In short

Odd Lots Podcast Episode Summary

Episode Title

Here's What's Going Wrong in the US Offshore Wind Industry

Hosts

Joe Weisenthal & Tracy Alloway

Guest

Chelsea Jean-Michel, Offshore Wind Industry Analyst at BloombergNEF

---

Overview In this episode, the hosts delve into the current challenges facing the US offshore wind industry, particularly in light of recent setbacks such as Orsted's decision to withdraw from a major project off the coast of New Jersey. The discussion highlights the interplay between economic factors—like rising costs and interest rates—and the structural issues of offshore wind development.

Key Themes

  • Offshore Wind Industry Setbacks:
  • Notable declines in the stock performance of key players like Orsted, which is down 50% year-to-date.
  • Challenges include high commodity costs, lack of installation vessels, and unfavorable bidding processes.
  • Current Economic Environment:
  • Higher interest rates are impacting the financial viability of projects which rely on long-term contracting and financing.
  • Inflationary pressures are increasing operational and capital expenditures.
  • Project Development Complexities:
  • The lengthy timeline for offshore wind project development in the US can stretch up to 14 years, causing risks related to changing economic conditions.
  • Key components such as seabed leasing, component costs (turbines, cables), and permitting contribute to development challenges.

---

Discussion Highlights

Factors Contributing to the Current Crisis

  • Interest Rates and Inflation:
  • Interest rates have surged from nearly 0% in 2021 to around 5.5% in 2023, significantly raising the financing costs for developers.
  • Operational costs have also increased due to inflation, with the Levelized Cost of Electricity (LCOE) for offshore wind rising from about $77.30 to $114.20 per megawatt hour since 2021.
  • Of-Take Agreements:
  • The lack of inflation-indexed offtake agreements in the US creates financial vulnerability for projects, unlike models used in the UK and other countries that protect against inflation over the life of contracts.

Regulatory and Structural Issues

  • Jones Act Constraints:
  • The Jones Act mandates that vessels used for offshore operations must be US-built, crewed, and flagged, posing significant supply chain challenges since there is a lack of suitable vessels in the US market.
  • Alternative strategies, such as using feeder barges and European vessels, are being considered but complicate logistics.
  • Renegotiation Challenges:
  • Developers are seeking to renegotiate contracts to account for rising costs, but regulatory bodies are often resistant, fearing that this undermines the competitive bidding process.

Industry Future and Strategic Importance

  • Importance of Offshore Wind:
  • Offshore wind is seen as critical for the US's energy transition, particularly in regions like the Northeast where alternatives are limited and energy demand spikes during winter.
  • The future of the industry will hinge on addressing regulatory hurdles, improving infrastructure, and adapting to changing economic conditions.

---

Key Takeaways

  • Complexity of Development: The offshore wind industry is impacted by a blend of economic, regulatory, and operational challenges, necessitating a multi-faceted approach to problem-solving.
  • Critical Role of Government Policies: State-level actions, such as implementing inflation adjustment mechanisms for contracts, could significantly alleviate financial pressures.
  • Need for Innovation and Standardization: The industry must explore innovative solutions for technology adoption and cost standardization to improve financial viability and project execution.

---

Conclusion The conversation with Chelsea Jean-Michel underscores the pressing issues facing the offshore wind industry in the US and the potential pathways to address them. As the industry navigates these challenges, the outcome will be pivotal for the broader goals of decarbonization and energy sustainability in the country.

---

For more insights and discussions, follow the Odd Lots podcast on [Bloomberg](https://www.bloomberg.com) and join related discussions on Discord.

Written by AI. May contain mistakes. Listen to the episode to check what was said.

Hear the part that matters, and keep it.Open this episode in VO. Double tap your headphones to save a moment as you listen.
Get VO free

Transcript

Automatic transcript. May contain errors.

0:00You're being sold an AI future where you're obsolete or irrelevant. That vision is wrong. At Palantir, they're building AI that helps workers and unlocks their full potential. American workers are our nation's greatest strength. AI shouldn't eliminate them. It should elevate them. Palantir is here to tell their stories. From factories to hospitals, AI is freeing people from drudgery, letting them do what humans do best. Create. Solve. Build. Palantir, making Americans irreplaceable.

1:01business smartphone plan savings. Terms apply.

1:14Hello and welcome to another episode of the Odd Lots podcast. I'm Jill Weisenthal. And I'm Tracy Alloway. Tracy, I have to say there are a lot of exciting things happening in energy, decarbonization, electrification of the grid, things we've talked about recently with people like Jigar Shah and so forth. But I have to say, I keep seeing negative headlines about wind. Oh, my gosh. You know, just before we came in studio to record this, I was taking a look at the S &P Global Clean Energy Index. Yeah. It's down 30 percent this year, more than 30 percent this year. And a lot of that is thanks to what's been going on in wind.

1:53And in fact, if you look at Orsted, which I think is the world's biggest provider of offshore wind farms. It's down 50 % year to date. Yes. So we are recording this November 15th. I think just earlier in the week, two top Orsted executives departed the company. I think there was a project off the shore of, I think, New Jersey that recently the plug was pulled on. And it just seems that every story everywhere around the world, with the exception maybe of China, it seems to be something seems to be wrong, whether it's the math doesn't pencil out on the actual projects themselves. There are companies, I think Siemens Wind has had all kinds of manufacturing issues with respect to turbines, et cetera.

