  3. Data centers need to earn their power [partner content]
Open Circuit

20 Nov 2026 · 23m · 12 chapters

Episode artwork

Data centers need to earn their power [partner content]

In short

Data centers can avoid long grid-connection delays and reduce power costs by deploying large, dispatchable on-site energy assets (especially hundreds-of-MW batteries) and using software to orchestrate them for utilities, ISOs, and electricity markets.

Guests

Syed Medini, co-founder and CEO of Verse; background includes power systems engineering, electricity market design PhD-level research, PG&E power portfolio work, Tesla AutoBidder, AMS optimization software (acquired by Fluence), and chief digital officer scaling AI for batteries/renewables. Interviewer: Stephen Lacey.

Key claims

Most data center operators want compute, not power; flexibility is required to meet SLAs when utilities require curtailment. Large batteries enable faster interconnection and can reduce T&D/capacity charges. Policy momentum exists (FERC “bring your own flexibility/capacity”), but utility commission rules complicate execution.

Notable examples

100 MW example with curtailment (20 MW firm, 80 MW curtailed); Texas math showing household bills could rise ~$200/year without flexibility, but drop to ~$10–$11 with “bring your own capacity,” and further savings by avoiding transmission investments.

Written by AI. May contain mistakes.

Chapters

0:08

Syed Madini's Background in Power Markets

Learn about Syed Madini's journey and expertise in electricity markets.

“He started with an undergraduate degree in power systems engineering and a master's in electricity market design, then a PhD in applied operations research.”
2:34

The Shift to Serving Energy Buyers

Discover why Syed focused on creating solutions for energy buyers.

“What did you actually see happening in the market that made you focus on large buyers?”
3:30

Data Centers' Choice: Grid or Off-Grid

Explore the strategic choices data centers face regarding energy sourcing.

“For big electricity buyers, higher prices and more volatile markets meant more contracts to manage, more risk to track, and more complicated decisions.”
5:32

The Need for On-Site Energy Assets

Understand the importance of on-site energy assets for data centers.

“Historically, we've seen this as two ends of a spectrum.”
8:00

Overcoming Grid Connection Challenges

Examine how data centers can speed up grid connections through flexibility.

“We just published a paper detailing the math behind this.”
11:04

The Role of Policies in Flexibility Adoption

Learn about the policies affecting energy flexibility in the market.

“Yeah, I would say there's a lot of great work that's happening.”
14:00

The Benefits of a Distributed Grid

Discover how distributed grids can reduce costs and improve efficiency.

“that really eliminates a lot of the kind of extra costs in households for energy bills.”
16:42

The Evolution of Data Center Conversations

Learn about the shift in discussions surrounding data centers and flexibility.

“But obviously that momentum has changed because of the need for compute and compute as power.”
17:53

Building Companies in a Growth Phase

Understand the challenges and strategies of growing a tech company.

“That's another episode probably with somebody else.”
19:10

Optimism in the Power Industry

Explore the potential for modernization in the power grid amidst challenges.

“The current mood about data centers is pretty dark in this country.”
Show all 12 chapters
20:29

The Future of Data Centers and the Grid

Envision how data centers will evolve with flexibility and technology.

“A plain vanilla data center with no power, no flexibility, just connecting to the grid, it'll take years and years and it's not going to happen.”
21:47

Orchestration and Energy Management

Learn about the importance of orchestration in energy procurement and management.

“I think the grid, the modern grid, will be a grid that's extremely flexible, resilient, and distributed.”
A man walking through an airport, asking his phone a question

Ask about this episode

Get the gist, explore an idea or ask about something said.

Claude

On Open Circuit, what are the key points of this episode?

Searching your listening

Transcript

Automatic transcript. May contain errors.

0:01This is Partner Content from Latitude Studios. Syed Madini has spent a lot of his life trying to figure out how electricity markets work and how to make them work better. He started with an undergraduate degree in power systems engineering and a master's in electricity market design, then a PhD in applied operations research. Basically, he studied the grid from every angle. So I did all I could to train myself academically for designing and running power markets and power grids. Were you a power nerd, like, at an early age? What got you into this? I'm not going to say when I was three, I was in love with electricity markets.

