and then ultimately coming in to manage the asset after COD.

14:28If I look in the UK market what you've got is a whole pile of the wind and solar market in the UK there's a lot of rock assets which had PPAs in place from 10 years ago whatever and what they're doing is they're coming out of PPA which means there's merchant risk there which I would have thought it's a huge opportunity for the likes of yourselves in terms of batteries how do you look at that do you look at it as an opportunity or you say it's not for us so we've talked to a number of off takers who have i would call it long wind exposure or long solar exposure and that's one of the things that they look at in terms of whether they're interested in tools or floors or like just to sort of balance out their portfolio generally i see the growth in intermittent renewables as a fantastic opportunity because it will create volatility coupled with sort of gas price volatility as well but specifically on those coming out of rocks and the like i think it's just going to drive more people to look for more contracted structures going forward and looking to firm some of their exposure if you think about the gb as a battery market the thing that differentiates gb to other markets is just the depth and maturity of the off-take market here that's why we've got to eight gigawatts operational.

15:39That's why we'll probably get to 20 gigawatts operational by 2030. There is a mature market. There's lots of people interested in providing those types of financeable products. And I think that's absolutely key. And if you look at that relative to other markets in Europe, that's the key differentiating factor of scale of batteries and markets. Gerard, you remember a few years ago, we went to see Vattenfall and we told them the most precious part of your portfolio are your brownfield assets yeah yeah you remember yeah i do indeed of course yeah and they were like so 50 acres so for our listener that's roughly 30 ish football a bit more than that depends how big your football pitch is but yeah and so your supplier of batteries is sunroh so you you're going to use the Power Titan 2.0.

16:33How did you make that choice? What was really interesting in their proposal? So we ran an extensive tender process, took 12 months. What was fascinating about that tender process is in the space of 12 months, the cost of the battery system is roughly halved. This was over sort of 2024, 2025s. It was an incredible reduction. Some of that was just the price of lithium some of it was technology evolution and some of it was just a competition first project of the scale people were as you can imagine were very keen to get involved particularly when they knew that our sponsor was eig and that there was credibility behind the project we chose sungrow price was one element i think another really important element was the long life batteries so when we look at it from a sort of financial modeling perspective from a debt sizing perspective the longer we can get warranted life and batteries the longer we can size the debt and ultimately the longer is before we have to repower the asset and look at the sort of returns from that so sun grows batteries were particularly good there to give you an example when we started the tender we probably assumed that we would get sort of for a two hour two cycle a day battery we might get sort of 12 to 15 years out and we've got a warranty from SunGrow that stretches from 15 to 20 years.

17:51And that makes a material difference in the economics. So as a whole package, and given their bankability and insurability, we just felt at the time they were the best auction. That's for Thorpe March or that includes West Burton Sea? West Burton Sea as well, yes. So we're using SunGrow batteries there. Okay, and then you get what, a third site, Enderby? Enderby is our third site. We expect to get to financial close at some point next year, subject to connection offers, which I'm sure we can have a long discussion on it at some point. We've not made any technology choice yet for that project. We're considering different battery providers and we're also looking at duration again.

18:32The projects at Thorpe Marsh and West Burton were both 2.2 hours. That was probably the right duration at the time. but now you could argue that sort of a slightly longer duration might be more economic, depending on the sort of the capex and the revenue curves. So we're looking at duration again, and Enderby, you know, fortunately is of a size similar to Thorpe Marsh, not quite as big as Thorpe Marsh, but similar that we could extend the duration to before us if we needed to. When I look at your banking pool, so you have 13 banks, and collectively they landed you£600 million. I have the name ABN AMO, China Minsheng, CIBC, Deutsche Bank, Investec, MUFG, NatWest, NordLB, Santander, Siemens Bank, SMBC, Societe, General and Standard Chartered.