2:39And so just trying to understand what is going on with this industry and how bad is it in terms of if it's not going as planned, reaching our decarbonization goals as a country. Yeah. So my understanding is there are two things kind of happening at once. You could say two headwinds for the wind power industry, creating a perfect storm, Joe. I'm just going to get a perfect storm would be good for wind. I'm just going to get as many weather puns as I can into this conversation. But there's higher borrowing costs because of surging interest rates. And then there are also higher component costs. Yes.

3:13And I guess my question is, how much of all of this is sort of growing pains for an industry that at least in the U.S. is still relatively new, although it is true that it's also facing problems in places like the U.K.? Or is this a kind of permanent change in the industry's trajection? Basically, is wind power a low interest rate phenomenon like, I don't know, WeWork or cheaper Ubers? Is wind power a lot of hot air? You know, you mentioned the renewable energy stocks. And that is sort of another, I don't know if funny is the right word, but we're having this great year in the stock market so far.

3:54And how many people would have bet? It's like, oh, the Inflation Reduction Act passed, all this money pouring into renewable energy, all these incentives, can't lose betting on these companies and wind and I think solar. I mean, it's been pretty dismal. Yeah, absolutely. And wind especially was like a much hyped component of the renewable energy revolution. And you're right. With the Inflation Reduction Act, there is this question about how much of this is a temporary holdup given permitting issues that we've discussed with people like Jigar versus how much of this is the math just doesn't pencil out.

4:29There is something fundamentally challenging in wind. Lots of questions. And we have the perfect guest to get the answers. We're going to be speaking with Chelsea Jean-Michel. She is an offshore wind analyst here at Bloomberg NEF, one of our colleagues on a different floor. So excited to chat. Chelsea, thank you so much for coming on OddLot. Thanks so much for having me, Joe and Tracy. Is our premise correct, more or less, that it's been a just dismal year for the industry? I think dismal is a bit of a big word to use, but, you know, it hasn't been great. And there have been a lot of negative headlines, and you guys highlighted a lot of the key issues already.

5:08I think maybe to highlight at a grander scale, we have seen a lot of the impacts most saliently in the U.S. And Tracy, you mentioned, you know, it's a very new industry in the U.S. For context, there's only seven operational turbines, 42 megawatts installed. However, there are two offshore wind farms currently under construction right now, almost a gigawatt. So the industry is growing, but we've also seen over 12 gigawatts of offshore wind projects seek to cancel or renegotiate their offtake contracts in the U.S. Now, what I mean when I say an offtake contract is that's typically an agreement that these offshore wind developers, their projects will sign with states, state utilities to essentially guarantee that they're going to buy their power for usually around 20 to 25 years.

5:53And that's really key for an offshore wind project because they need, you know, you have variable generation. So if you can't guarantee your generation, you can guarantee the price at which that generation is sold. And that makes it easier for these projects to reach financial close, make a business case for them. Now in the U.S., this is interesting because this happens a little bit earlier on in a project's process. So in the U.K., before you bid for an off-take contract, you need to have a grid connection agreement. You also need to have your permits in. In the U.S., that's not needed. And so you might have a couple of years when between when you lock in your off-date contract until you finally reach financial close and then you want to construct and build the project.

6:30So that leads to a certain level of risk that's a little bit higher in the U.S. than you see in other parts of the world. And that's also why, you know, we've seen just how much interest rates have shifted over the last few years, how much inflation has changed. And that has meant that now when these projects are looking to reach financial close, they're in a different macroeconomic environment than when they had initially placed their bids and made those assumptions back in 2019, 2020. Oh, that's really interesting because I was wondering how higher rates are actually feeding into a lot of this.

6:58You would have assumed that the financing was in place, but you're highlighting the discrepancy between the revenue coming in through the offtake agreements and the financing that is still coming up in the higher interest rate environment. So just on this note, could you maybe tell us like the factors or the calculations that go into creating a wind farm, whether it's onshore or offshore? Like if Joe and I were at a bar and we were riding on a napkin, here's our rough cost and here's like our rough revenue source. What would that napkin actually contain? Yeah, so there's a lot that goes into it.

7:35And it depends on, you know, if you're building in the U.S. versus if you're building, say, in the Netherlands or in Germany. We're building in the U.S. We're building in the U.S. Yeah, so if we're building in the U.S., right, for context, offshore wind development takes a really long time. As I mentioned, there's very few projects currently operational in the U.S. right now. But around eight to 10 years is what we see globally. But in the U.S., you know, this can take as long as 14 years. We've seen that for some other projects that are currently in the process of getting built right now. But when you take a look at that really long process, one of the first things you think about is, okay, so that's like 10 years where you have like development costs going in, right?