0:40But during undergrad years in college, I really loved financial systems and markets. And I loved engineering, electricity markets combined both. But for Sien, the research was never the end goal. He wanted to put it to work in the real world. I didn't complete a PhD to be a professor, although my dad is a professor, is retired now. And I had that DNA. But for me, it's mostly applied. How do we apply these things? So he joined PG &E, helping manage the utility's power portfolio in California's wholesale electricity market. It allowed him to see how market theory held up when real money and real power assets were on the line.

1:22And from there, it evolved to how do we do this better? How do we build software using AI and all of those fancy things that we learn at school to make sure these large energy assets are run efficiently and they can be monetized properly in electricity markets. That question took him into the software business. At Tesla, he helped develop an early version of AutoBidder, a trading platform for large batteries. Then he led a startup called AMS, which built software to optimize distributed power assets. When AMS was acquired by Fluence, he became the chief digital officer, focusing on scaling AI solutions for batteries and renewables.

1:58Each company had a common mission, help owners of energy assets make more money in the power markets. But along the way, Sayed uncovered a blind spot. Those platforms and products, it would take large, big batteries and other renewables and try to monetize them in markets. So the end user essentially is the market bidding entity, the IPP, the developer, the trading shops, the supply side of the equation. And throughout those years, I realized that the buyer side of this equation is extremely underserved. So that was really the push for us to create Verse. Let's create a platform, a team, a product that takes all the complexity that energy buyers are facing with and make it go away.

2:47What did you actually see happening in the market that made you focus on large buyers? I would say in late 2022, the load growth story was already cemented. not because of just data centers, but because of the thesis of electrify everything. So we all knew that load is going to increase, prices are going to increase, the volatility in electricity markets are going to increase. Now we had an extreme catalyst, which was the birth of OpenAI and ChatGPT and therefore LLMs and AI and super intelligence. Now we're in this big, big kind of a massive problem that we're dealing with. But the trends were there.

3:30For big electricity buyers, higher prices and more volatile markets meant more contracts to manage, more risk to track, and more complicated decisions. Then AI turned up the pressure, and that also changed what happens at the site itself. You actually need to deploy physical assets because if you want to slash your costs by 20%, you can't just do it by reorienting your contracts or think differently about your risk management. You need physical assets that can operate on your key sites. And the operation yields to avoided T &D charges and capacity charges and reduces the cost. Historically, on-site assets like batteries were used for backup or managing monthly bills.

4:12But for data centers, they're the difference between connecting to the grid today or waiting five to seven years. It helps with the speed interconnection by showing I'm flexible, I can be dispatchable, and as a result, I can be on a more speedy path to get interconnection. And obviously, with all of these large assets, you can orchestrate them well to bring the bills down as well.

4:42Data centers have a stark choice. Wait years for the grid or go entirely off-grid. But there's a third pathway emerging, using flexible resources to earn a faster connection. In this episode, Syed Medini, the co-founder and CEO of Verse, talks with Stephen Lacey about what that flexibility strategy should look like. They talk about the role of batteries, the economic benefits, and why software is so critical to making it work. So our vision is to become a one-stop shop for these large enterprises that spend hundreds of millions of dollars, if not billions, on power, which is growing every minute.

5:27it.

5:33Historically, we've seen this as two ends of a spectrum. Either you sit and wait for the grid connection seven or however many years, or you build it entirely off grid, and you're saying that there's this third pathway, which is to become more flexible. So what are you seeing in terms of customer adoption in their willingness to be flexible, what kind of flexibility they're willing to tolerate on the data center side? Yeah. So I would say the majority of these customers, they don't want to be in the business of power. They want to be in the business of compute. But they're so entangled and you can't really separate them.

6:06So even data centers are measured in units of megawatts, how much power they're consuming. So with that mindset, their number one goal is to get connected to the grid sooner. And essentially at a high level, without going into too much details of the nitty-gritties of all the policy proceedings and the utility tariffs and what's happening, at a high level, the reason that the data center can get connected, if you look at the engineering problem associated with it, it could be there's not enough capacity and power at the grid level to serve that data center. Or it could be there may be enough power, but there might not be enough transmission and distribution infrastructure power lines to get power to your location.