19:22Is there anyone that kind of led the whole pack? For Thoughtmarsh, because it was a bit of a first of a kind project, we appointed Santander as our financial advisor. But we were also keen that they sort of backed the deal with their balance sheet as well. they were probably the one that we had in our mind that were sort of not only doing the advisory work but also we'd come in with their balance sheet but they were all very keen to come in it was a club it was a large club but it was a club of banks that we were able to coordinate some of them were perhaps more active than others in the UK sector in the likes of MUFG and ABN have done a number of deals now in the battery sector including follow-ons on West Burton for us I wouldn't say there was any one particular bank leading but certainly Santander were our financial advisor and sort of driving the whole process.

20:10Chris, just from my side, given that you come from the gas background, what's your view on the future of gas in the system? And I'm talking about really, I'd love to hear your view. You've gone from gas to batteries, which says something, but just dig into that. Secretly, and it won't be secret after this broadcast, but I still love gas. Gas has really got an important role in the system to play because ultimately you need somebody to do that last 5-10 % of work in the system and gas will always be a critical part of it and gas generation assets we need to utilise them to their full life in the UK.

20:44We've seen a number of assets with their life extended I think they're a relatively low cost in building other forms of new technologies. Personally I think gas has got a long way to go and a long way to run. It'll certainly run less in the UK but provided it's remunerated properly through the capacity market or through a strategic reserve or however it might be i think these plants will be around for a long time and if you look at the uk market as a whole we still have 30 to 40 gigawatts of gas in the uk and we might not have as much of that in 20 years time i think we'll have still have quite a lot of it and they think the case for gas is still pretty strong across the uk and frankly across some european markets as well italy germany poland those types of markets so there is according to the plan another 15 gigawatt of batteries to install in the uk and that's not even counting if we have data centers and you know the demand starts to go up that's not even counting the pump hydro if they are done one way or another how do you see the competitive landscape between the big titans and the guy who spray and fray it's a fascinating site coming again from the gas generation world when there was maybe five or six key players in the market back in sort of 2010s what's happened in the battery sector is is you've you've got the early fund managers of the greshams the gore streets who focused on those smaller assets then you've got the large platforms backed by infrastructure investors so ourselves to terrors and ob field other people in the market and the utilities are dabbling if i can call it that with batteries but not really making a a big play to it.

22:26So you've got this incredibly fragmented market for battery storage, which at some point feels like it's ripe for some level of consolidation in the sector, particularly because most of these platforms, if they're owned by infrastructure investors, are probably on five to seven year type horizons anyway, in terms of sort of equity hold timelines. What's going to be really interesting come the end of this decade is the level of consolidation in the market, and whether we see this move from being very, very fragmented, lots of different players, some with small projects, some with large projects, some utilities, into something that's more like the UK market for other forms of power generation, like offshore wind and gas, where you've got the very big players dominating that sector.

23:12I think that's going to be a really interesting one to watch and see who decides that they're going to be that consolidator in the market. I'm not putting us up for that challenge yet, but I just think it's going to be a really interesting one to watch there's an interesting dynamic to play out there. Well, Chris, thank you so much. And it's great to have some smart gas guy join our family. Oh, you're more than welcome. Great having you, Chris. Thank you very much. Thank you, guys. Well, Gerard, I really enjoyed this one because hands-on, no nonsense, and their ambition, come on, I mean, like 40 football pitchers, 600 batteries next to another.

23:51I mean, it's the triumph of modularity. Repeat, repeat, repeat. And he said himself to build a one gigawatt battery is much simpler than to build a one gigawatt turbine. I get that. It's clear in my head. Like if you're talking about battery versus gas, the simplicity of these batteries is really unbelievable, right? I suppose I'm not convinced in this whole thing of when you compare a decentralized battery to a centralized. Now, I take his point, which is it's the economies of scale. Yeah, but where I'm coming from is we're going to have massive flexibility in the system, which is what I call behind the transformer.

24:30You know, whether that is EV batteries or large scale batteries in an industrial park. I can see the batteries being much more towards the low because, and that also from a risk management point of view, I just, I prefer to own a battery in those locations rather than the large scale ones. Now, you always call me Mr. Equity and you're Mr. Debt. So I'm now saying to you, I prefer the small ones because they're less risky. What's your reaction to that? Look, it's an industrial approach, which is transformational because those people are looking at brownfield sites, former coal plants, former gas plants, and we have a lot in Europe in general.