8:16So you need the people that are going to help formulate the bids. In the U.S., you have a seabed lease auction. So this is usually the first step in the process where you're like, I want to acquire my seabed for X amount of dollars. We recently saw the New York Bight Lease auction last year. Millions and millions of dollars of revenue for the U.S. government, over$4 billion to secure these sites. And that's just step one. And then you also have... Can I ask really quickly, does the U.S. government own all the seabeds? On the Outer Continental Shelf, they do. However, that being said, I think it's three nautical miles.

8:47That's state waters, but most offshore wind development is going to take place in federal waters. Ah, yes. I remember this from my offshore gambling days. But yeah, so that's like a cost you can expect to pay for the seabed. Then you have kind of other development costs when it comes to, you know, bidding into an offshore wind procurement or bidding into an offshore wind solicitation. So this is where you go in to say, I will bid X price, I will bid Y price, I'll bid Z price for, you know, this offtake contract that we've talked about in state solicitations. And so that takes also some costs. Now, you have costs over the development lifetime.

9:22Then let's say you get to the point where you need to reach financial close and actually build that project. So let's talk about the equipment costs. This includes your turbines. This includes your foundations. This includes your transition pieces, which are kind of, you know, the pieces that exactly what they sound like transition from the foundation into the turbine. You have your array cables, which connect the turbines to each other. You have your offshore substation, which kind of collects all the power within the offshore wind farm to then get it ready to transmit to shore. Then you have your offshore cable, onshore substation, et cetera, et cetera.

9:53So part of the reason why I mentioned, you know, the Netherlands and Germany is because these are markets where they pay for offshore transmission. In the U.S., that responsibility falls on the developer. And then, of course, you know, as you're financing the project, you also have different financing costs involved with that. So if you're using project finance and you're going to go to the bank, then you have to factor in the payments that you're going to be making to pay off your loan. And if you're talking about lifetime costs, renewable energy is great because you don't have to pay for fuel costs.

10:19But that being said, you do have some O &M, so some operations and maintenance that you need to take care of as well. This seems complicated, Joe. It's so complicated. Also, you know how every once in a while, Tracy, you try to convince me to write a book? Yeah, with me, to be clear. With you. And the reason I can't do a project that's going to take two years, that's just too long. And so when I hear, oh, the process is going to be 10 to 14 years, I can't even imagine thinking about starting out a project 10 to 14 years. I can't even do a two-year project. So just that blows my mind. But when you're talking about such long development timelines, it really drives home how much financing costs can matter.

11:02And that's a lot of time where you're spending a lot of money on various things without revenue. And the whole math changes with the change in financing conditions. But why don't you talk to us about, okay, what are the conditions for these developers in 2023 versus 2019, both in terms of the rate environment, but also just the inflation environment, the cost of labor, the cost of construction, the cost of steel for the materials and so forth? How much have things changed for them in four years or three years? significantly. I actually I have those numbers when we're talking about the impact that inflation interest rates and also you mentioned, Tracy, the Inflation Reduction Act have had on the levelized cost of electricity.

11:45So what this means is this is essentially the price at which electricity must be sold in order to kind of break even, make sure your returns are met, etc. So in 2021, we did some analysis estimating that the LCOE for offshore wind projects in the U.S., assuming a 30 % investment tax credit. So this is investment tax credits as allowed in the Inflation Reduction Act, was around$77.30. So this is assuming a 30 % ITC. If you take into account CapEx and OpEx rise, so OpEx being operational expenditure, this added around$17 per megawatt hour. Then take into account interest rate hikes, that's around$27 per megawatt hour.

12:25But then we also had, when the IRA came out, bonus tax credits, so developers could also get plus 10 % for meeting certain requirements. That took down, so it reduced the levelized cost of electricity by around$7 per megawatt hour. So when we're sitting here in 2023, this means that now the LCOE, assuming a 40 % investment tax credit, stands around$114.20 per megawatt hour. So you can see comparing that$114 to that$77 per megawatt hour number, just how much that environment has changed. And I think to highlight a couple of, you know, movement pieces in terms of, you know, what has been happening on a macroeconomic scale.

13:06So U.S. CPI, so this is, you know, consumer price indexed, averaged at around 1.9 % before COVID-19 in 2019. And then if you take a look at how it peaked in 2022, it was at around 9%. And so you can really see how that environment has shifted. Also, for several projects, the secured overnight financing rate, so this is the base rate for interest rates in the US, stood at around 0%, almost nothing in, you know, kind of end 2020 into 2021. And then when you take a look at where it is in 2023, it's, you know, around 5.5%. And so you can see just how much the base rate for, you know, borrowing money has increased.

13:44Wow. It's like a almost 50 percent increase in the cost, which is almost perfectly tallied with the drop in Orsted's share price. Oh, perfect. Yeah. Efficient markets right there.

14:10Silicon Valley is selling you a future where you're obsolete, or worse, identical. At Palantir, they're witnessing something different and revolutionary, From re-industrializing the nation's defense base to shipyard workers building faster and frontline workers boosting productivity, AI is transforming work across the nation. AI is not replacing American workers or flattening them into conformity. It's unleashing what makes each one irreplaceable. Their judgment, their craft, their creativity. When American workers become more powerfully themselves, they own the future. Palantir, making Americans irreplaceable.