6:47So in this case, what's happening is the data center cannot say, if I'm using a 100 megawatt example, cannot come forward and say, I'm just going to use 100 megawatts around the clock. They need to be curtailed. They might apply for 20 megawatts as firm power, and the 80 megawatts, they're going to say, cut the power from me. I'm fine. That doesn't add up with the SLAs they have. They can just compute by 80 % over a sustained period. So what happens is you need to equip them with on-site energy assets. And these energy assets, we're not talking about small batteries in a basement. We're talking about a couple of hundred megawatt systems, which five years ago, they would have been the largest in the world.

7:32Now they're behind a meter. So if you equip them with that system and you solve one of the most complicated problems that are out there, which is orchestrating these assets based on the data center needs, the utility needs, the grid needs, the ISO needs, and the market needs, and that's what we do through our software. If you do that, then you're not disrupting the energy usage of the data center. You're basically contributing and giving back to the grid. And in many cases, you can avoid investments in transmission and distribution infrastructure and really bring the bills down for the end customers.

8:07We just published a paper detailing the math behind this. So that's really the solution. And I would say there's a lot of willingness to adopt this in the market. But we've got to do a little bit more to make sure the rules are clear. And what is most complicated in orchestrating between market and customer and asset? Yeah, having worked in the world of battery operations and energy asset operations, let's say you deploy a 500 megawatt battery system. That's huge. Once you energize it, it's not going to do anything. It's just going to sit there and stare at you. By virtue of deploying a large battery, you haven't solved the problem.

8:48It really depends on how you operate it. And by operations, I mean every second, if not every millisecond, you need to tell it what to do. Essentially, you bought a car. It's on the parking lot. Well, you need a driver. And there's no human drivers here. It needs to be automated because the level of decision-making is every second. So what do you need to do? First, you need to serve the needs, in this case, let's say a hyperscaler, the needs of the hyperscaler in the data center. It could be AI load smoothing. It could be voltage stability. A lot of different things that they need. Backup power.

9:24So essentially, you need to operate the assets every second to serve the host customer. And the promises you made to the utility by avoiding T &D and by avoiding hours of consumption on hours when the grid is stressed, you need to fulfill it. So that means any custom tariffs that the utility imposes, any CP charges, coincident peak charges, any demand charges which are essentially a symbol of when the grid is stressed, and managing the power at the interconnection lines, you need these assets to operate. Transmission systems are congested. Fire up the battery so you can alleviate that transmission bottleneck and without cutting the power from the data center and call it a success.

10:15So that's a whole host of requirements. And then you also want to give back to power markets. You want to participate in capacity markets, energy markets, demand response markets, ancillary service markets. So when you stack them all up, this technology problem is extremely massive. There's a AI and intelligence problem, and then there's a control problem. So we essentially stack all of that up. And in a seamless over-the-air kind of deployment, we can make these large physical systems cooperate and work seamlessly as possible. We have this commercial pull right now where data center owner operators clearly see the value and flexibility for both speed and operational cost.

11:00What about the push from the market? What are you out in the market in terms of policy regulation that is making flexibility necessary? Yeah, I would say there's a lot of great work that's happening. I mean, FERC, essentially all these proceedings around bringing your own new capacity or bringing your own flexibility, it's happening at the FERC level. They get different forms and flavors, but fundamentally all they're saying is you got to get curtailed. You can connect now, but you got to get curtailed, go and equip yourself with flexibility so you don't ruin your SLAs. That's essentially the fundamental message.

11:35So, so far, so good. But then at the end of the day, the entity that you're dealing with in a connection are the utilities. And we all know that ISOs don't have jurisdiction over the utilities. It's the commissions. So, that line of command really breaks down between the final level of implementation between high-level policies and the utility kind of execution. So that's why the commissions are involved, and each utility has its own taste and flavor. And to the extent we can streamline all of this, that will be phenomenal. Because, you know, I always say, you know, the vision of moving towards a distributed grid, it's not news.

12:17I mean, people have been writing papers about it for decades. Now we're at this place that the world's largest financial institutions are willing to finance this distributed grid for the sake of getting power sooner. It will be a shame if we fumble at the five-yard line. We just need to make sure the policies are there. Because at the end of the day, this absolutely helps regular households to bring their costs down. So why not do both? win the AI race and bring their costs down and make sure we double down on this. You studied the value of flexibility in Texas. What did you find in terms of how it could potentially bring bills down in the state?