25:12and the fact that they can bring another cycle of life by using, honestly, some sites which are extremely dirty now and some connection which already exists, some permit that already exists, for me, that's a great approach. Now, are they going to make money or not? As you said, they have hedged 50 % of their future revenues and they've been able to raise debt without a problem. so I don't know what's the potential of those gigawatt scale batteries but what is for sure and especially because he said that okay so the first two, Thorpe March and West Burton, they are two hours but for the third one is already looking into four hours which means there's a lot of plan like long duration energy storage, a lot of those pump hydros.

26:03I don't think they're going to cycle a lot and in my opinion if you do a four days pump hydro yeah okay fine but if you want to do a 10 hour pump hydro it is financial suicide because those battery will eat their lunch every day yeah no this is clear for me is that there's no doubt about that they're more flexible and they're quicker i suppose the approach that i like from these guys is they come from the conventional world just said as well is when you come from that world you finance projects in a different way and you manage projects in a different way than a lot of the renewables infrastructure people so i do like that and i also realize as well is that what's very clear for me across europe and i'll start in the uk is that peak demand is is going to go through the roof in the next few years it's the peaks that will kill you and that's where these guys will make the money going forward is the peaks well Gerard we'd like to thank Chris Helder I really like what they're doing yeah and Chris just want to wish you all the best with this and keep in contact and I talk to you next week looking forward to it thank you for listening to Redefining Energy don't forget to rate the show and subscribe on Apple Podcasts Spotify or the platform of your choice

From the publisher
Battery Energy Storage Systems (BESS) were traditionally developed as portfolios of relatively small, MW-scale projects, reflecting the experience of renewable energy funds rooted in solar and wind. But a new generation of GW-scale projects is entering the market, led by developers with different backgrounds, industrial expertise and a fundamentally different view of scale: bigger is better.

Statera, Copenhagen Infrastructure Partners (CIP), Zenobē and Fidra Energy are emerging as major players, backed by infrastructure investors such as EQT, Ares and KKR. Fidra Energy is one of these new titans. Backed by EIG, with $27 billion in assets under management, and the UK National Wealth Fund, Fidra is pursuing an ambitious strategy in Great Britain, with just three projects in its pipeline, but on an unprecedented scale: the 1.45 GW / 2.9 GWh Thorpe Marsh project, the 500 MW / 1 GWh West Burton C project, and Enderby, a 1 GW project potentially offering four hours of storage.

A single project can occupy an area equivalent to around 40 football pitches. These are not simply larger versions of conventional battery installations. Their teams bring extensive gas industry experience and a different approach to engineering, project delivery and infrastructure development. 

They are also strategically located on brownfield sites, often former coal-fired power stations or gas plants, benefiting from existing grid connections, lower connection costs and shorter permitting timelines. Laurent and Gerard welcome Chris Elder, CEO of Fidra Energy, to explore what sets this new generation of projects apart and why scale is becoming such a competitive advantage. Despite their size, these projects can be highly bankable. Around 50% of future revenues can be secured through capacity payments and tolling agreements, providing the long-term visibility lenders need.

Thorpe Marsh demonstrates this: a consortium of 13 banks has committed £600 million in debt financing. We also examine one of the most critical decisions in delivering projects of this magnitude: battery supplier selection. Following a year-long tender process, Sungrow's PowerTitan 2.0 was selected for Thorpe Marsh. More than 600 twenty-foot containers will be installed on site, creating a significant logistical and construction challenge. Yet, as Chris explains, building a battery storage facility can be considerably simpler than delivering a gas-fired power plant.

Finally, we explore an energy system increasingly shaped by gigawatt-scale batteries. As these assets become central to grid stability, flexibility and renewable integration, Chris anticipates significant sector consolidation. Will a handful of large-scale developers come to dominate the market? And are GW-scale batteries set to become the backbone of tomorrow's electricity grid? It is a conversation about the people, capital, technology and industrial thinking driving the next chapter of battery energy storage.