15:18leading 3.6 % APY high yield cash account. Switch to the platform built for those who take investing seriously. Go to public.com slash market and earn an uncapped 1 % bonus when you transfer your portfolio. That's public.com slash market. Paid for by public investing. All investing involves the risk of loss, including loss of principal. Brokered services for U.S. listed registered securities, options, and bonds in a self-directed account are offered by Public Investing, Inc., Member FINRA and SIPC. Crypto trading provided by XeroHash. Complete disclosures available at public.com slash disclosures.

15:52Okay, so you just laid out wonderfully all the different cost pressures that have landed on the wind industry. And I guess my question now is, what levers can they pull to offset some of these? So, you know, you have fixed rates on the revenue side because of those offtake agreements. can they renegotiate to try to get additional money? And then on the cost side, I imagine putting together these massive wind turbines is a pretty expensive and complicated endeavor. But we have seen, for instance, in the oil industry that you can do things like have standardization on components and things like that that can bring down costs.

16:37So which of these is the industry looking at? Which, in your opinion, might be most effective here? So I think what comes to mind are three things. So one, the first you mentioned being renegotiation. So that's what a lot of these developers have been trying to do. So far, not really any of the renegotiation attempts have been successful. We did see some green lights in New Jersey when Orsted requested basically being able to keep some of the upside of their federal tax credits. So traditionally in their contracts, they're meant to pass down those benefits to ratepayers if they're going to get any extra access.

17:13But New Jersey kind of passed a bill saying that, no, this is OK. Orsted can keep the upside to make sure that that project goes forward. Now, even though that bill passed and Orsted was able to receive the upside, that project still did not go through. If we take a look at renegotiation attempts in Massachusetts, the regulators had also said, no, we're not willing to renegotiate. And so then we saw fines of around$50 million,$60 million that these developers were paying to kind of exit those agreements so that they could then rebid into future solicitations. In New York, we also saw regulators decline requests to increase offtake prices.

17:50And so for New York, we're still waiting to see what exactly might happen. But basically renegotiating kind of opens up a whole can of worms because this is a competitive process that these developers are competing against each other for. And then the second you reopen that up to say, oh, I want a higher offtake price, then that kind of calls into question the competitive nature of the award. Wait, sorry. Explain that further when you say it calls into question. Can you clarify that? Yeah. So essentially when we see something like an offshore wind solicitation, I've been using a lot of different words, solicitation, procurement.

18:19They're also known as request for proposals, RFP. Some people might call them an auction. So these are essentially developers coming in. The state says, I want to procure, let's say, four gigawatts of electricity of offshore wind power. And so then you'll have multiple developers kind of develop a proposal with different projects. They'll say, I'm developing a one gigawatt project. I'm developing a 500 megawatt project, et cetera. They'll then say, I'm willing to provide this project at, let's say,$100 per megawatt hour. And this project is going to commission in 2030. And so then you'll have all of these different elements.

18:52Now, usually in the U.S., they'll take into account the bid price. So the lower your price, you know, the more that you can save a rate payer's money. And so then the better that looks. So that's usually around maybe 70 percent of the evaluation. And then you'll have 30 percent be attributed to things like environmental attributes, economic development opportunities. How much are you investing in the state? Also things like project viability, developer experience, different pieces like that. But the big portion is how cheap can you, you know, sell electricity to me? And so when you have these different developers essentially saying, I can sell it at this price and this is the lowest one or this is the most attractive one that the state selected, you award it and then a couple years later you say, oh, I need an increase.

19:36Then that calls into question, okay, what about the previous developers that lost out in the auction? Were they bidding at a price because perhaps they had less optimistic assumptions about what the future would be like? Yeah, their math was better. Exactly. Right. So when you think about contingency planning, things like that, it's good to have an optimistic view of the future. But when the optimistic view doesn't actually end up happening, then that kind of, you know, makes it a little bit more difficult. And what about on the supply side, like the component idea? How much can be squeezed out of costs there?

20:08That is a great question. So a lot of the cost declines we've seen in offshore wind has been due to increasing sizes in turbines. And so what that means is that as a turbine gets bigger, that means that oftentimes you need less turbines for the same amount of output. So for, you know, a one gigawatt wind farm, you need less turbines if you have bigger turbines at higher rated capacities. You also need less array cables to interconnect them, less foundations, oftentimes less vessel trips needed to, you know, go in and install the turbines because there's fewer of them. So with that being said, you know, sometimes when you have this longer runway for offshore wind development, that means, oh, OK, well, I have a little bit longer time to kind of pick the biggest, newest technology that is going to allow for cost savings on a per megawatt basis.

20:55Now, that being said, a lot of these projects that have been raising red flags are a little bit more in the later stages. And so kind of, you know, reconfiguring and getting the newest and biggest turbine or signing new supplier agreements and, you know, trying to figure out where to squeeze can be a little bit more challenging. Because oftentimes a lot of these supplier agreements are already being put in place or have already been put in place. So this was the case for Ocean Wind 1 and 2, where if you take a look at Orsted's impairment, the vast majority of it was due to supply chain complications, mostly in Ocean Wind 1.