12:57Yeah, basically what we found is, and it's all published on our website, I had my team of PhDs in power markets essentially do this math, because what we wanted to answer was, what does good look like? We all know if we add 480 gigawatts in Texas in form of data centers, it's not rocket science to understand that's going to drive up power prices because new generation needs to be invested in, new transmission lines needs to be invested in, the utilities take their rate base, and they essentially socialize it across everyone. That should not happen. Because if that happens, we're talking about every household in Texas will increase their utility bill by 200 bucks a year.

13:42That doesn't work. It's not good for everyone. And I don't think any of the hyperscalers have that intention and they want to avoid that. So the next phase of this is what if these data centers bring their own power? What that means is they invest in generation capacity anywhere on the grid. And that helps. that really eliminates a lot of the kind of extra costs in households for energy bills. To the extent from$200 for if we're adding 10 gigawatts of data centers, that brings it down to$10 or$11. But the next level is bring your own capacity and bring it on site and create that flexibility, meaning that you're seamlessly operating to avoid any bottlenecks in the transmission system to get power to your location.

14:29Not only you're avoiding investments in generation capacity, but you're also avoiding investments in transmission systems. That actually helps by reducing the bill for the end customer because you're avoiding investments in transmission systems, which everybody needs to pay for. So those are the benefits of a distributed grid. Again, not rocket science. And we're at the moment that a lot of folks are willing to finance this, but we just need to make it happen. I'm curious about what you're hearing from customers about whether they think they'll be off-grid permanently or whether they'll eventually connect to the grid.

15:10What do you think that bridge to the grid looks like? And will we see a lot more development that is separated from the grid? Yeah, I personally don't think anybody has a desire to be off-grid. They see more work. They see total independence, which they need to, you know, getting to the 99.99999 % SLAs reads. These are not microgrids. They're macrogrids that we're talking about. They're large power systems that people are thinking about building. We support them as well. But I think inherently people see that as a last resort. So if we can fundamentally clean up the rules and make sure that these assets can be connected with the flexibility, I don't think people have this secret desire to go off-grid.

15:57They're doing it based on necessity. And how do we streamline it? It's going to be the key question that is out there. How quickly has this conversation moved? It felt like overnight data center developers were taking batteries very seriously. Sometime in the last year, demand and interest really picked up. What did you see from your side? Was it happening well before that? And we've had this academic conversation for a while on the value of flexibility, but now the rubber is truly meeting the road. So I'm just curious about how you have seen this conversation and ultimately execution advance in the last year or two.

16:32I would say the concepts that we're talking about, if we were talking about this 10 years ago, it would have been the same, but we would not be using the word data center. We were talking about large load, the benefit of a distributed grid, DERs for bringing down essentially non-wires alternatives, which was around 15 years ago. But obviously that momentum has changed because of the need for compute and compute as power. So, I would say the conversations have picked up massively in the past 12 months, in particular as we're seeing these policy proceedings, are overall moving in the right direction by advocating for a data center that's independent, brings their own power, brings their own flexibility.

17:17So compared to 12 months ago, I would say a lot of major improvements. So we're at the final line of making sure the utilities adopt what the right framework is for the final layer of execution and interconnection. So that's all good. So compared to power system years, we have accelerated a lot. But compared to AI years, still a dinosaur. So I think that's the fundamental cultural shift that we need to make, which is in order to win this race, you can argue this is a good race or a bad race. That's another episode probably with somebody else. But if we argue we want to win this race, then we need to act much, much faster.

18:04What's it like building a company right now that's right in the center of growth? growth. You've gone from 25 to 65 people in the last year. You're expanding really quickly. What is that ride like right now? Yeah, I mean, that's kind of the fundamental, like, you know, building companies are art and science. The science, you can kind of think about your burn and what type of engineers you need, what's your go-to-market strategy. The art is making sure you put your foot on the gas pedal when it's needed. I've seen a lot of companies fail by over-hiring at the wrong time, by under-hiring at the wrong time.