21:26And this is because they experienced kind of knock-on effects from delays and kind of scheduling issues that they were having with suppliers, predominantly with vessels. And so there is some wiggle room that you can do with reconfiguration and redesigning, you know, the project. We have seen, you know, I mean, Orsted mentioned for their Skipjack projects in Maryland that they are revisiting some reconfiguration to see if they can, you know, make the project as valuable as possible. But that being said, for some projects, it's not always possible. Sometimes you reconfigure as much as you can until you kind of have to make a final investment decision.

22:01And for some projects, you have less runway. So if you're early on in the development process, then you have more leeway to shift, you know, your designs and change your suppliers. But if you're later on, it's a little bit more challenging. So you mentioned supply chains. And the big stress point has actually been the vessels. For Orsted's Ocean Wind 1 and 2, that's what they mentioned. Was that the one that was going to be off of New Jersey? Yes. And wait, what's the vessel constraint? Is it actually the number of ships? Yeah, what's going on there? Yeah, so the U.S. has essentially this law called the Jones Act.

22:33I'm not sure. Are you guys familiar? Oh, we love it. It always comes back. It always comes back to the Jones Act. No, we've done a couple episodes. I had no idea this was going to turn into a Jones Act episode. Now I'm really excited. So I have my own personal feelings about it. But that aside. I've noticed, by the way, like on social media, that's one of the most hot button topics that you can talk about. So you never say anything about the Jones Act online. People have really strong opinions. OK, sorry. Go on. No worries. I mean, it's a hot button topic. So essentially, basically, if you are traveling between two points in the U.S., then that ship has to be U.S.

23:12build, U.S. crewed, U.S. flagged. And what that means for offshore wind is that that offshore wind farm counts as a point. And so the U.S. has, you know, I mentioned seven turbines currently installed, two projects currently under construction. But what happens is because of the Jones Act, you either have to have a Jones Act compliant vessel that can do that transportation. That doesn't exist in the U.S. right now. Currently, there's only one wind turbine installation vessel that Dominion is building right now. I'm getting dredging. This is so amazing. It all comes full circle. So, yeah, there's only one vessel currently under construction right now, and that's not going to be ready until a few years from now.

23:55And Dominion's planning on using that on their 2.6 gigawatt coastal Virginia offshore wind project set to be the largest in the U.S. when it commissions, one of the largest in the world, which is great for them. But for other projects, Orsted was actually hoping to use this for their Sunrise Wind and Revolution Wind projects. But now that the vessel has been delayed, they are no longer able to use that Jones Act compliant wind turbine installation vessel. So another thing that you can consider doing is using a European wind turbine installation vessel and then using a kind of like feeder barge method.

24:24And so this is what a lot of U.S. offshore wind projects are hoping to do. Essentially, the feeder barges are Jones Act compliant and you feed in the components to the European vessel that stays at the offshore wind site. This is traditionally not how projects are installed in Europe, as you might imagine. Usually the European WTIV will go to the port, pick up the components, load it up, go to site and then install the components. And so you kind of have this mishmash way of doing things. And then the last one that we don't really expect to see because it's super expensive, but you might stage your components in, say, Canada and then use a European WTIV and then go get the components and then install them.

Read the full transcript

25:01So the Jones Act has essentially created a situation where so many vessels involved in the offshore wind installation process need to be built here. And right now there's only one. So that's a huge constraint. Joe, I dare you to tweet that the Jones Act causes pollution and adds to the U.S.'s carbon load by denying wind energy. I'll tweet it from my locked alt account that nobody knows about. OK, but this actually leads nicely into another question. Just going back to the IRA, a lot of this sounds like difficulty with how the U.S. system is set up for wind power. So you have the ship constraints via the Jones Act that you just described.

25:42And then you have the permitting process, which can also be difficult. You have the sort of time discrepancy between when the offtake agreements are agreed and when the financing is actually secured, which is different to other countries, different types of subsidies and things like that. How much can the government do to alleviate some of these pressures? And then on the IRA specifically, setting the griping aside about the permitting process, what does it actually do to help win power here? Does the existence of a very large underwriter in the form of the U.S. government provide some certainty to the industry at a time when it seems like there are a lot of challenges?

26:25Yeah, so I think that you mentioned like what can governments do? So I think going back to one of your initial questions that I think that I'd end up missing at some point, starting at the state level, what states have begun to do is starting to introduce inflation adjustment mechanisms in their offtake contracts. And so the U.S., I mentioned having that timeline between being so long between when you agree with that offtake to the offtake price and then when you actually finance the project being really long, that makes it really risky. But also another piece is that the U.S. offtake contracts are not indexed to inflation.

26:59And so what that means is that in the UK, in Poland, partially in Ireland, over the 20, you know, 15, 20, 25 year offtake contract lifetime, the price might go up by a certain percentage that is usually up by inflation. In the U.S., these projects bid at like a flat price or at a set escalator, say two or three percent. And so, again, given the shifts that we've seen in the environment over the last few years, this means that these projects are not nearly as protected as they are elsewhere. And so states have been starting to say, OK, we're not necessarily going to index this price over the lifetime of the contract, but we will say we'll give you a one time adjustment mechanism.