18:45So we took a more measured approach. Once our committed backlog grew significantly, then that was time which we had to execute. And right now we're in that phase. All of this orchestration and flexibility doesn't fall from the sky. It takes a lot of smart people to put together these essentially engineering layers of software in AI to make it happen. The current mood about data centers is pretty dark in this country. Lots of claims about data centers raising power prices, you know, sucking up resource use, etc. And so I think there are people in the power industry who see this as a really optimistic moment.

19:28I'm certainly not discounting some of the issues related to large-scale data center development, but seeing this as a chance to modernize the grid, to execute on the concepts that we've been talking about for years around distributed power and flexibility. And I'm curious about where you sit on that spectrum. How optimistic are you that we could use this moment to advance the grid in ways that we've been talking about for years? I'm very optimistic because it's not just a policy issue anymore. It's not bringing ISOs and utilities in a room and raising the fact, and we think about this differently.

20:06There is a strong business need associated with it. Whenever there's a business opportunity, I think the opportunities just naturally increase. For all the folks out there listening to this, absolutely true. Just a plain vanilla data center would increase costs, and nobody wants that. Nobody can argue against that. But I don't think that's going to happen. A plain vanilla data center with no power, no flexibility, just connecting to the grid, it'll take years and years and it's not going to happen. So we're in this moment now that flexibility is key and flexibility is what's going to help you bring your costs down.

20:48So as a person that's worked in this space, I can stand behind our numbers and basically say, if you deploy large DERs and if you operate them well, we're going to get a more modern power system and we're going to bring costs down. Now, somebody's paying for it for that essentially DER infrastructure. Those are the ones that have the business opportunity and they're willing to do it. Pick a date, let's say 2027. What percentage of data centers are going to have some flexibility component built into them? I would say 100 % of data centers that go online are going to have a flexibility. Now, the question is, how many are going to go online?

21:27How many do you think? I would say 10 to 20, but we'll see. Yeah. So paint your vision for the future grid. You've been at this for a while, five years from now, as we see these large loads become more interactive with the grid. What does that enable? What does the system itself look like to you? Yeah, I mean, about 10 years ago, I said the future of the grid are batteries and advanced energy assets all distributed with a bunch of algorithms. I think we're getting to there. I think the grid, the modern grid, will be a grid that's extremely flexible, resilient, and distributed. I think there's no question to ask.

22:07And the way we want to play in this space is not only think about the orchestration that benefits our customers and the grid, but also serve the other bits and pieces of what the customers want. We talked a lot about the orchestration, but that just doesn't end there. Folks need power procurement. Folks need risk management. Folks need contract management. So we've essentially pumped out these products. It's a cliche statement, but that's how you become the operating system for energy as it relates to enterprise. I mean, today we're managing 30 gigawatts, which is 14 Hoover dams. And I think in five years, those numbers are going to increase tremendously.

22:44Sayed, thank you so much. Sayed Medini is the co-founder and CEO of Vers. The company develops software to help large electricity buyers manage power procurement, contracts, and financial risk. And coordinate on-site energy assets like batteries. Versus Dispatch Intelligence Platform is designed to operate those assets for the benefit of customers and the grid. Learn more at vers.inc or follow the link in the show notes.

From the publisher

Data center developers face a difficult choice: wait years for a traditional grid connection, or build their own power systems and operate independently of the grid. 

But a third path is emerging. By bringing onsite generation, batteries, and sophisticated software controls, data centers can be more flexible when the grid is constrained — and potentially connect to the system faster.

But batteries alone don't make a data center flexible. They need to be coordinated in real time to meet the demands of the facility, the utility, and the broader electricity market.

And the stakes go well beyond the data center industry. If these new loads can help utilities avoid expensive infrastructure upgrades, they could also help limit electricity bill increases for a wider range of consumers.

In this partner episode, produced in collaboration with Verse, Stephen Lacey talks with Seyed Madaeni, co-founder and CEO of Verse. 

They talk about the growing role of flexibility in connecting data centers. How do we ensure the rush to power AI allows us to build a more distributed, resilient, and affordable electricity system?

This episode was produced in partnership with Verse. Verse helps large energy buyers secure power faster and manage electricity costs through intelligent software that optimizes energy procurement, batteries, and onsite power assets. Learn how Verse is helping data centers unlock faster grid connections through flexibility.