27:41And so in New York, what this means is from the time that you bid until the time you receive your final federal permits, your price will be indexed to metrics like steel, labor, fuel, copper, different pieces like this to help kind of protect the developers a little bit more and stave off a little bit more of that risk. So that's one beneficial thing that we've seen kind of help in this way at the state level. Now, at the federal level for the Inflation Reduction Act, a lot of the big drivers for offshore wind have, you know, has been at the state level. And so, you know, the Biden administration came out with a 30 gigawatts of offshore wind by 2030 goal a few years ago.

28:18And that's a good sign for the industry. But in reality, these offtake agreements that are really what, you know, these developers need, a guarantee of like route to market and, you know, a future for like how much build is going to be. Is there going to be in the future? You know, that kind of long term certainty, that's what the states have really been giving. And so the Biden administration's goal, while a good sign, also just for context of Bloomberg NEF. Didn't one of your colleagues call it a pipe dream? One of my colleagues did call it a pipe dream. And, you know, part of the reasons for that is because we've never once forecasted that the U.S.

28:51was going to meet this goal even before it came out. But it is a good sign for the industry just to kind of, you know, hammer that home. The ambition is good, but it doesn't look like it's realistic. And in our latest forecast, it looks more likely that it's going to be half of that. Wow. And for the Inflation Reduction Act, I think that the tax credits that are included in it are a very good sign. They help kind of decrease the price of offshore wind, onshore wind, onshore renewables in general, right? And so it becomes a more attractive space to certain investors, let's say. But offshore wind is one of the most expensive renewable energy technologies out there.

29:27And so when we take a look at why developers and countries are building it, it's not necessarily because it's the cheapest form of electricity. Offshore wind has super high capacity factors. And so what that means is that essentially if you take the entire year and assume a wind farm is generating at 100%, the wind speeds are ideal. Generation is at 100%. But then you actually take the actual generation. So, you know, sometimes wind is variable and wind speeds are lower and the turbines, you know, aren't spinning always at high speed all the time. There's some curtailment, perhaps. That percentage of the year, which it's like fully operational, is the capacity factor.

30:07And so for solar, where you might have a capacity factor like 20 percent, and that makes sense given that, you know, it's only really generating when the sun is out. Onshore wind, you might have something like 30 percent or so, 35 percent. Offshore wind in the U.S., you can get, you know, 40, 45 percent. And so it's a lot higher. And so when you're looking at renewable generation, as it gets more and more integrated into the grid, having higher capacity factors, you know, having technology which is able to generate a lot more is more beneficial for the system. And then also scale. So you have gigawatt scale projects that are offshore wind projects.

30:39You know, for context, you might see 100, 200 megawatt onshore wind project in the U.S., but that turns to 1 ,000, sometimes 2 ,000 megawatts when you go offshore. And so you have things like scale, higher capacity factors, also their huge economic development opportunities, really kind of being the driver for offshore wind more so than it is the price of that electricity. And so I think the IRA is great for, you know, taking the impact off, you know, the price of that electricity and the amount that like states are going to have to be paying and, you know, kind of putting that on the federal budget side of things.

31:14But in terms of actually spurring on that build and making it, you know, essentially being a driver for more offshore wind growth, I think that that's really lying more so with the states than it is with the federal government and the IRA. All right. That's why they built an investing platform for those who take it seriously. On Public, you can put together a multi-asset portfolio for the long haul. Stocks, bonds, options, crypto, it's all there. Plus an industry-leading 3.6 % APY, high-yield cash account. Switch to the platform built for those who take investing seriously. Go to public.com slash market and earn an uncapped 1 % bonus when you transfer your portfolio.

32:20That's public.com slash market. Paid for by Public Investing. All investing involves the risk of loss, including loss of principal. Brokered services for U.S.-listed registered securities, options, and bonds in a self-directed account are offered by Public Investing, Inc., member FINRA, and SIPC. Crypto trading provided by XeroHash. Complete disclosures available at public.com slash disclosures. When you own your own business, you own every decision. Now own the card that rewards you for it. The Chase Sapphire Reserve for Business card brings the best Sapphire Reserve benefits to business owners who expect hardworking rewards.

32:52Designed to meet the needs of business owners at scale, this Pay-in-Full card elevates your travel experience and offers premium benefits and value toward business services that can take your business to the next level. Sapphire Reserve for Business provides over$2 ,500 in annual value. Fuel your business and maximize rewards with 8x points on all purchases through Chase Travel, 3x points on social media and search engine advertising, annual partnership credits, and more. Make every journey more rewarding with a$300 annual travel credit and access to a network of airport lounges, whether you're looking for pre-flight productivity or time to rest and recharge.

33:31Chase Sapphire Reserve for Business. With over$2 ,500 in annual value, it's the car that gives back all you put in. Learn more at chase.com forward slash reserve business. Chase for Business. Make more of what's yours. Accounts subject to credit approval. Restrictions and limitations apply. Cards are issued by JPMorgan Chase Bank and a member FDIC. Just to hammer this point home, how much of the challenge here is the physics of wind power versus financial conditions, the increase in borrowing costs and the higher, you know, cost of physical components like labor, like ships, things like that. In other words, could there be an argument that unless those costs come down really significantly, that wind power just isn't, I guess, energy dense enough to make financial sense?

34:24That's a really interesting question. I think that one thing that's important to contextualize is that these things that we've been talking about in terms of inflation, interest rates, it's not just relegated to wind, right? Like we have been seeing this hit other renewable technologies. We've been seeing it hit other sectors. I know I go to the grocery store now and say, oh, my goodness, what? Like this has gone up by X amount. This is a ridiculous amount of money. Or now when, you know, you try to, you know, go for a loan. I think my parents were saying the other day that interest rates are crazy nowadays.

34:59And so this is something that's hit a lot of industries. And it's not necessarily just wind power. If we take a look at offshore wind in particular, I think that one of the reasons why we've been seeing so much news around it is because these are large infrastructure projects. You know, they're billions of dollars. The second one project says, you know, I can no longer develop, it's huge news because that's like a gigawatt of clean electricity versus, you know, if one solar project doesn't move forward, you know, maybe that's 50 megawatts and it's gone. So it's a smaller fraction. These are also, you know, huge government initiatives.

35:33So you might have government-backed contracts now being called into question versus, you know, if you have like a corporate bilateral PPA at a smaller scale, you know, that's a little bit easier to renegotiate, perhaps have a little more wiggle room. And so I think that a big portion of it is on, you know, the financing side of it and the macroeconomic situation that's impacting, you know, everything. But also if we take a look at wind and offshore wind in particular, there are some unique pieces to it that I think make it a little bit more susceptible to say, I'm trying to figure out the right words, but let's say grandioseness or like bigger news because they are larger projects.

36:14They are billions of dollars. They are huge when it comes to like amount, the amount of clean energy that you see it can contribute to countries, portfolios, but also from a company level as well. Right. We've seen a lot of oil and gas majors get into offshore wind. And it's because, you know, they've been starting to integrate, you know, renewable energy goals into their strategies. And offshore wind, you know, you win a huge seabed lease, a seabed lease auction, you get gigawatts immediately added to your clean energy portfolio. and so I think the bigness of the projects bigness is not a word but we'll go with it close enough to a word how expensive they are but also you know these longer timelines I think I mean I don't know about you guys but I'm a lot more upset when I've been working on something for a really really long time and it doesn't work out than you know when you've been working on it for you know a couple days Joe just admitted that he doesn't work on any long term projects I don't do long term projects so I completely agree I have one last question which is okay there are all these challenges from interest rates to statewide legal issues to the Jones Act, whatever.

37:17If things don't get figured out, how important is the wind component to overall clean energy goals? Especially, I know in the Northeast, we don't get a ton of sunlight. There aren't a ton of other alternatives for decarbonization. Just talk a little bit about the significance of somehow getting this right in terms of the U.S.'s bigger strategy? Yeah, I mean, I think it's huge. For context, our view at BNF is that this is more of a bump in the road than anything. So for years, we've seen cost declines, cost declines, cost declines, cost declines, especially in solar. And now's one of the first time in years where we've seen a little bit of a bump in costs.

37:56And so a lot of it in part is due to the inflationary pressures and higher costs of capital that we've been seeing. Now, we do think we're going to see a return to normal, whatever that means to you in the next few years. And so then we should come back to seeing some cost declines. And yes, there are bigger components. And I think that there are some structural issues that the industry needs to work out. I mentioned bigger turbines being like a huge push, a huge reason why we've seen cost declines in offshore wind. Then there's also the question of how big can those turbines get? Yeah, I saw like one of them or some of them are now like 350 feet or like 100 meters, something like that.

38:38I think in meters. Yeah. So the Vestas 15 megawatt turbine has a 236 meter rotor diameter. Oh, my gosh. Yes. They're really big. But yeah, as they get bigger, you need vessels that are going to be able to install them, ports that can house them, you know, factories that can manufacture them. The entire supply chain has to grow with it. And so there's some structural issues there that also need to be worked out. And turbine makers have differing strategies on whether or not it's better to keep going big or to, you know, kind of maintain it, you know, one turbine size. Now, that aside, in terms of like how important it is to your question, Joe, yeah, we can't necessarily just have an energy system that's made completely of solar panels, right?

39:18The sun's going to rise. You're going to have lots and lots and lots of solar energy. And then it's going to set. And then everyone's in a blackout. You know, that doesn't really make sense. Then you add storage. How many batteries can you add? You have wind, you want to have different sorts of electricity sources with differing profiles so that your system can be a little bit more flexible. You can be a little bit more nimble with, you know, moving your resources around so that you can actually go where demand is needed. So that includes investments in the grid, right, and making sure that that is upgraded to a point where electrons can flow a little bit more easily.

39:51And in the Northeast, as you mentioned, there's not a lot of sun. And it doesn't always make a whole bunch of sense to build solar, even if it might be, you know, cheaper on a levelized cost of electricity basis than onshore offshore wind. And so the big push in the northeast for offshore wind has to do with, you know, we see these really high electricity price spikes in the winter because, you know, gas due to gas constraints and high prices for gas. And so offshore wind kind of helps offset that a little bit more. So those kind of tie into some of the other benefits that I mentioned, not necessarily environmental attributes and economic benefits.

40:22But when you look at the electricity system as a whole and kind of trying to reduce, you know, those price spikes and price drops, offshore wind can kind of help add to it in that way. So there are benefits there that I think are good for the industry. And I think wind is a really big, necessary part of the energy transition. Chelsea, Jean-Michel, that was amazing. That answered so many questions. Really appreciate you coming on the podcast. No, for sure. Happy to be here. Thank you, guys. Yeah, that was great.

41:00Tracy, I thought that was great. That answered so many questions. And the fact that it ended up coming back around to being a Jones at episode two, it was like a classic interview from my perspective. We should have seen it coming. I didn't. I had no idea. I had no idea that was a big part of the story. Yeah. So there was so much packed into that. Chelsea got so much in. I'm struggling to think about where to start. So one thing I'm thinking is like, on the one hand, a lot of this sounds really complicated to solve. So these are huge infrastructure projects, as she laid out, working on very long timelines.

41:33And so you would imagine that the macro environment might change, you know, as the project actually matures and comes to fruition. But on the other hand, it does seem like there are some little things that could be kind of fixed almost immediately. So the idea of offtake contracts actually being indexed to inflation, I'm sure that would be a extremely politically unpopular move. But I guess if other countries are doing it, maybe you could make the argument. And if wind power is a necessary source of energy to get us to our carbon goals, like maybe there is some political appetite for making the projects more financially sound.

42:14but yeah it seems like it's complicated it seems like there are like multiple things happening here and multiple levers you could pull and the question is again like which are the most efficient and at the end of the day if you do all of them is wind power still efficient and financially viable yeah and you can see though too why even with all of these challenges from engineering to financing The prize is great, right? I think I saw some stand in one of the, all it takes is one spin of the blade, literally just one, and that powers multiple houses for a few days or something like that. And there's just so much potential energy out there a couple miles off the shore that you can see why there's this pursuit.

42:58But then also, there are so many different follow-up conversations that we can now have related to questions about, well, what is the optimal size of the blade or the optimal size of the turbine and all these different things that you could see or the optimal bidding process, as you described. Oh, yeah, that was really interesting. Also, like the idea, the renegotiation of the offtake agreements and the idea that like, obviously, the environment has changed. So if you're an energy provider, you might want to get additional revenue to cover your costs. But given the way those auctions are structured, you can't really do that in a fair way.

43:35Electricity markets future episodes for sure. Yeah. And probably a Jones Act debate in our future. Yes, for sure. All right. Shall we leave it there for now? Let's leave it there. Okay. This has been another episode of the All Thoughts podcast. I'm Traci Alloway. You can follow me at Traci Alloway. And I'm Jill Weisenthal. You can follow me at The Stalwart. Follow our producers, Carmen Rodriguez at CarmenArmin, Dashiell Bennett at Dashbot, and Kale Brooks at Kale Brooks. Thank you to our producer, Moses Andam. For more Odd Lots content, go to bloomberg.com slash oddlots, where we have a blog, transcripts, and a newsletter.

44:11It comes out every Friday. And if you want to chat with people about energy, one of the favorite places I go to check, Energy News, in the Discord. We actually have two channels that this is relevant to. We have a climate channel, Energy. People are chatting in there about these topics, 24-7, discord.gg slash oddlots. And if you enjoy Odd Lots, if you want us to hold that Jones Act debate, then please leave us a positive review on your favorite podcast platform. Thanks for listening.

45:13We'll see you next time.

45:29It means a half day. Yeah. Give it a try at mintmobile.com slash switch. Upfront payment of$45 for three month plan equivalent to$15 per month required. New customer offer for first three months only. Speed flow after 35 gigabytes of network's busy. Taxes and fees extra. See mintmobile.com. Look, Santa. The kids love you Pepperidge Farm cookies. Milano mint chocolate. So rich. Chessman butter cookies. So buttery. And Linza raspberry. A holiday classic. These are fancy Santa. Fancy Santa? Fancy Santa. Designer cologne? Spritz me! Vintage timepiece? Classy oak lock? Gold chain? Hmm. With diamonds?

46:06Now that's fancy. Pepperidge Farm Cookies. Fancy a taste?

From the publisher

The effort to decarbonize the US electricity grid involves a range of technologies and power sources. Solar is part of the solution, nuclear may also be a component. Battery storage is key. And so is wind — both onshore and offshore. While there are challenges throughout the process, the offshore wind industry in particular has seen a number of setbacks lately, with the Danish company Orsted having recently made headlines for pulling out of a project slated to be built off the coast of New Jersey. Challenges range from surging commodity costs to a scarcity of vessels, the bidding process for deals, and of course, the surge in interest rates over the last two years. On this episode, we speak with Chelsea Jean-Michel, an offshore wind industry analyst at BloombergNEF, to get a clear breakdown of the problems, the degree to which these challenges threaten the larger trajectory of the industry, and the efforts to decarbonize the grid.